An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Contract Choice and Product Quality Outcomes in Outsourcing:Empirical Evidence from Software Development Sandra Slaughter Donald E. Harter Soon Ang Jonathan Whitaker American University

  2. Software Quality • Problem • In April, a software glitch resulted in the loss of thousands of dollars for US Airways Group Inc. when some tickets were mistakenly priced at $1.86. (ComputerWorld 7/25/05) • A software bug apparently caused the largest power outage in North America, the Northeast blackout of August 2003, which threw millions of people into darkness (ComputerWorld 7/25/05) • Flawed software cost the U.S. economy $60 billion in 2002 (NIST 2002) American University

  3. Research Motivation • Solutions • Process maturity is key to higher quality, lower costs, shorter development time • Harter, Krishnan, Slaughter, Management Science 2000 • Questions remain: • How to encourage higher quality? • Research question • Can contract selection be a vehicle to encourage software quality? • If so, what factors drive contract selection? American University

  4. Contract Selection • Contract theory & agency theory • Choice of contract structure is crucial to ensure that agent’s goals are aligned with principal (Crocker & Reynolds, 1993; Grossman & Hart, 1983; Milgrom & Roberts, 1992) • Issues: • Hidden information leads to adverse selection • Information asymmetry leads to moral hazard • Type of contract can serve as an effective governance mechanism American University

  5. Information Asymmetry • Sources of information asymmetry • uncertainty in product specifications and uncertainty about the vendor’s ability to develop quality products • Artz and Norman 2002 • Stump and Heide 1996 • Kalnins and Mayer 2004 • High uncertainty increases costs of writing specific contract terms American University

  6. Specification Uncertainty Design Complexity Prior Contracting Experience Software Process Maturity Research Model Uncertainty of Product Specifications: H1, H2 Contract Choice Time & Material, Hybrid, Fixed Price Verification & Validation Quality H5a, H5b Uncertainty of Vendor Quality: H3, H4 American University

  7. Product Uncertainty • Issues • Client requirements can be ambiguous (Nidumolu 1995) • Software products are innovations and innovations embody uncertainties (Ang & Beath 1993) • Software development is frequently exploratory (MacCormack 2001) • Client understanding is evolutionary (Richmond 1992) • Hypothesis • H1: Time & Materials contracts more likely when specification uncertainty is high American University

  8. Product Complexity • Issues • Complex designs are more difficult to develop (Brooks 1995) • Effort required for testing complex designs is highly variable (Banker 2002) • Higher software complexity increases technical risk (Barki 1993) • Development cost estimation is more uncertain • Hypothesis • H2: Time & Materials contracts more likely when design complexity is high American University

  9. Vendor Uncertainty • Issues • Inability to determine vendor quality can create problems of adverse selection and moral hazard (Artz & Norman 2002) • Repeated interaction and long-term relationships mitigate adverse selection and moral hazard (Baker 1994) • Repeated transactions provide incentives that decrease likelihood of opportunism (MacNeil 1978; Granovetter 1985) • Corts & Singh (2004) • Repeated interactions reduce contracting costs, leading to fixed price • Interaction reduces opportunism, leading to time & material • Variance of these costs affects contract choice (Kalnins & Mayer 2004) • Hypothesis • H3: Hybrid contracts more likely when contracting experience between vendor and client is low American University

  10. Vendor Uncertainty • Issues • Adverse selection can be addressed using signals designed to reveal private information (Milgrom & Roberts 1992; Mishra 1998) • Qualification process can identify vendors with necessary skills (Stump & Heide 1996) • Process maturity can be used to signal quality (Arora & Asundi 1999) • Hypothesis • H4: Fixed price contracts more likely when software process maturity is high American University

  11. Effect of Contract Choiceon Quality Outcomes • Issues • Opportunity for ex post opportunism by both parties (Williamson 1979) • Vendor has financial incentive to freeze the specification in fixed price contract • Incentives are to develop the software right the first time, according to the specification • Clients may change are articulate new requirements as they discover what they truly need • Vendor profits from new requirements under Time & Materials, and may accommodate client’s requirements • Hypotheses • H5a: Fixed price contracts have higher development and production verification quality • H5b: Time & Materials contracts have higher acceptance validation quality American University

  12. Research Site &Data Collection • Data collected on software projects developed from 1987 to 2004 • 78 contracts were negotiated • 26 time and material • 38 fixed price • 14 hybrid American University

  13. Contract Types • Time & Material • Vendor reimbursed through hourly rate • Technical and financial risks on client • Fixed Price • Vendor agrees to fixed contract value • Technical and financial risks on vendor • Costly to negotiate – requires detailed specifications ex ante • Hybrid • Agreement on cost estimate, but client pays all costs; profit based on initial estimate and performance • Financial risk primarily on client American University

  14. Measures • Contract choice • Categorical variables • 1-T&M, 2-hybrid, 3-Fixed price • Quality • Verification (development & production) – technical issues of whether the software has been developed correctly and performs correctly • Validation (acceptance) – whether the right software has been developed that satisfies the users • Antecedents of contract choice • Specification uncertainty • Design complexity • Prior contracting experience • Software process maturity • Controls • Product size American University

  15. Regression Models: Choice • Stage 1: Contract Choice • multinomial regression using Newton-Raphson maximum likelihood estimation • Prob(yi=j) = e jXi / Σe kXi • Corrections • Non-independence of disturbances across different contract segments • Huber (1967)/White (1982) sandwich estimator • Results • Antecedents significant in predicting choice (p<.001) • Explain significant variance (pseudo R2 = 0.751) • Correlation between predicted and actual contract is 88.5% American University

  16. Uncertainty & Complexity Likelihood of Contract Choice Given Levels of Specification Uncertainty Likelihood of Contract Choice Given Levels of Design Complexity American University

  17. Hypotheses Summary • H1: Time & Materials preferred over fixed price for higher levels of specification uncertainty • 66% likelihood for high specification uncertainty • 10% likelihood for low specification uncertainty • H2: Time & Materials preferred over fixed price and hybrid when there is higher design complexity • 71% likelihood for high design complexity • 8% likelihood for low design complexity American University

  18. Experience & Process Likelihood of Contract Choice Given Levels of Prior Contracting Experience Likelihood of Contract Choice Given Levels of Software Process Maturity American University

  19. Hypotheses Summary • H3: hybrid contracts preferred over fixed price when prior contracting experience is lower • 84% likelihood of hybrid for low experience • 88% likelihood of fixed price for high experience • H4: fixed price preferred for higher levels of process maturity American University

  20. Regression Models: Quality • Stage 2: Quality Outcomes of Contract Choice • Multivariate general linear modeling (GLM) • Two-step multinomial selection bias correction method of Lee (1983) • Models • Development Verification Quality = f(Contract-Choice, Specification-Uncertainty, Design-Complexity, Prior-Contracting-Experience, Software-Process-Maturity, Product-Size) • Production Verification Quality = f(Contract-Choice, Specification-Uncertainty, Design-Complexity, Prior-Contracting-Experience, Software-Process-Maturity, Product-Size) • Acceptance Validation Quality = f(Contract-Choice, Specification-Uncertainty, Design-Complexity, Prior-Contracting-Experience, Software-Process-Maturity, Product-Size) • Results • Hotelling’s T2 test of contract choice significant (p<.001) • Post hoc calculation of power is 0.97 American University

  21. Quality Outcomes American University

  22. Discussion • Information asymmetry arising from product uncertainties (specification uncertainty and design complexity) shifts contract choice to Time & Material • Uncertainty of vendor quality is a strong motivator of contract choice • Vendor quality (30.2%) explains eight times the variance of product uncertainty (3.7%) American University

  23. Discussion • Prior contracting experience is a critical mitigator of information asymmetry • Hybrid contracts more likely when experience between client and vendor is low • Reducing contracting and shirking costs • Vendor quality certification explains highest variance in contract choice (20%) • Quality certification engenders greater confidence in the vendor’s abilities to estimate and deliver software products to specifications American University