Learn to optimize network planning for successful project management in just 54 days - key activities A, C, E, H, I on critical path.
E N D
C(14) E(11) A(7) H(4) D(5) F(7) I(18) B(5.3) G(11) Example 2. Network ES=7 EF=21 ES=21 EF=32 Duration = 54 Days ES=0 EF=7 ES=32 EF=36 LS=7 LF=21 LS=21 LF=32 ES=7 EF=12 ES=12 EF=19 LS=0 LF=7 LS=32 LF=36 ES=36 EF=54 LS=20 LF=25 LS=25 LF=32 ES=0 EF=5.3 ES=5.3 EF=16.3 LS=36 LF=54 Critical Path: A-C-E-H-I LS=19.6 LF=25 LS=25 LF=36