90 likes | 96 Views
PROJECT 3004(18) NORTH CARPENTER ROAD MAJOR RECONSTRUCTION. PUBLIC MEETING MARCH 5, 2019. Project Team. Shelly & Sands, Inc.: Northeast Ohio Construction Manager Gene Galloway Superintendent Fred Weidenthal Ohio Department of Transportation District Three:
E N D
PROJECT 3004(18) NORTH CARPENTER ROADMAJOR RECONSTRUCTION PUBLIC MEETING MARCH 5, 2019
Project Team Shelly & Sands, Inc.: • Northeast Ohio Construction Manager Gene Galloway • Superintendent Fred Weidenthal Ohio Department of Transportation District Three: • Construction Engineer Mike Fair, P.E. • Area Engineer Mike Titus, P.E. • Project Engineer Andy Blazek, P.E. • Program Manager Matt Walter, P.E., P.S.
Project Team Resource International, Inc.: • Vice President Transportation Engineering Sam Khorshidi, P.E. City of Brunswick: • Director of Public Service Paul E. Barnett • Consulting City Engineer Matthew M. Jones, P.E.
Project Overview • Widening of North Carpenter Road between Concord Drive and Boston Road • Addition of concrete pavement, curb, and sidewalks throughout the project • Addition of turn lanes on Grafton Road and North Carpenter Road at the Grafton Road intersection • Construction of a new storm sewer system • Traffic signal and signage updates
2019 Construction – Grafton Rd • Construction of the Grafton Road intersection utilizing 2 separate 30 day closures (total of 60 days) • Eastbound traffic will be maintained during each detour phase. Westbound traffic will be detoured during this time.
2019 Construction – North Carpenter Rd • Construction of North Carpenter Rd south of Grafton Road utilizing 2 separate 60 day closures (total of 120 days) • Southbound traffic only will be maintained during this phase from Grafton Road to Concord Drive • Normal traffic pattern will be maintained on North Carpenter Road north of Grafton Road
2020 Construction – North Carpenter Rd • Construction of North Carpenter Rd north of Grafton Road utilizing 2 separate 60 day closures (total of 120 days) • Northbound traffic only will be maintained during this phase from Grafton Road to Boston Road • Normal traffic pattern will be maintained on North Carpenter Road south of Grafton Road
General Traffic Overview • Grafton Road will have two, 30-day detours. • Eastbound traffic will be maintained at all times. • Westbound traffic will be detoured. • North Carpenter Road will have two, 120-day detours. • Driveway access will be maintained at all times • Mailbox banks may be used • Side streets may have detours. • Side streets that do not have alternate access routes will have traffic maintained at all times.
Thank you for coming! Feel free to ask questions and meet the Project Team.