1 / 23

Architectural Engineering Construction Management Senior Thesis April 11 th , 2011

Architectural Engineering Construction Management Senior Thesis April 11 th , 2011 Consultant: Dr. Riley. Architectural Engineering Spring 2011 – Senior Thesis. Diab Shetayh. Project Overview Project Team Overview of Analyses Analysis 1 – LEED Certification Analysis 2 – Brick Façade

ishi
Download Presentation

Architectural Engineering Construction Management Senior Thesis April 11 th , 2011

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Architectural Engineering Construction Management Senior Thesis April 11th, 2011 Consultant: Dr. Riley Architectural Engineering Spring 2011 – Senior Thesis Diab Shetayh

  2. Project Overview • Project Team • Overview of Analyses • Analysis 1 – LEED Certification • Analysis 2 – Brick Façade • Mechanical Breadth • Analysis 3 – BIM Coordination • Conclusion • Acknowledgements • Questions Architectural Engineering Construction Management Senior Thesis April 11th, 2011 Consultant: Dr. Riley Presentation outline Architectural Engineering Spring 2011 – Senior Thesis Diab Shetayh

  3. Project Title: Function: Location: Building Size: Project Cost: Date of Construction: Delivery Method: Paint Branch High School Education Burtonsville, MD 349,000 SF $ 80,973,293 12/15/2009 – July 30, 2013 Modified CM @ Risk • Presentation Outline: • Project Overview • Project Team • Overview of Analyses • Analysis 1 – LEED Certification • Analysis 2 – Brick Façade • Mechanical Breadth • Analysis 3 – BIM Coordination • Conclusion • Acknowledgments • Questions Project Overview Architectural Engineering Spring 2011 – Senior Thesis Diab Shetayh

  4. PB Phase Diagram • Presentation Outline: • Project Overview • Project Team • Overview of Analyses • Analysis 1 – LEED Certification • Analysis 2 – Brick Façade • Mechanical Breadth • Analysis 3 – BIM Coordination • Conclusion • Acknowledgments • Questions • Phase 1: • Construction of the new facility • Substantial completion date: June 1, 2012 Project Overview • Phase 2: • Reconfigure Parking lots for staff & Students • Substantial completion date: August 19, 2011 Phase 2 Phase 3 Phase 1 • Phase 3: • Abatement & demolition of old facility • Substantial completion date: July 30, 2013 Architectural Engineering Spring 2011 – Senior Thesis Diab Shetayh

  5. Project Team Owner: Architect: Construction Manager: Civil Engineer MEP Engineer: Structural Engineers: Montgomery County Public Schools (MCPS) Moseley Architects HESS Construction + Engineering Services ADTEK Engineers B2E Consulting Engineers Wolfman & Associates • Presentation Outline: • Project Overview • Project Team • Overview of Analyses • Analysis 1 – LEED Certification • Analysis 2 – Brick Façade • Mechanical Breadth • Analysis 3 – BIM Coordination • Conclusion • Acknowledgments • Questions Project Team Architectural Engineering Spring 2011 – Senior Thesis Diab Shetayh

  6. Analysis 1: LEED Certification • Reviewing LEED scorecard for opportunities • Analyzing opportunities for additional costs • Analysis 2: Brick Façade • Cost & Schedule impact to project • Mechanical Breadth • Structural Breadth • Analysis 3: BIM Coordination • Reviewing clash detection logs and case studies • Determine cost and schedule savings to project • Presentation Outline: • Project Overview • Project Team • Overview of Analyses • Analysis 1 – LEED Certification • Analysis 2 – Brick Façade • Mechanical Breadth • Analysis 3 – BIM Coordination • Conclusion • Acknowledgements • Questions Overview of Analyses Architectural Engineering Spring 2011 – Senior Thesis Diab Shetayh

  7. Green Schools Statistics • Daylight: • with brighter learning environments, test scores increase by 25% • Ability to learn 20-25% faster on standardized tests • Presentation Outline: • Project Overview • Project Team • Overview of Analyses • Analysis 1 – LEED Certification • Analysis 2 – Brick Façade • Mechanical Breadth • Analysis 3 – BIM Coordination • Conclusion • Acknowledgements • Questions Analysis 1 – LEED Certification • Problem: • State of the art High School • LEED Gold Certified (43 Points) • Air Quality: • Children miss 10 million school days a year due to asthma • Poor air quality can cause mold growth and disease to spread • Research Goals/Methodology: • Review LEED scorecard for opportunities • Achieve LEED Platinum Certification (52 Points) • Acoustics: • Students score up to 20% higher on word recognition tests • Poor acoustics cause distraction, which affects a students ability to learn LEED Version 2.2 Architectural Engineering Spring 2011 – Senior Thesis Architectural Engineering Spring 2011 – Senior Thesis Diab Shetayh Diab Shetayh

  8. Sustainable Sites • Credit 7.1 – Heat Island Effect, Non-Roof • Placed 50% of parking under canopy • Energy & Atmosphere • Credit 2.1 – On-Site Renewable Energy • Incorporated Wind Turbine on site • Credit 4 – Enhanced Refrigerant Management • Changed refrigerant to R134A • Credit 5 – Measurement & verification • Third Party to establish plan • Indoor Environmental Quality • Credit 1 - Outdoor Air Delivery Monitoring • Incorporated CO2 monitoring Systems • Credit 5 - Indoor Chemical & Pollutant Source Control • Proposed entry grates at all major entrances • Credit 7.1 - Thermal Comfort, Design • Heating & Cooling loads to be calculated by ME • Presentation Outline: • Project Overview • Project Team • Overview of Analyses • Analysis 1 – LEED Certification • Analysis 2 – Brick Façade • Mechanical Breadth • Analysis 3 – BIM Coordination • Conclusion • Acknowledgements • Questions LEED Scorecard Architectural Engineering Spring 2011 – Senior Thesis Diab Shetayh

  9. Presentation Outline: • Project Overview • Project Team • Overview of Analyses • Analysis 1 – LEED Certification • Analysis 2 – Brick Façade • Mechanical Breadth • Analysis 3 – BIM Coordination • Conclusion • Acknowledgements • Questions • Requirements: • 50% of parking spaces under deck/roof • Material used must have a Solar Reflectance Index (SRI)2 of at least 29 Credit 7.1 – Heat Island Effect, Non-Roof Total Parking spaces: 355 Total Parking Spaces Required: 178 Total Parking Spaces Under Canopy: 188 = Single cantilever System = Double Cantilever System Architectural Engineering Spring 2011 – Senior Thesis Diab Shetayh

  10. Presentation Outline: • Project Overview • Project Team • Overview of Analyses • Analysis 1 – LEED Certification • Analysis 2 – Brick Façade • Mechanical Breadth • Analysis 3 – BIM Coordination • Conclusion • Acknowledgements • Questions Credit 7.1 – Cost Analysis = Single cantilever System = Double Cantilever System Architectural Engineering Spring 2011 – Senior Thesis Diab Shetayh

  11. Analysis 1 Conclusion • Presentation Outline: • Project Overview • Project Team • Overview of Analyses • Analysis 1 – LEED Certification • Analysis 2 – Brick Façade • Mechanical Breadth • Analysis 3 – BIM Coordination • Conclusion • Acknowledgements • Questions Advantages: Disadvantages: Complete Cost Analysis • Savings in operating Costs • High Upfront Cost • Increased Test Scores • Cleaner learning Environment Architectural Engineering Spring 2011 – Senior Thesis Diab Shetayh

  12. Presentation Outline: • Project Overview • Project Team • Overview of Analyses • Analysis 1 – LEED Certification • Analysis 2 – Brick Façade • Mechanical Breadth • Analysis 3 – BIM Coordination • Conclusion • Acknowledgements • Questions • Problem: • Congested site • Façade is primarily face brick Analysis 2 – Brick Façade • Research Goals/Methodology: • Contacting Prefab. Manufacturers • Determine cost & Schedule impact with new system • Proposed System: • 1” face Brick • 3.5” Polyurethane • 4” Steel Stud • 5/8” Gypsum Board • 1” Membrane (2) • ½” Fiberboard • Current System: • 4” face brick • 1” Air Space • 2” Rigid Insulation • 10” CMU Architectural Engineering Spring 2011 – Senior Thesis Diab Shetayh

  13. Total SF of Brick: 108,000 SF • Presentation Outline: • Project Overview • Project Team • Overview of Analyses • Analysis 1 – LEED Certification • Analysis 2 – Brick Façade • Mechanical Breadth • Analysis 3 – BIM Coordination • Conclusion • Acknowledgements • Questions Calculations Prefab. Panel Size: 12’ X 40’ = 480 SF Total Number of Panels Needed: 225 Panels • Proposed System: • 1” face Brick • 3.5” Polyurethane • 4” Steel Stud • 5/8” Gypsum Board • 1” Membrane (2) • ½” Fiberboard Panels Installed Per day : 8-15 panels (5 man crew) • Current System: • 4” face brick • 1” Air Space • 2” Rigid Insulation • 10” CMU Architectural Engineering Spring 2011 – Senior Thesis Diab Shetayh Architectural Engineering Spring 2011 – Senior Thesis Diab Shetayh

  14. Analysis 2 Conclusion • Presentation Outline: • Project Overview • Project Team • Overview of Analyses • Analysis 1 – LEED Certification • Analysis 2 – Brick Façade • Mechanical Breadth • Analysis 3 – BIM Coordination • Conclusion • Acknowledgements • Questions Advantages: Disadvantages: Façade Comparison • Decrease in Project Schedule • More Expensive System • Minimize Site Congestion • Better quality Schedule Savings: 139 Days – 19 Days = 120 Days (6 Months) Additional Cost: $4,320,000 - $2,226,960 = $2,093,040 Architectural Engineering Spring 2011 – Senior Thesis Diab Shetayh

  15. Wall Sections Comparison in R –values and U-values Calculate each systems heat transfer Conduct cost analysis between both systems • Presentation Outline: • Project Overview • Project Team • Overview of Analyses • Analysis 1 – LEED Certification • Analysis 2 – Brick Façade • Mechanical Breadth • Analysis 3 – BIM Coordination • Conclusion • Acknowledgements • Questions Mechanical Breadth • Current System: • 4” face brick • 1” Air Space • 2” Rigid Insulation • 10” CMU • Proposed System: • 1” face Brick • 3.5” Polyurethane • 4” Steel Stud • 5/8” Gypsum Board • 1” Membrane (2) • ½” Fiberboard Proposed System Current System Architectural Engineering Spring 2011 – Senior Thesis Diab Shetayh

  16. Proposed Façade • Presentation Outline: • Project Overview • Project Team • Overview of Analyses • Analysis 1 – LEED Certification • Analysis 2 – Brick Façade • Mechanical Breadth • Analysis 3 – BIM Coordination • Conclusion • Acknowledgements • Questions Current Façade Architectural Engineering Spring 2011 – Senior Thesis Diab Shetayh

  17. Cost ANALYSIS • Alternative Interior Finish: • Changed CMU finish to Gypsum wall board • Changed Rigid insulation to Polyurethane • Presentation Outline: • Project Overview • Project Team • Overview of Analyses • Analysis 1 – LEED Certification • Analysis 2 – Brick Façade • Mechanical Breadth • Analysis 3 – BIM Coordination • Conclusion • Acknowledgements • Questions Cost ANALYSIS Architectural Engineering Spring 2011 – Senior Thesis Diab Shetayh

  18. Presentation Outline: • Project Overview • Project Team • Overview of Analyses • Analysis 1 – LEED Certification • Analysis 2 – Brick Façade • Mechanical Breadth • Analysis 3 – BIM Coordination • Conclusion • Acknowledgements • Questions Analysis 3 – BIM Coordination Architectural Engineering Spring 2011 – Senior Thesis Diab Shetayh

  19. Presentation Outline: • Project Overview • Project Team • Overview of Analyses • Analysis 1 – LEED Certification • Analysis 2 – Brick Façade • Mechanical Breadth • Analysis 3 – BIM Coordination • Conclusion • Acknowledgements • Questions Architectural Engineering Spring 2011 – Senior Thesis Diab Shetayh Architectural Engineering Spring 2011 – Senior Thesis Diab Shetayh

  20. Presentation Outline: • Project Overview • Project Team • Overview of Analyses • Analysis 1 – LEED Certification • Analysis 2 – Brick Façade • Mechanical Breadth • Analysis 3 – BIM Coordination • Conclusion • Acknowledgements • Questions Architectural Engineering Spring 2011 – Senior Thesis Diab Shetayh Architectural Engineering Spring 2011 – Senior Thesis Diab Shetayh

  21. Analysis 1: • Achieved LEED Platinum Certification • Total Additional Cost - $968,859 • Presentation Outline: • Project Overview • Project Team • Overview of Analyses • Analysis 1 – LEED Certification • Analysis 2 – Brick Façade • Mechanical Breadth • Analysis 3 – BIM Coordination • Conclusion • Acknowledgements • Questions Conclusion • Analysis 2: • Additional Cost w/ Prefab System - $2,093,040 • Savings in project schedule – 6 months Architectural Engineering Spring 2011 – Senior Thesis Architectural Engineering Spring 2011 – Senior Thesis Diab Shetayh Diab Shetayh

  22. Acknowledgements • Academic Acknowledgements: • Dr. Riley – CM Advisor • Dr. Robert Leicht • Dr. John Messner • Penn State AE faculty • Presentation Outline: • Project Overview • Project Team • Overview of Analyses • Analysis 1 – LEED Certification • Analysis 2 – Brick Façade • Mechanical Breadth • Analysis 3 – BIM Coordination • Conclusion • Acknowledgements • Questions Acknowledgements • Special Thanks To: • Matt Evans (HESS Construction) • Saurabh Gangwar (Hess Construction) • George Houke (HESS Construction) • Paint branch Project Team Architectural Engineering Spring 2011 – Senior Thesis Diab Shetayh

  23. Presentation Outline: • Project Overview • Project Team • Overview of Analyses • Analysis 1 – LEED Certification • Analysis 2 – Brick Façade • Mechanical Breadth • Analysis 3 – BIM Coordination • Conclusion • Acknowledgements • Questions Questions? Questions? Architectural Engineering Spring 2011 – Senior Thesis Diab Shetayh

More Related