GEO-NRG Project

GEO-NRG Project. Adrovicz Áron Soós S zabolcs Vető Benjamin. The blocks of flats. It was built in 1973 It was a normal blockhouse 256 flat 1000 people It was heated by normal central heating but it had very great loss of heat 25.320 GJ/year. The first steps. 2007-7446 GJ/year

jamescastro
Download Presentation

GEO-NRG Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. GEO-NRGProject Adrovicz Áron Soós Szabolcs Vető Benjamin

  2. The blocks of flats • It was built in 1973 • It was a normal blockhouse • 256 flat • 1000 people • It was heated by normal central heating but it had very great loss of heat • 25.320 GJ/year

  3. The firststeps • 2007-7446 GJ/year • 120 million Ft invested • They couldn’t save money becouse the prices have grown by time • „Főtáv” conferancia • 1998-block of flats has own cenral heating • 25.320 GJ/year -25%=18.996 GJ • 45 Celsius • In 2000 they started 8 project

  4. GEO-NRG • They begin to plan in 2008 • 2009.06.01 heating is started to work • First time just warm water • 2009. october heating • No airconditionar • 60-70 Celsius • -15% heat loss • 2010-6097 GJ/year • It cost’s160 million Ft • They begin to put Fenkor radiators into the flats

  5. Howdoesitwork?

  6. Chateaud’Yquem El Corte Ingles Disneyland in Tokyo LaDefense

  7. Kreml Vatican Telenor

  8. Thank’s foryourattention!