An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ASM Phase IIReserve Constraint Penalty Factors rev1.0 NEPOOL Markets Committee May 23, 2005 Jim Milligan ISO-NE Markets Development

  2. Outline • Proposed Reserve Constraint Penalty Factors • Use of RCPFs • Dispatch Solutions • Example • Reserve Shortages

  3. Proposed Reserve Constraint Penalty Factors

  4. Derivation of RCPFs • RCPFs have been established to be consistent with operational requirements and practices of power system. • RCPFs reflect the costs the ISO would be willing to incur to procure reserves given the $1000/MW Energy Cap. • RCPFs will replace the existing Reserve Shortage Condition Pricing Rule as defined in Market Rule 1. • RCPFs will provide mechanism to reflect reserve shortages in stages for system and locational requirements.

  5. Use of RCPFs • RCPFs have two functional uses under ASM Phase II: • Allows the real time dispatch algorithm to achieve a feasible solution when a Reserve Constraint cannot be satisfied, • Determines a real time Reserve Clearing Price (by product and location) when a Reserve Constraint cannot be satisfied.

  6. Dispatch Feasibility • The real time dispatch algorithm will include system reserve requirements for TMSR, TMNSR and TMOR and local reserve requirements for TMOR for each Reserve Zone • The real time reserve requirements (system and locational) will be calculated based on real time conditions and will be inputs to the dispatch

  7. Dispatch Feasibility (cont) • Additional Dispatch Rules: • Unused MWs of higher quality reserves will be available to meet lower quality reserve requirements • Lower quality Reserve Clearing Prices will cascade upward to higher quality Reserve Clearing Prices • Reserve capability of on-line Resources will be computed based on either 10*MRR or 30*MRR from DDP constrained by EcoMax using MRR at DDP. • Reserve capability of off-line Resources will be computed based on CLAIM10/30 Offer data constrained by EcoMax.

  8. Dispatch Feasibility (cont) • Objective function of real time dispatch will be to minimize the cost of meeting all constraints from available Resources. • Constraints include: • Nodal/system energy balance, • Resource specific constraints (limits, MRR, etc.) • Transmission constraints (branch, interface, etc.) • System/local reserve requirements

  9. Dispatch Feasibility (cont) • RCPFs will be set equal to values as specified. • When a reserve constraint cannot be satisfied with available resources, the constraint will bind in the dispatch solution, and the RCPF will act “conceptually” as a reserve resource with infinite MW and a price equal to the RCPF. • This “concept” will allow the dispatch algorithm to arrive at a feasible solution.

  10. Locational Example of RCPFs • Initial conditions: Actual EcoMin EcoMax Energy MRR Reserve • GenA 25 25 100 $70 1 30 • GenB 80 50 100 $50 5 20 • GenC 0 5 25 $150 C10=25 25 • GenD 0 5 25 $200 C30=25 25 GenA and GenB committed, Local Reserve Req’t = 100 MW Interface Limit =200MW, Interface Flow=150MW Local Load = 255 System LMP = $50, Reserve Prices = $0

  11. Conditions at t=0 Local Load = 255 Reserve Zone System GenA 25 R=30 GenB 80 R=20 GenC 0 R=25 GenD 0 R=25 Load 255 L Res = 150 Local LMP $50 L RCP = $0 System LMP = $50 System RCPs = $0 Limit = 200 Actual = 150

  12. Conditions at t=1 Local Load = 300 Reserve Zone System GenA 25 R=30 GenB 100 R=0 GenC 0 R=25 GenD 0 R=25 Load = 300 L Res = 105 Local LMP = $55 L RCP = $0 System LMP = $55 System RCPs = $0 Limit = 200 Actual = 175 Energy Balance is satisfied Local Reserve Req’t is satisfied

  13. Conditions at t=2 Local Load = 310 Reserve Zone System GenA 30 R=30 GenB 100 R=0 GenC 0 R=25 GenD 0 R=25 Load = 310 L Res = 100 Local LMP = $70 L RCP = $15 System LMP = $55 System RCPs = $0 Limit = 200 Actual = 180 Energy Balance is satisfied Local Reserve Req’t is satisfied Re-dispatch of Interface – similar to Gen opportunity cost

  14. Conditions at t=3 Local Load = 351 Reserve Zone System GenA 70 R=30 GenB 100 R=0 GenC 0 R=25 GenD 0 R=25 Load = 351 L Res = 99 Local LMP = $105 L RCP = $50 System LMP = $55 System RCPs = $0 Limit = 200 Actual = 181 Energy Balance is satisfied Local Reserve Req’t is violated

  15. Conditions at t=4 Local Load = 371 Reserve Zone System GenA 71 R=29 GenB 100 R=0 GenC 0 R=25 GenD 0 R=25 Load = 371 L Res = 79 Local LMP = $120 L RCP = $50 System LMP = $55 System RCPs = $0 Limit = 200 Actual = 200 Energy Balance is satisfied Local Reserve Req’t is violated

  16. Reserve Shortages • Previous example shows local reserve shortage and use of local RCPF • Similar concept employed for system reserve shortages • Typical condition would begin with a shortage of TMOR followed by shortage of TMNSR, and in extreme cases, a shortage of TMSR. • Under this scenario, system TMOR RCPF would bind first followed by system TMNSR RCPF and finally system TMSR RCPF

  17. Reserve Shortages (cont) • Frequency of System Reserve Shortages • Reference: Analysis of Historical Reserve Shortages White Paper • Historical analysis indicates that the Control Area has experienced a deficiency in Operating Reserves (TMOR) in real time approximately 0.26% of time. • Of the total Number of deficient conditions (24), five resulted in a deficiency of TMNSR, and of the five, three may have resulted in a deficiency of TMSR.

  18. Reserve Shortages (cont) • Historical information does not exist to perform similar analysis of locational reserve shortage conditions. The ISO is continuing to investigate the feasibility of producing such an analysis.

  19. Discussion and Questions