Status of the TOFs Inti Lehmann University of Glasgow 27 June 2011
Work done in May • All scintillators • detached • re-aligned • secured with new brackets • Short flasher fibres attached • Modules moved to Doris • Framing done • Subframes moved into main frame • All!? 34 TOF modules installed OLYMPUS TOF Status 27/06/2011
May2011 OLYMPUS TOF Status 27/06/2011
Misalignment realised • Observed effect • Chambers > TOF 17 • Gap from target • Huge mismatch: 10-25cm • TOF CAD • On-site (Michael) • Explanation • Unsynchronised changes in CAD • Solution • Move group 3 (modifying brackets, add. support) • Add TOFs #18 (add. cables, short by 1 in flasher) OLYMPUS TOF Status 27/06/2011
Not beautiful but... OLYMPUS TOF Status 27/06/2011
Status and to-do • 34 TOFs in place • 2 TOFs in preparation • Hardware to extend frames expected on Thu • 72 HV cables and 70 signal cables labelled • Require ordering more signal cables • Route cables to hut • 72 mu-metal shields ready • Mounting on top may prove difficult • 7 (possibly) loose PMTs • Re-attachment started • Flasher work • Light-coupler, electronics, route • Tests OLYMPUS TOF Status 27/06/2011
Mismatch OLYMPUS TOF Status 27/06/2011