1 / 13

Injector Scope, Management & Organization D. H. Dowell, SLAC Lehman Review August 10-12, 2004

Injector Scope, Management & Organization D. H. Dowell, SLAC Lehman Review August 10-12, 2004. Injector Performance Requirements Description of Scope of Work Injector Organization Budget Critical Path and Milestones Summary. LCLS Injector Performance Requirements: .

jessem
Download Presentation

Injector Scope, Management & Organization D. H. Dowell, SLAC Lehman Review August 10-12, 2004

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Injector Scope, Management & OrganizationD. H. Dowell, SLACLehman Review August 10-12, 2004 Injector Performance Requirements Description of Scope of Work Injector Organization Budget Critical Path and Milestones Summary

  2. LCLS Injector Performance Requirements: PRD 1.2-001 General System Requirements

  3. Injector Scope of Work • Build a 135 MeV Injector at Sector 20 • S20 Alcove Construction • Drive Laser • RF Gun • Accelerator Sections and Beamline • Power Conversion • Controls • Commission Injector • RF Conditioning • Drive Laser and Controls Integration • Beam Optimization

  4. RF Gun Load Lock L0-1 & L0-2 3-m SLAC Sections Gun Diagnostics Laser Heater Transverse RF Cavity DL1 Bend Straight Ahead Spectrometer LCLS Injector Configuration • Progress Since CD2a: • L0-1 Dual Feed RF Design Completed • 120 Hz Gun RF Design Nearly Complete • Laser Heater Added to Injector • =>Replacing SC Wiggler

  5. S20 Alcove Floor Plan • Title I Completed • Title II Specifications Released • Room & Utilities Sized for 2 Drive Lasers

  6. Injector Organization

  7. Budgeted Cost of Work Scheduled (BCWS) • FY04: PED and R&D • FY05: PED, R&D and Long Lead Procurements • FY06: Construction, Installation and Start of Commissioning • FY07 & FY08: End of Commissioning and Beginning of Operations

  8. FTEs • Ramp up to FY05 Levels in Progress (~14 FTE’s in July)

  9. July FTEs Shows Effort Concentrating on Long Lead Procurement

  10. Labor vs. M&S • Injector Construction (TEC) is a Near Equal Split Between Labor and M&S • OPC is Mostly Labor for Commissioning and R&D

  11. Critical Path Total Float = 289 days, 107 Days Float Before Beam on Linac Axis

  12. Level 3 Milestones

  13. Summary • Working to build a system which meets the performance goals • Injector at FTE level planned for FY04 • Increasing staff from internal & external sources for FY05 • Critical Path is low risk • Level 3 and 4 Milestones established

More Related