1 / 35

GM Facility Image Overview and Best Practices

GM Facility Image Overview and Best Practices. Facility Image Process. Designed to ensure dealers meet and exceed customer expectations for facility design Facility brand elements are consistently applied across dealer body The largest retail image effort ever!!!

hisano
Download Presentation

GM Facility Image Overview and Best Practices

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. GM Facility Image Overview and Best Practices

  2. Facility Image Process • Designed to ensure dealers meet and exceed customer expectations for facility design • Facility brand elements are consistently applied across dealer body • The largest retail image effort ever!!! • It’s part of EBE, but its process is distinct from the EBE process

  3. General Best Practices • Review www.gmfacilityimage.com for general program overview • Keep up to date on facility timeline • Be mindful of lead times for ordered items • Floor tile, exterior building materials, brand focused merchandising materials from DCI Marketing, exterior signage from Pattison Sign Group

  4. General Best Practices • Gensler sends automated emails when something is received. If you don’t receive the email after a day or two, please verify address and re-send. • Always include your BAC in all communication to streamline processing

  5. www.gmfacilityimage.com • Home Page Links: • Brand specific information • Electronic enrollment • GMFI signage • Essential Brand Elements (EBE) • Contact Us • Questions? • Contact your • Zone Manager

  6. www.gmfacilityimage.com • For Each Brand: • Image elements • Process description • Required finishes and furnishings • Space standards • Questions? • Contact your • Zone Manager

  7. Facility Image Timeline

  8. Pre-Enrollment Discussion • Early communication is key to success • Review enrollment process with your Zone Manager • Identify facility type • Gather as-builts / identify as-built provider • Review the facility image timeline • Obtain site approval for all site relocations

  9. Enrollment Phase • Enroll on-line at www.gmfacilityimage.com • Enter BAC and receive PIN to enroll • Send as-builts to Gensler within 15 days: • Send CAD as-builts to gmfi_as-builts@gensler.com • A separate email will notify status of compliance • Detailed requirements listed on www.gmfacilityimage.com and in enrollment letter

  10. Enrollment Phase • Best Practice: • Request the PIN online, enroll using the same computer • Send as-builts early to allow for 2 business days for review and potential resubmission if non-compliant

  11. Enrollment Phase Best Practice: • Go to www.GMPrograminfo.com • Press release templates for key milestones in facility completion • Dealer Investment • Dealer Groundbreaking • Dealer Grand Opening

  12. Enrollment Phase Best Practice: • “Dealer Investment” template • Go to www.GMPrograminfo.com

  13. On-Site Consultation Phase • Once enrollment and as-builts are compliant, Dealer is contacted by Gensler to schedule dealership consultation: • Zone Manager is notified of on site consultation date • Scheduling will occur in the quarter you are assigned • A Gensler consultant is assigned to the project and becomes the single point of contact • Gensler’s role is to draw a compliant imaged facility

  14. On-Site Consultation Phase • Best Practice: • Invite dealer selected local architect and/or contractor to consultation • Attend consult and be prepared to discuss solutions

  15. Design Intent Document (DID) Phase • Once initial design drawings are received, please review and respond within 10 business days • If no response after the 10 day period, Design Intent Document (DID) will be sent • Gensler produces DID containing “schematic design” • Conveys the general, conceptual intent for the finished facility • Your local architect must elaborate and coordinate with any other facility upgrades and produce construction documents for code compliance, bidding and permits

  16. Design Intent Document (DID) Phase • Best Practice: • Hire a local architect that has experience with dealership facilities • Provide copy of D.I.D. to local architect

  17. Construction Document (CD) Phase • Once construction documents are complete send CD’s to Gensler at gmfi_cd-review@gensler.com in .pdf format • Response email will be sent back when submission is received • CD Review Checklist will be emailed to dealer noting “Compliant” or “Non-Compliant” status. • Non-Compliant items will be noted • Resubmissions will be reviewed in the order they are received

  18. Construction Document (CD) Phase • Best Practice: • Review the CD Review requirements document and the CD Submission and Review Process Training Video on www.gmfacilityimage.com • Utilize a lighting consultant for the development of a program compliant lighting design and energy optimization. • Be sure the construction document package is complete with all required documents. Incomplete packages will be rejected without review

  19. Construction Document (CD) Phase • Best Practice: • Don’t wait until your due date or quarter end to submit. Allow 10 business days for review and potential resubmission if non-compliant • Encourage Gensler architect to dealer architect communication on technical questions

  20. Verification Phase • Start of Construction • Mid-Point Notice • Construction Complete

  21. Verification Phase – Start of Construction • Advise Zone Manager when Construction has begun • 2 of these 7 criteria are required, vary by site: • Photo with date stamp of major excavation (footings, site utilities, etc) • Photo with date stamp of major exterior building demolition (fascia removal, roof and wall demolition, entrance reconfiguration) •  Photo with date stamp of major interior building demolition(floor tile removal, partition/ceiling removal,  interior barricades, etc) • Copy of Building Permit issued by city • Copy of signed Contract for Construction showing contractor’s determination of cost of project • Photo with date stamp of significant building materials stored on site • Copy of  P.O. or shipping invoice for long-lead items (glass doors, elevators, ACM)

  22. Verification Phase – Start of Construction • Best Practice: • Order “Pardon our Dust” graphic displays to entice customers with future facility design • Two Banner Sizes for Exterior Display: 4’x8 or 5’x12’ • 2’x4’ Foam Core for Easel Display (Interior). • Note: Custom print for each dealer using Gensler rendering.

  23. Verification Phase – Start of Construction Best Practice: • Go to www.GMPrograminfo.com • Press release templates for key milestones in facility completion • Dealer Investment • Dealer Groundbreaking • Dealer Grand Opening

  24. Verification Phase – Tile Best Practices Best Practice: • Allow 6-8 weeks for delivery. • Use qualified, professional installers. • Recommend epoxy grout (most durable, easiest to clean) but: • Installers must avoid epoxy residue on tile surface (very hard to remove); professional installers have no problem doing this properly. • Use grout that matches or is only slightly darker than floor tile (per DID)

  25. Verification Phase – Tile Best Practices Best Practice: • Floor tile install should be done last (after other heavy construction is completed) • If tile install is NOT last, floor must be covered to protect it. • Require deep cleaning from installer before final “sign off”. • Helps identify any defects • Follow manufacturer’s specs for tile cleaning • Posted on www.gmfacilityimage.com • Do NOT place any sealers or finishes on floor tile. • Creates “haze” on tile that is very difficult to remove. • Tile does not need any sealers, etc.

  26. Verification Phase – Midpoint of Construction • Submit copy of Electrical permit or Evidence of electrical inspector’s visit • Send image to gmfi_cd-review@gensler.com • Response email will be sent when submission is received and notify of compliance status

  27. Verification Phase – Construction Complete • After facility is 100% complete, provide required verification documents on a compact disk to Gensler • No email submissions allowed • Allow 10 business days for Gensler to review • Response email will be sent when submission is received • Verification photography requirements can be found on www.gmfacilityimage.com and also in the Design Intent Document

  28. Verification Phase – Construction Complete • Best Practice: • Notify Zone Manager when construction is completed • Review the Verification Submission training video on www.gmfacilityimage.com • Consider verification photography enrollment at www.gmfacilityimage.com to have a Gensler representative take your verification photos • Allow 10 business days for review and potential resubmission if non-compliant • Keep a copy of your CD in case of loss in mail

  29. Verification Phase – Start of Construction Best Practice: • Go to www.GMPrograminfo.com • Press release templates for key milestones in facility completion • Dealer Investment • Dealer Groundbreaking • Dealer Grand Opening

  30. Digital Signage – Service Menu • Digital Signage Overview: • Service menu enables quick and easy pricing updates to reflect current mailer prices, specials, and promotions • RSS ticker allows dealer to communicate special promotions, community events, and personally greetings customers • Slideshow features Certified Service and brand messages • Additional features coming soon!

  31. Digital Signage – Service Menu • Recommended Devices, Integrated Google TVs: • Size: 55” or larger screen with 1080P resolution and HDMI compatibility • 55” Screen: LG 55 G2 or Sony NSZ-GT1 Blue Ray Disc Player with Integrated Google TV • 46-47” Screens: Sony NSX-46GT1 or LG 47G2 • External Device: • Sony NS2-GT1 Blue Ray Disc Player • * A wired Ethernet connection is strongly encouraged to sustain connectivity

  32. Digital Signage GM Digital Signage

  33. Digital Signage – Fee Comparison vs. Other Providers GM Digital Signage Silver - $1,390/month ($2,998 set up) Dealer TV 5.0 Service Menu Custom RSS ticker that can be updated with dealer specials/messages POS Banner - choose from asset library of promotional service offers Gold - $1,790/month ($3,998 set up) Silver Package Plus: 1 digital sign 1 - 42” LG HDTV Platinum - $1,990/month ($4,998 set up) Silver Package Plus: 2 digital signs 5 – 42” LG HDTV * Minimum 24 month agreement Service Menu - $0 Service Menu Weather widget Custom RSS ticker that can be updated with dealer specials/messages POS Banner - choose from asset library of promotional service offers Showroom Display - $0 (Coming Soon) • Brand provided YouTube Video • Digital point of sale material Dealer Content - $50-100/month Optional for Dealer Upload local video/digital content ACB approved Bronze - $483/month ($3,995 set up) • Service Queue Messaging • POS Banner Ads • (Not for Live TV) Silver - $576/month ($4,995 set up) • TV Ad Substitution • POS Banner Ads • (No Service Queue) Gold - $669/month ($5,995 set up) • TV Ad Substitution • POS Banner Ads • Service Queue Messaging *Minimum 12 month agreement

  34. Digital Signage – Status Update • Roll Out Schedule : • June - December: Pilot Phase • January: National Launch

  35. Contact Information • Facility Image questions: Zone Manager or Gensler • Gensler – 313.496.8980 • Enrollment Option 1 • CAD As-Builts Option 2 gmfi_as-builts@gensler.com • CD Review Option 3 gmfi_cd-review@gensler.com • Verification Option 4 gmfi_verification@gensler.com • EBE program headquarters: • EBE – 877.401.6938

More Related