1 / 30

P-981 Antimatter Gravity Experiment: Accelerator Augmentations and Civil Construction

P-981 Antimatter Gravity Experiment: Accelerator Augmentations and Civil Construction. Dr. Gerald P Jackson Hbar Technologies, LLC. gjackson@hbartech.com. Table of Contents. Main Injector deceleration (history, simulation, improvements)

jbuster
Download Presentation

P-981 Antimatter Gravity Experiment: Accelerator Augmentations and Civil Construction

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. P-981 Antimatter Gravity Experiment:Accelerator Augmentationsand Civil Construction Dr. Gerald P Jackson Hbar Technologies, LLC gjackson@hbartech.com

  2. Table of Contents • Main Injector deceleration (history, simulation, improvements) • Beam extraction from Main Injector (existing infrastructure) • New antiproton transfer line (in existing carrier pipe & penetrations) • Proposed experimental facility location and scope (new construction) • Proposed antiproton energy degrader and optics • Penning trap injection optics • Introduction to the NASA HiPAT penning trap • Conclusions • Informational slides (WBS cost structure and project scope details)

  3. Main Injector Deceleration • These deceleration studies occurred in 2000, consuming 8 parasitic accelerator study sessions and 27 hours. • A beam momentum of 3GeV/c was achieved without any accelerator hardware modifications. • Note the red RF glitches, and accompanying green beam intensity losses.

  4. Deceleration Efficiency RF Bucket Area Beam Intensity with RF Glitch There is a fix for this situation requiring simple LLRF electronics modifications Beam Intensity without RF Glitch Beam Momentum These simulation results agree very well with the experiment

  5. MI-10 Extraction The materials for the MI-8 xfer line switch magnet (2 GeV/c) have been purchased, and the laminations have been stacked. The stand needs to be finished and the coils wound. The finished magnet with stand is offered as an in-kind contribution from Hbar Technologies, LLC.

  6. MI Extraction Magnets & Lattice

  7. Antiproton Transfer Line Lattice design by David Johnson of FNAL for Hbar Tech

  8. Transfer Line Carrier Pipe Installed in 2001 for the speaker and paid for by private venture capital under a Work-for-Others Agreement

  9. Proposed Facility Location

  10. Preliminary Facility Design Design by FESS and Cost Estimate by Vic Kuchler of FNAL for Hbar Tech

  11. The degrader material has already been purchased by Hbar, and will be loaned to the experiment as an in-kind contribution. The blue spectrometer magnet must be built (parts already purchased) The wedge degrader must be built (not in cost estimate) Degrader Optics Antiproton Distribution after the Degrader Spectrometer Magnet

  12. Wedge Magnet Design

  13. Spot Size at Wedge Focal Point

  14. Foil Internal to the Pbar Trap Because the HiPAT trap only has a 20keV electrostatic barrier potential, this broad energy distribution imposes the dominant antiproton loss mechanism. The estimated survival fraction into HiPAT from 8 GeV is 5x10-4.

  15. NASA HiPAT Trap Hbar Tech is transporting this trap, along with its commissioning H- and H+ linacs and auxiliary cryo and vacuum hardware in the next months.

  16. Conclusions • For the full facility civil construction scenario, the total project cost for the facility plus beamline is estimated to be $6.9 million (see information slides). • For a stripped-down civil construction scenario in which a smaller underground enclosure is provided (along with power and water but no sewer), the total project cost for the facility plus beamline is estimated to be $3.9 million. • This facility not only serves the needs of the proposed antimatter gravity experiment, but during commissioning many small scale experiments aimed at atomic and nuclear physics, medicine, defense, homeland security, nuclear propulsion for NASA’s return to Mars, and advanced deep-space propulsion R&D can be performed.

  17. Scope and Cost Estimate • The following files document the proposed project scope and WBS-based cost estimate.

  18. Full Civil Construction Scenario

  19. Basement-Only Scenario

  20. Subsystem Cost Distribution

  21. Dipole List (2 GeV/c)

  22. Quadrupole List (2 GeV/c)

  23. Magnet Cost Estimate Given the nature of the beamline, no spares are needed and are not included in the cost estimate. If 1 GeV/c is the design momentum, permanent magnets are possible, which would reduce the project cost to $2.5 million (enclosure only scenario), down from $3.9 million.

  24. Vacuum System Cost Estimate Given the nature of the beamline, no spare ion pumps or gauges or their controllers are needed and are not included in the cost estimate.

  25. Beam InstrumentationCost Estimate

  26. Power Supplies and CablesCost Estimate

  27. Controls Cost Estimate

  28. Safety Systems Cost Estimate

  29. Other Labor Costs with FringeCost Estimate

  30. Overhead & Contingency

More Related