Maplewood Middle School Addition. Board of Education Meeting May 7, 2012. Approval Process. Identify Program Requirements and Budget Develop Design Documents NJDOE Approval (educational capacity) Planning Board Courtesy Review NJDCA Approval (specification codes) Bid Construct.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'Maplewood Middle School Addition' - hewitt


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
maplewood middle school addition

Maplewood Middle School Addition

Board of Education Meeting

May 7, 2012

approval process
Approval Process
  • Identify Program Requirements and Budget
  • Develop Design Documents
  • NJDOE Approval (educational capacity)
  • Planning Board Courtesy Review
  • NJDCA Approval (specification codes)
  • Bid
  • Construct
develop design documents
Develop Design Documents
  • 2010-2011 Confirmed Need to Address Increasing Enrollment
  • 2010-2011 Identified Need to Renovate Science Labs
  • Reviewed 2001-2003 Original Addition Plans
  • Updated Plans for current needs, efficiencies, and cost analysis
  • 2011-2012 Funding for Project Identified
plan development and approvals
Plan Development and Approvals
  • NJDOE Approved Project and Educational Capacity
  • Maplewood Planning Board Raised question regarding brick façade facing Maple Avenue and Impact on Existing Foliage
  • Interior Details Being Finalized for Submittal to NJDCA
future timeline
Future Timeline
  • June 2012 Submittal to DCA
  • Summer 2012 Bid for Project
      • (dependent on DCA review)
  • September 2012 Begin Construction
      • (dependent on DCA review)
  • September 2013 Opening of New Addition
slide7
Site Plan

for Maplewood Middle School Addition

slide8
Existing Building

Front Façade

Facing Burnet Street

slide17
Basement Level

Classrooms

what s next
What’s Next?
  • Finalization of Plans and Internal Space
  • June 2012 Submittal to DCA
  • Summer 2012 Bid for Project
  • September 2012 Begin Construction
  • September 2013 Opening of New Addition

Communication to Neighbors:

    • Sign up for Notification this evening
    • Send contact information to:

[email protected]