Overview of IG UCTE Accounting

Overview of IG UCTE Accounting. Appendix 2 for the IG UCTE Accounting Version 1.0; Released by ENTSO-E RGCE WG Op&Sec 30. November 2009. Overview of IG UCTE Accounting. Agenda Provided documents

honey
Download Presentation

Overview of IG UCTE Accounting

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Overview of IG UCTE Accounting Appendix 2 for the IG UCTE Accounting Version 1.0; Released by ENTSO-E RGCE WG Op&Sec 30. November 2009

  2. Overview of IG UCTE Accounting • Agenda • Provided documents • Overview UCTE Accounting and Settlement process • Meter Measurement Data synchronization • Matching of Accounting Point Data • UCTE Settlement Report

  3. Provided documents • Phases covered by the IG UCTE Accounting: The Implementation Guide UCTE Accounting cowers the following 3 phases • Establishment of Accounting Point Relevant data • Matching of Accounting Point Data • Issuing of UCTE Settlement results Each of these phases is managed by a different document as following: • For the establishment of Accounting Point Relevant data • ”Measurement Value Document” (MVD) • For the matching of Accounting Point data • ”Energy Account Report” (EAR) • For issue of UCTE Settlement results • ”UCTE Settlement Report” (USR)

  4. Description of documents • The UCTE Accounting and Settlement process is based on the following documents • 1. Measurement Value Document (MVD) • used for the verification of Accounting Point Relevant data on meter data level: message types SOMA and (SOVM: only for internal use, no data exchange with neighboring TS0) • Identification of Accounting Point Relevant data by 10T-Code for tie-lines, (identification of optional additional meter data by local 10Z-Code for meters) • 2. Energy Account Report (EAR) • used for the matching of the Accounting Point data on accounting data level:message type SOAM for matching between TSO and SOVA for agreed values for exchange via Publication Framework • Identification of Accounting Point data by official 10Z-Code for accounting point • 3. UCTE Settlement Report (USR) • used for the information of the UCTE Parties about the Settlement results:message types CBSR and CASR • Identification of Accounting Point data by official 10Z-Code for accounting point

  5. Overview • UCTE Accounting and Settlement pyramid

  6. Process overview The UCTE Accounting and Settlement pyramid

  7. EAR doc Process overview MVD doc USD doc The UCTE Accounting and Settlement pyramid

  8. Meter Measurement Data synchronisation

  9. Meter Measurement Data synchronisation

  10. Establishment of Accounting Point Relevant data • Process: • The neighbouring TSO agree on the Accounting Point per Tie-Line (Accounting point located in a Substation or on the border) • If the accounting point is on the border both TSO have to agree on how to calculated the flow on the border • Also they agree on the Meter Measurement Data set be exchanged and validated in the Accounting Point Relevant Data synchronization process • Then the TSO exchange the set of Meter Measurement Data by help of the SOMA file. Once both TSO have received a positive Ack. the data are synchronized and provided in file SOVM. • SOMA and SOVM files are ”Measurement Value Document” (MVD) documents

  11. Use of Meter Measurement data in MVD document Identified by an EIC Z Code Identified by an EIC T Code

  12. Matching of UCTE Accounting Point Data

  13. UCTE Accounting process overview diagram

  14. Matching of UCTE Accounting Point Data • Process: • Once the SOVM document, containing the synchronized Accounting Point Relevant Data is received, the TSO calculate (consideration of tie-line losses) the Accounting Point Data. • As next one of the two TSO prepares the EAR based SOAM document and send it to the neighbour who will release a positive ACK if the Accounting Point Data match with his data. • Than the Accounting Point Data are made available on the UCTE Publication Framework (UPF) by both TSO by delivery of the EAR based SOVA document. • The final step is the verification of the Accounting Point Data by the concerned UCTE body (Control Area, Control Block and Coordination Centre). There for they download the data from the (UPF) and check if they are consistend.

  15. Sequence diagram UCTE Accounting process

  16. Sequence diagram UCTE Accounting process

  17. UCTE Settlement Report

  18. UCTE Settlement Report • Process: • Once the Accounting Point data are agreed the UCTE Settlement is performed and the results are made available on the UCTE Publication Framework. • The UCTE Settlement Process goes from top of UCTE Pyramid to its bottom. • As first the Settlement is performed for the coordination Centres and when agreed the calculation for the control blocks is executed. The result are provided to the control blocks by help of the UCTE Publication Framework. • Then the control block operator calculates by help of the UCTE Settlement reports, provided by the CC’s, the UCTE Settlement Reports for the Control Area and provide them also by the UCTE Publication Framework. • One distinguish between “daily” and “weekly” Settlement Report. Depending on this the content of the UCTE Settlement Report is different.

  19. UCTE Settlement Report

  20. UCTE Settlement Report

  21. UCTE Settlement Report

  22. UCTE Settlement Report

  23. UCTE Settlement Report sequence flow

  24. Overview daily UCTE Settlement

  25. Overview weekly UCTE Settlement

  26. UCTE Settlement Document Information Model UCTE Settlement Report sequence flow Provide the Status of the account for unintentional deviation per tariff Provide the Tariff Type AX1 = Winter HT AX2 = Winter HHT AX3 = Winter NT AX4 = Summer HT AX5 = Summer HHT1 AX6 = SummerHHT2 AX7 = Summer NT Nature of the time series A44 - Compensation program within the reporting period Ax1 - Schedule Ax2 - Energy flow Ax3 - Compensation Requirements for the compensation period, applied only in a weekly settlement report. A21 - Inadvertent deviation (also called unintentional deviation)