-9 AFT Recovery. Layouts (13) Final Due by EOY – X Total X are supported by current staffing X resource help needed for systems/ducting Approved Due by EOY – X Total X are supported by current staffing X resource help needed for doors X held for Engineering. -9 AFT Recovery.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about '-9 AFT Recovery' - inga


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
9 aft recovery
-9 AFT Recovery
  • Layouts (13)
    • Final Due by EOY – X Total
      • X are supported by current staffing
      • Xresource help needed for systems/ducting
    • Approved Due by EOY – X Total
      • X are supported by current staffing
      • X resource help needed for doors
      • X held for Engineering
9 aft recovery1
-9 AFT Recovery
  • ME Review/Signoffs (109)
    • Structures
      • 0 are due by EOY
      • X are complete and need to updated in Everett tracking log
      • X will close with current staffing
        • X have been reviewed and waiting on pickup feedback from DE
      • X have/will missed red line date
      • X resource help needed
sow for immediate help needed
SOW for Immediate Help Needed

Need 2 MEs familiar with door surrounds to assist with these layouts and ME Review/Signoffs

sow for immediate help needed cont d
SOW for Immediate Help Needed, cont’d

Need 1 ME (familiar with frame installation preferred) to assist with these OPF ME Review/Signoffs until LCPT can get mobilized to take on this work.

immediate help needed
Immediate Help Needed
  • Need total of x immediately to support current release schedule
    • x to support door surrounds (Andrew Wildrick)
    • x to support OPFs (Ed Pylant, Abe Ortiz)