1 / 19

Chapter No 3 Project Scope and Estimation of Times and Cost

Chapter No 3 Project Scope and Estimation of Times and Cost.

Download Presentation

Chapter No 3 Project Scope and Estimation of Times and Cost

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Chapter No 3Project Scope and Estimation of Times and Cost

  2. IntroductionProject Management is usually always about meeting the issues in the magic triangle: scope, time and cost.If one of the goals is missed or wrongly planned, the project's success usually can only be achieved by reallocation of more resources, which costs money and/or will take more time. Planning is the key to careful overview and balances these three parallel goals.Project Kick-Off Meeting“The first team meeting sets the tone for how the team will work together. If it is disorganized, or becomes bogged down with little sense of closure, then this can often become a self-fulfilling prophecy for subsequent group work. On the other hand, if it is crisply run, focusing on real issues and concerns in an honest and straightforward manner, members come away excited about being part of the project team.”

  3. There are three typical objectives project managers try to achieve during the first meeting of the project team. The first is to provide an overview of the project, including the scope and objectives, the general schedule, methods and procedures. It is important to establish basic rules as guidelines for the upcoming work. The second is to begin to address some of the interpersonal concerns captured in the team development model: 1.Who are the other team members? 2.How will I fit in? 3.Will I be able to work with these people?The third and most important objective is to begin to model how the team is going to work together to complete the project. The project manager will recognize and evaluate for the first time the behavior of the team members. This can be critical, especially in intercultural teams where often different kinds of behaviors and personalities can be observed, which can have a high potential to collide.

  4. Project Scope ManagementProject scope is a precise explanation of the expected result of the project in a specific, tangible, and measurable way. Scope describes what one expects to deliver to the customer when the project is complete. Due to the high priority of the project scope, a checklist should contain the following elements:1. Project objective 2. Deliverables 3. Milestones 4. Technical requirements 5. Limits and exclusions 6. Reviews with customer

  5. 1. Project objective Objectives describe “the what it is” you’re trying to do, accomplish, or produce. If your objectives is to increase warehouse space, it would be better to say the objectives is to build four new warehouses. Objectives always involve the triple constraints: time, cost, and quality. In case of objectives, the triple constraints are used as measurements to determine project satisfaction and completion. 2. Deliverables Deliverables are measurable outcomes, measurable results, or specific items that must be produced to consider the project or project phase completed. 3. Milestones The milestone schedule shows only major segments of work. It represents first, rough cut estimates of time, cost and resources for the project. The milestone schedule is built using the deliverables, as a platform to identify major segments of work and an end-date.

  6. 4. The technical requirements The technical requirements have to ensure the proper performance. For example, a technical requirement for a project with a university library could be that a student can be identified with his Computer IP-Address if he logs in into an internal database, to enable the university to track down any misuse. The importance of technical requirements is obvious because such a malfunction on a project could cause enormous damage. 5. The limits and exclusions The limits and exclusions should be well defined. Failure can lead to false expectations and to expending resources and time on the wrong problem. 6. Review with customer The completion of the scope checklist ends with a review with the customer. The objective is the common understanding and agreement of expectations. • Is the customer getting what he or she desires in deliverables? • Does the project definition identify key accomplishments, budgets, timing, and performance requirements? • Are questions of limits and exclusions covered?

  7. Estimation of Project Cost: The question that’s forever on the mind of the executive management staff: How much is it going to cost? The purpose of the Cost Estimating process is to answer that question. Every project has a budget, and part of completing a project successfully is completing it within the approved budget. Cost Estimating has five tools and techniques used to derive estimates: Analogous Estimating, Parametric Modeling, Bottom-up Estimating and Computerized Tools Cost Estimating Methods. We’ll look at each of these next. Analogous Estimating: With this technique, you will use the actual cost of a similar activity completed on a previous project to determine the cost of the current activity. Remember that analogous estimating is a form of expert judgment and it is a less accurate technique.

  8. Parametric Modeling: The idea here is to find a parameter, or multiple parameters, that changes proportionately with project costs and then plug that into the model to come up with a total project cost. For example, we might know from past experience that it costs $275 per square foot to build an office building. The $275 becomes the parameter that we use in the parametric model to come up with an estimate of total project cost. Bottom-up Estimating: The bottom-up estimating technique you will estimate every activity or work item individually and then roll up that estimate, or add them all together, to come up with a total project estimate. This is a very accurate means of estimating, provided the estimates at the work package level are accurate. However, it takes a considerable amount of time to perform bottom-up estimating as every work package must be assessed and estimated accurately to be included in the bottom-up calculation. Computerized Tools: Project management software can be a useful tool in Cost Estimating as are spreadsheet programs. Using software can make the job of Cost Estimating easy and fast.

  9. Time Estimating Techniques: Estimating the duration of project activities involves identifying the activities and sequencing them in the correct order. Then, time estimates are assigned as baseline measurements and used to track project activities to ensure the project is completed on time. Activity Definition Process The Activity Definition process is a further breakdown of the work package elements of the WBS. In practice, many times Activity Definition might be accomplished during the construction of the WBS, and the activities themselves are the work package level. This process produces an output called an activity list, which is an extension of the WBS. The activity list should contain all the activities of the project with a description of each activity so that team members understand what the work is and how it is to be completed. Once the activity list is completed, the WBS might need to be updated.

  10. Activity Sequencing Process: We’ve identified the activities and now need to sequence them in a logical order and find out if dependencies exist among the activities. For example. Let’s say you’re going to paint your house, but unfortunately, it’s fallen into a little disrepair. The old paint is peeling and chipping and will need to be scraped before a coat of primer can be sprayed on the house. After the primer dries, then the painting can commence. In this example, the primer activity depends on the scraping. Important techniques for developing activity sequencing process are; Mandatory Dependencies: Mandatory dependencies, also known as hard logic or hard dependencies, are defined by the type of work being performed. The scraping, primer, painting sequences are examples of mandatory dependencies. The nature of the work itself dictates the order the activities should be performed in.

  11. Discretionary Dependencies: Discretionary dependencies are delineated by the project management team. Discretionary dependencies are also known as preferred logic ,soft logic , or preferential logic . These are usually process or procedure driven, or “best practices” techniques based on past experience. For example, past experience on house-painting projects has shown that all slim work should be hand painted while the bulk of the main painting work should be done with a sprayer. External Dependencies External dependencies are, well, external to the project. The weather forecast might be an external dependency in the painting example because you wouldn’t want to start painting prior to a rain storm.

  12. Precedence Diagramming Method (PDM) The precedence diagramming method (PDM)is what most project management software programs use today. Precedence diagrams connect activities with arrows that show dependencies between the activities. This method is also called activity on node (AON). The activity information is written on the nodes with arrows connecting the nodes, or dependent activities. The nodes are shown as rectangles, and the minimum information that should be displayed on the node is the activity name. The example below shows a PDM, or AON, of the house-painting example. Arrow Diagramming Method (ADM) The arrow diagramming method (ADM) is visually the opposite of the PDM. The arrow diagramming method places activities on the arrows, which are connected to dependent activities with nodes. This method is also called activity on arrow (AOA) Project Start Prime Paint Scrap Finish Scrap Prime Start Finish Paint

  13. Estimating Activity Durations: The Activity Duration Estimating process takes the activities defined in the WBS and activity list and assesses the number of work periods needed to complete these activities. Work periods are usually expressed in hours or days. However, larger projects might express duration in weeks or months. Activity Duration Estimating is performed using the following tools and techniques. Expert Judgment: Activities are most accurately estimated by the staff members who will perform the activities. In this case, expert judgment is used by team members because of their experience with similar activities in the past. You should be careful with these estimates, though, as they are subject to bias and aren’t based on any scientific means. It’s good practice to combine expert judgment with historical information and use as many experts as you can.

  14. Qualitatively Based Durations: Suppose you are working on a company-wide network upgrade project. This requires you to run new cable to the switches on every floor in the building. suppose we have 10,000 meters of new cable to run. We know from past experience it takes 1 hour to install 100 meters. Using this measurement, we can make a qualitatively based estimate for this activity of 100 hours to run the new cable. Therefore, the cable activity duration estimate is 100 hours. Reserve Time (Contingency): Reserve time, also called buffer or contingency time means adding a portion of time to the activity to account for schedule risk. You might choose to add a percentage of time or a set number of work periods to the activity or the overall schedule. For example, we know it will take 100 hours to run new cable based on the qualitative estimate we came up with earlier. We also know that sometimes we hit problem areas when running the cable. To make sure we don’t impact the project schedule, we build in a reserve time of 10 percent of our original estimate to account for the problems we might encounter. This brings our activity duration estimate to 110 hours for this activity.

  15. Activity Resource Estimating (ARE) Activity resource estimating (ARE) is closely related and coordinated with the cost estimating process. The schedule for activity resource estimating involves determining what resources (staff, equipment, or material) and in what quantity each resource is needed. Inputs for the estimation are in general: Activity List: The activity list identifies the schedule activities for resources that are estimated. Activity Attributes: The activity attributes provide the primary data input for use in estimating those resources required for each schedule in the activity list. Resource availability: Information on which resources are potentially available is used for estimating the resource types. This knowledge includes consideration of various geographical locations from which the resources originate and when they may be available.

  16. Major tools and techniques for such an Activity Resource Estimating (ARE) are: • Any group or person with specialized knowledge in resource planning and estimating can provide such expertise • An alternatives analysis which includes such thoughts as, for instance, make or buys, hand versus automated, different size or type of machine • Published estimating data which are routinely published by various companies, e.g. on production rates and unit costs of resources for an extensive display of labor trades, equipment for different countries and geographical locations within countries • PM-Software, that helps planning, organizing, and managing resource pools and develops resource estimates • Bottom-up estimation which is used when a scheduled activity cannot be estimated with a reasonable degree of confidence, whereby the work within the scheduled activity is decomposed in more detail. The output of the activity resource estimating process is an identification and description of the types and quantities of resources required for each scheduled activity in a work package.

  17. Resource Calendar: A composite resource calendar for the project documents working days and non-working days that determine those dates on which a specific resource, whether a person or equipment, can be active or is idle. The resource calendar typically identifies resource-specific holidays and resource availability periods. Request Changes: The activity resource estimating process can result in request changes to add or delete planned scheduled activities within the activity list.

  18. Project Communication Plan (PCP): Communication is a key component in coordinating and tracking project schedules, issues, and action times. The PCP is a fundamental part of the overall project plan because it maps out the flow of information to all different stakeholders in a project. When developing a PCP the following points should be considered: 1.Stakeholder analysis: Identifies the target groups. Typical groups could be the customer, sponsor, project team, or anyone who needs project information in order to make decisions and/or contribute to the project processes. 2.Information needs: What information is important for whom? For example, top management needs to know how the project is progressing, whether it is encountering critical problems and the extent to which project goals are being realized. This information is required so that they can make strategic decisions and manage the portfolio of projects. Furthermore, team members need to see schedules, task lists and specifications, so that they know what needs to be done next.

  19. 3.Sources of information: When the information needs are identified, the next step is to determine the sources of information. Information can be collected using milestone reports, team meetings, and project status meetings. 4.Distribution modes: One of the most common distribution channels in modern companies is e-mailing. There are of course other methods through which information can be distributed, for example through teleconferencing, Lotus Notes, SharePoint and a variety of database sharing programs. Project management software is used by companies to transfer information directly to the Web site so that different people have can immediate access to relevant project information. In some cases it is a standardized routine that important information is transferred directly to key stakeholders. 5.Responsibility and timing: Determine who will send out the information. For example, a common practice is to have minutes of meetings or specific information forwardarded to the appropriate stakeholders. Other centres of know-how can be the project manager. Timing and frequency of allocation appropriate to the information needs to be established.

More Related