State of the Project SHARELIFE Delft, April 29th 2008 (Mathis Schröder)

Loading in 2 Seconds...

play fullscreen
1 / 19

State of the Project SHARELIFE Delft, April 29th 2008 (Mathis Schröder) - PowerPoint PPT Presentation


  • 72 Views
  • Uploaded on

State of the Project SHARELIFE Delft, April 29th 2008 (Mathis Schröder). Agenda. Timeline: detailed schedule Translation and Certification Country pilot feedback Country pilot results. Tasks and Timetable (from March 2007). Phase 1: First Pre-Test by December 2007

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'State of the Project SHARELIFE Delft, April 29th 2008 (Mathis Schröder)' - ilar


Download Now An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
slide1

State of the ProjectSHARELIFE

Delft, April 29th 2008

(Mathis Schröder)

agenda
Agenda
  • Timeline: detailed schedule
  • Translation and Certification
  • Country pilot feedback
  • Country pilot results
tasks and timetable from march 2007
Tasks and Timetable(from March 2007)
  • Phase 1: First Pre-Test by December 2007

First survey draft: finished in July 2007

Programming: finished in September 2007

1st pilot : finished successfully in September/October 2007

2nd pilot: not in the field in January 2008, “in-house” testing

  • Phase 2: Main Survey ready by November 2008

survey revision and translation for country pilots: March 2008

country pre-testing: July 2008

  • Phase 3: “First Results” by December 2009

data collection finished: June 2009

cleaning and first evaluation: November 2009

timeline pre test
Timeline – Pre-Test
  • Translations (LMU open):
    • Version 3.5 (changes from pilot): May 2nd to May 9th
    • Version 3.6 (pre-test version): May 16th to May 23rd
  • SMS/CAPI versions scheduled release:
    • Version 3.5 (generic): May 6th

-> feedback until May 12th

    • Version 3.5 (country): May 16th (Translation!)
    • Version 3.6 (generic): May 16th
    • Version 3.6 (country): May 30th (Translation!)
  • SMS Server:
    • First version released May 9th
    • Final generic version May 16th
timeline pre test1
Timeline – Pre-Test
  • Fieldwork material:
    • SRC prepares
    • To be delivered by May 13th
  • Preload database:
    • Prepared by MEA by May 16th
    • Checked by Agencies until pre-test starts in June
  • TTT:
    • Server SMS: May 19th, Frankfurt Airport, 10:30-16:00
    • Make sure Survey Agencies know!
    • May 27th-29th in Mannheim
timeline pre test2
Timeline – Pre-Test
  • Pre-Test Field Duration:
    • National Training Sessions (NTS) from June 2nd to 13th
    • Deliver Data by July 18th (50 days after TTT)
  • After the pre-test…
    • Evaluation of pre-test results in August
    • Edesheim 21./22.8.
    • Translate the changes to final version
  • TTT September 23rd – 26th in Mannheim
  • Main Field Duration:
    • Start in October/November 2008
    • Be finished by March/April 2009
adaptation
Adaptation
  • Certification
    • Done externally by cApStAn
    • Received a subset of the translated questions
    • Evaluate adaptations using the generic questionnaire
    • 14 Items in the first round, for all countries
    • Based on first round results, second round with 11 Items
    • 5 out of 10 versions went into second round
    • Overall, some flaws were found, some questioning the comparability of the questions across countries
  • For the LMU 3.5, each country will receive the results of the certification separately tomorrow (4-30)
pilot feedback
Pilot - Feedback
  • Thanks to all CTLs for providing feedback!
  • The interviewer feedback is mainly positive
    • Interview enjoyable
    • Almost no technical breakdowns
    • Flexible modules order was not used
    • Corrections were made via the calendar
    • The search tool is not used…
length summary
Length Summary
  • We are overall OK in terms of time
  • What happened in Denmark?
  • Some quick stats: 2% > 2.5 h 4% > 2 h 15% > 1.5 h 26% < 45 min 3% < 30 min
  • But: still add CV and Grip Strength
and what now
And what now…?
  • Cuts or changes have already been made in the…
    • AC module: moves starting at age 10
    • RE module: some questions out, clarified others (ISCO)
    • HS module: deleted some questions, combined others
    • HC module: major cuts in the loops for preventive care
    • RC module: cut the stillbirths and abortion loop
    • RP module: improved the marriage section
  • Addition in the GL-module on persecution
    • Thanks to Radim and Michal for pointing this out
    • One general filter and then some follow up questions