LSWT#4. Open Cruise Requirements status and planning. LSWT#4, Venice 30/03-01/04-2009. SCrOP Annex_G - PC10. Active Payload Checkout PC10: Regular tests for active checkouts ESS RAM Patch Test for ESS events Finalize SW Upload for Lander Units, Part 2 of 2: SW Upload for SESAME

ince
Download Presentation

Open Cruise Requirements status and planning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LSWT#4 Open Cruise Requirements statusand planning LSWT#4, Venice 30/03-01/04-2009

  2. SCrOP Annex_G - PC10 • Active Payload Checkout PC10: • Regular tests for active checkouts • ESS RAM Patch Test for ESS events • Finalize SW Upload for Lander Units, Part 2 of 2: • SW Upload for SESAME • SW Patch for ADS (tbc) • + COSAC SW Upload • + CIVA SW Upload • + APXS parameter setting, re-run PC8 test All units SW shall be final after PC10. This does not apply for CDMS: • SW8.0 upload PC12 • Lander internal Interference Tests (Part 1) • On-comet Preparation tests, Part 1 • New requirements from • PTOLEMY to finalize activities (substitute existing requirement) • CONSERT tests on switch-ON accuracy

  3. SCrOP Annex_G - PC12 • Active Payload Checkout PC12: • CDMS SW Upload to V8.0 • Battery charge to 100% prior DSH • Regular tests for active checkouts • Contingency activities, if needed • S-D-L combined tests(mainly driven by Flywheel S-D-L operations) • Lander Internal Interference Tests, Part 2 • On-comet Preparation tests, Part 2(MUPUS, CONSERT) ANCHOR, COSAC, PTOLEMY, CONSERT

  4. Cruise Phase Events 2009 • Passive PC9 Jan 2009  • PC9 execution -> Jan 2009 • Rosetta Thermal Characterization  • Test execution -> Feb-2009 • Active PC10 • High level inputs to ESA  -> Feb 2009 • Start of GRM campaign -> May 2009 • End of GRM campaign -> July 2009 • LOR delivery -> Aug 2009 • GO/NOGO -> 03-Sep-2009 • PC10 execution -> 21-Sep to 02-Oct 2009 • ESB3 (no Philae activities) • High level inputs to ESA  -> Feb 2009 • ESB3 CA -> 13-Nov-2009

  5. Cruise Phase Events 2009/2010 • In-flight Power System Test (PSS, MPPT, SBatt) • High level inputs to RMOC -> Nov 2009 (tbc) • End of GRM campaign -> Jan 2010 (tbc) • LOR delivery -> Feb 2010 (tbc) • PST execution -> February 2010 • CDMS SW V8.0 verification • Start -> September 2009 • End -> Nov 2009 • Active PC12 • High level inputs to ESA -> Oct 2009 • End of GRM campaign -> Feb 2010 • LOR delivery -> Mar 2010 • GO/NOGO -> Apr 2010 • PC12 execution -> April/May 2010

  6. Cruise Phase Events 2009/2010 • Lutetia • High level inputs to ESA -> March 2009 • End of GRM campaign -> Apr 2010 • LOR delivery -> May 2010 • GO/NOGO -> June 2010 • LUT CA -> 10-July-2010 • Passive PC13 =>Last payload activity prior DSH!!! • PC Change Req. to ESA -> Sep 2010 • LOR delivery -> Oct 2010 • GO/NOGO -> Nov 2010 • PC13 execution -> Dec 2010

  7. Cruise - OPS Preparation Schedule 2009 • PC10 EQM Test RMOC -> April 2009 • PC10 Start of GRM campgn -> May 2009 • PC10 End of GRM campgn -> July 2009 • PC10 LOR delivery -> Aug 2009 • PC10 GO/NOGO -> 03-Sep-2009 • CDMS SW8.0 Test Start -> September 2009 • PC10 execution -> 21-Sep to 02-Oct 2009 • PC12 First Inputs to ESA -> Oct 2009 • PST Inputs to RMOC -> Nov 2009 (tbc) • PC12 SCrOP + timeline -> Nov 2009 (tbc) • CDMS SW8.0 Test End -> Nov 2009

  8. Cruise - OPS Preparation Schedule 2010 • PST GRM campgn -> Jan 2010 (tbc) • PST LOR delivery -> Feb 2010 (tbc) • PST execution -> February 2010 • PC12 End of GRM campgn -> Feb 2010 • PC12 LOR delivery -> Mar 2010 • PC12 GO/NOGO -> Apr 2010 • LUT End of GRM campgn -> Apr 2010 • PC12 execution -> April/May 2010 • LUT LOR delivery -> May 2010 • LUT GO/NOGO -> June 2010 • LUT CA -> 10-July-2010 • PC13 Change Req. to ESA -> Sep 2010 • PC13 LOR delivery -> Oct 2010 • PC13 GO/NOGO -> Nov 2010 • PC13 execution -> Dec 2010

  9. Longterm planning • Deep Space Hibernation Phase (DSH) • Start DSH July 2011 • End DSH January 2014 • Payload Commissioning Period April/May 2014Limited Resources !!! (Power/Data) • Comet Phase Start August 2014 • Global Mapping 18-Aug to 21-Sep 2014 • Close Observation 22-Sep to 19-Oct 2014 • Lander Delivery Period Start October 2014 • Lander Delivery 11-Nov-2014 • Lander Baseline Mission 12 to 16- Nov2014 • Comet Escort Phase • Start Escort Phase 17-Nov-2014 • Perihelion 13-Aug-2015 • End Escort Phase 31-Dec-2015

  10. Open NCR Status • Total of 28 open NCRs to units FM model: • APXS (1) ->PC10 ADS (2) ->PC10 • CIVA (3/1*) ->PC10 Battery* (1) • CONSERT (2) ->PC10 CDMS (10) ->PC12 • COSAC (1) ->PC10 ESS* (2) • PTOLEMY (1) ->PC10 PSS* (3) • ROMAP* (2) Last review based on dedicated emails and LOWG#12 presentations (*) further clarification required