An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BUAD306 Chapter 17 – Project Management

  2. Life is a Project • You are already a project manager! • Work-related projects • Organizational/club projects • Sport-related activities • Event planning

  3. Types of Projects • Doesn’t matter the size, must be cost effectively and in timely manner: • Corporate - Mergers, systems conversions, relocations, new business ventures, new products, start—ups… • Department - Quality improvement, work-flow modifications, new technology/ equipment, automation, new products…

  4. Project Plan • The roadmap for your project • Designates who does what, when, where • Shows sequence of activities and schedule of when they occur • Analyzed regularly (daily) to identify issues and gauge timeliness of project • “How” is determined by team members! • Conveying the “why” is critical to the Project manager’s job!

  5. Gantt Charts • Visual display of project tasks • Specific tasks • Timeframe to complete • Sequence • Assignments of Responsibility • Pros/Cons • Simple, easy to create • Doesn’t show interdependencies

  6. WK1 WK2 WK3 WK4 WK5 WK6 WK7 WK8 WK9 WK10 Gantt Chart Gantt Chart Paint Develop Floor Plan Buy Furniture, etc. Hang fixtures Install lighting Arrange Furniture Display Inventory Open Store

  7. PERT and CPM • PERT – Program Evaluation and Review Technique • CPM – Critical Path Method • Together, Project Managers can do the following: • See a graphical display of activities • Estimate length of project • Identify tasks most critical to completion • Determine how long any activity can be delayed without delaying the project

  8. 1 2 3 Network Diagram Network consists of branches & nodes Node Branch Predecessor Activity

  9. Network Conventions (AOA) a b c a c b c a a c Dummy activity b b d

  10. Project Network Hang Fixtures 4 Display Inventory/ Goods 2 Paint Install Lighting 1 6 5 OPEN START Arrange Furniture Develop Floor Plan Buy Furniture 3

  11. Critical Path • A path is a sequence of connected activities running from start to end node in network • The critical path is the path with the longest duration in the network • Project cannot be completed in less than the time of the critical path

  12. Slack • Represents time available for getting a path completed as compared to the critical path • is the “wiggle room” you have on that path

  13. 3 weeks 4 3 weeks 2 4 weeks 5 weeks 1 5 6 2 weeks 2 weeks 9 weeks 3 Find the Critical Path & Slack

  14. Example 1 D E F A C H B G

  15. Example 2 D C A B G H E F *Max you can crash any activity is one week *For each week crashed, can earn $2500

  16. Expediting Your Project? • Why? • Save $ • Make $ • Improve customer satisfaction • Government requirements • Other non-financial benefits?

  17. Crashing • Use of additional resources, which typically cost money, to shorten the original length of the overall project • Conditions: • Activity crashed must be on the critical path(s) • Benefit of crashing must outweigh the cost of crashing

  18. 3 weeks 4 3 weeks 2 4 weeks 5 weeks 1 5 6 2 weeks 2 weeks 9 weeks 3 Should We Crash? Can earn $700 for each week opened early $500/week; maximum = 1 $500/week; maximum = 3

  19. 3 weeks 4 3 weeks 2 4 weeks 5 weeks 1 5 6 2 weeks 2 weeks 9 weeks 3 Should We Crash? Can earn $700 for each week opened early What if $100/week; maximum = 1 $500/week; maximum = 3

  20. Example 2 – Part 2 D C A B G H E F *Max you can crash any activity is one week *For each week crashed, can earn $2500

  21. Example 3 E D H J A B C G F I *Max you can crash any activity is one week *For each week crashed, can earn $2000

  22. Handout #1: • Given the project diagram below and the table of info: • Calculate the critical path and slacks • If the company wants to shorten the project by 3 weeks and spend no more than $5,000, is it possible? Assume no task can be crashed more than twice. Explain • Using original data: if activity D is delayed by 5 weeks, is there a delay in the entire project? If so, by how much? C A B D H E F G

  23. Handout #2: • Given the project diagram below and the table of info: • Calculate the critical path and slacks • The company has crash costs as shown (costs are listed for 1st week crash and 2nd week. If no cost shown, it cannot be crashed). The company would like to crash the project by 4 weeks. How much will it cost to do this and what tasks will be crashed and by how much? B C E G A I J H D F

  24. Handout #2: - ALTERNATIVE!!!!!!!!!! • Given the project diagram below and the table of info: • Calculate the critical path and slacks • The company has crash costs as shown (costs are listed for 1st week crash and 2nd week. If no cost shown, it cannot be crashed). The company would like to crash the project by 4 weeks. How much will it cost to do this and what tasks will be crashed and by how much? B C E G A I J H D F

  25. Handout #3: • Given the project diagram below and the table of info: • Calculate the critical path and slacks • If task D were to slip by 4 weeks, would there be a delay in the project? If so, by how much? • Given the original info, the company must complete the project in 20 weeks or else be fined $2000 for each week beyond 20. Is it possible for the company to complete the project and NOT be fined? If so, how would they do so? B F D A I C E H G

  26. Microsoft Project • Powerful business tool • Easily entry and organization of project tasks • PERT/CPM flexibility • Standard project communications • Custom reporting

  27. Risk Management • Types of Risks • Project Risks – overall project • Task Risks – individual components • Decision Risks – strategic • Cost Benefit Analysis Read Text

  28. Key Project Tasks • Project Designation • Project Manager Selection • Project Team Designation • Project Planning • Managing Resources/Activities • Issues Management • Communication • Post-Mortem/Analysis

  29. Project Manager • Ultimately responsible for success/ failure of project • Manages: work effort, resources, communications, quality, timetables, and costs • Requires strategic management, “juggling” & prioritization skills, etc. • Can be certified (PMI)

  30. Project Management Issues • Time Considerations • Quality Factors • Conflicts of Interest • Limited Resources • Perception within Organization • STRESS! So why do it???