L3PT. Large Portable Projected Peripheral Touchscreen Team Jackson Brian Gosselin Greg Langlois Nick Jacek Dmitry Kovalenkov. Midway Design Review. ing. Project Overview. Portable Large workspace Affordable Single / Multi user Multi touch capabilities

1 / 17

Download Presentation

L3PT

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. L3PT Large Portable Projected Peripheral Touchscreen Team Jackson Brian Gosselin Greg Langlois Nick Jacek Dmitry Kovalenkov Midway Design Review ing

  2. Project Overview • Portable • Large workspace • Affordable • Single / Multi user • Multi touch capabilities • No other product currently on the market meets all these specifications.

  3. System Block Diagram

  4. MicroVision SHOWWX Laser Pico Projector • Small: .55” x 2.36” x 4.64” • Light: 122g • Resolution: 849 x 480 • Image Size: 6” to 100” • This projector provides the best resolution and size within budget.

  5. Microsoft LifeCam vx-2000 • Purchased for prototyping • Processes up to 30 fps • Removed visible light filter • Replaced with IR longpass filter For the final design, we may need to upgrade to a faster camera to minimize delay.

  6. Image Processing • Touch locations correspond with brightest areas • Distinguishes between touch pixels and background pixels • Finds coordinates of touches • Coding in C++ • Utilizing OpenCV libraries

  7. Image Processing – Algorithm # 1 • Scans image for first touch pixel • Records location of touch • Draws black circle to cover brightest region • Saves touch coordinates • Sometimes more than 1 coordinate per touch • Very fast and simple

  8. Image Processing – Algorithm # 2 • Finds bounding rectangle of touch region • Assigns center of rectangle as the touch location • Always only 1 coordinate per touch • More complex and slower than algorithm 1

  9. Speed Of Image Processing • Algorithm # 1 has complexity O(). • Algorithm # 2 has complexity O().  

  10. Windows 7 Driver • Communicates touch coordinates to operating system • Dependent on image processing • Main focus for the spring semester

  11. Calibration • Adjust the size of projected screen • Touch four corners to define the screen boundary • Map image coordinates to projected coordinates

  12. Infrared Emitting Pens • Components: • Switch • Infrared LED • 120Ω Resistor • AAA Battery • Battery Life: • Capacity of 1000 mAh • 3.1 mA drawn by pen • Life: 322.5 hours

  13. Physical Assembly • Stable base supports projector and camera at a height up to 3.5’ • Designed to support adjustable heights for projector and camera • Handle for portability • Top opens for storage

  14. Midway Design Review Goals • Choose detection method • IR emitting pens • Position of projector and camera • In front and above • Use camera to detect infrared light • Camera with IR longpass filter • Extract coordinates of touch locations • Image processing algorithms

  15. What’s Next? • Determine whether or not a dedicated signal processing chip is necessary • Windows 7 driver • System calibration

  16. Updated Gantt Chart

  17. Conclusion • Met all midway design review goals • On track to complete L3PT by scheduled deadline DEMO