1. Risk Management For Projects with Pertmaster
Erum Abbas Naqvi
SLIDE OBJECTIVE: Start of introduction
Add location
Add date
SLIDE OBJECTIVE: Start of introduction
Add location
Add date
2. Agenda
What is Pertmaster and who are the people behind it?
Project Risk Management concepts
Introductory Demonstrations
Importing from Primavera and MS Project
Quick Risk Templates
Running a Risk Analysis
Advanced Risk Management
Using a Risk Register with your schedule
Schedule cost loading techniques
Probabilistic cashflow and profitability breakeven
Weather Modelling
Summary & Q&A
3. Primavera Pertmaster Closed loop RM
We can also work with MSP and Open PlanClosed loop RM
We can also work with MSP and Open Plan
4. Pertmaster Overview Enterprise Project Risk Management
Capital investment analysis
Portfolio risk exposure
Cost/Schedule/Bid analysis
Contingency/mitigation planning
What if scenario modeling
Risk Techniques
Schedule improvement: PPM maturity
Risk Impact assessment: Risk Register
Risk Analysis Engine: Monte Carlo simulation
Full Lifecycle Risk management
Portfolio risk– strategic project selection
Project risk– tactical project controls/PM
Integration
PV P3, P3e, P5, Suretrak
MS Project, EPM, Deltek
6. Project Intelligence Arena ‘We understand time related data’
The butler group coined this phrase, Pertmaster is decision related = Pertmaster is analytics and modelling
Pertmaster + risk helps understand EV looking forwards
Strategic/Investment modelling (production levels)
‘We understand time related data’
The butler group coined this phrase, Pertmaster is decision related = Pertmaster is analytics and modelling
Pertmaster + risk helps understand EV looking forwards
Strategic/Investment modelling (production levels)
7. Monte Carlo Simulation
8. Pertmaster Risk Analysis Methodology Risk Ready state
Schedule: sound logic
Scheduling errors
Risk Inputs
Estimate uncertainty: “Quick Risk”
Risk Events: risk register
Risk Impacts
Map risks to tasks
Risk Analysis
Monte Carlo simulation
Risk hot spots
Risk Response
Determination of contingency
Mitigation scenarios
Probabilistic cashflow
9. Plan Validation: Schedule Check
10. Types of Risk Estimate uncertainty
11. Initial Risk Inputs 3 pt estimates/ triangular + “Quick Risk” analysis
12. Types of Risk Task Existence
13. Types of Risk Branching
Probabilistic & Conditional
14. Accuracy with Ease!
15. Risk Events Model impact of risk events
Generate a “risk event plan” Import from XLS, CSV, Sharepoint
Compare pre/post mitigated plans
Have you ever heard or said these statements yourself? These are actual quotes by people just like you who are dealing with this issue. “ My Project Managers are too optimistic”
“ Every week my PMs tell me everything is fine”, “People hide problems from me”, “By the time I find out about it, its too late”, “Reports just tell me what happened in the past”. Wouldn’t it be so much better that whether it’s one project or many, you’ll have accurate trends and forecasts to avoid surprises?
[Stop. Get conformation. If they are not with you here, keep working it until they are. Let them put this pain in their own words so that they own it. The more they own it, the more that this pain will become a driving reason to purchase the software and services].Have you ever heard or said these statements yourself? These are actual quotes by people just like you who are dealing with this issue. “ My Project Managers are too optimistic”
“ Every week my PMs tell me everything is fine”, “People hide problems from me”, “By the time I find out about it, its too late”, “Reports just tell me what happened in the past”. Wouldn’t it be so much better that whether it’s one project or many, you’ll have accurate trends and forecasts to avoid surprises?
[Stop. Get conformation. If they are not with you here, keep working it until they are. Let them put this pain in their own words so that they own it. The more they own it, the more that this pain will become a driving reason to purchase the software and services].
16. Risk Outputs Determine key risk drivers
Risk Hot Spots
Cost & schedule
Risk Histogram: “risk status”
Risk Tornado: “how to fix it”
Contingency + mitigation
17. With Pertmaster, you can chart the differences between your deterministic cumulative cash flow and your risk-adjusted cash flow over time. This produces the envelope you see on the slide here, providing a more intelligent guideline for controlling costs within your projects and programs.
In addition, the bars behind the Probabilistic Cash Flow envelop are showing us areas where we are potentially under funding and over funding certain parts of our project or program over time; based on the risk analyzed data.With Pertmaster, you can chart the differences between your deterministic cumulative cash flow and your risk-adjusted cash flow over time. This produces the envelope you see on the slide here, providing a more intelligent guideline for controlling costs within your projects and programs.
In addition, the bars behind the Probabilistic Cash Flow envelop are showing us areas where we are potentially under funding and over funding certain parts of our project or program over time; based on the risk analyzed data.
18. Case Study