1 / 16

T/D Group Update to CNF

T/D Group Update to CNF. Overview of Transmission Transfer Studies Results of CNF T/D Studies – Lower Michigan Group Status. Thomas Vitez Director, System Planning International Transmission Co-Chair Michigan Capacity Needs Forum T/D Group May 27, 2005.

hassett
Download Presentation

T/D Group Update to CNF

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. T/D Group Update to CNF • Overview of Transmission Transfer Studies • Results of CNF T/D Studies – Lower Michigan • Group Status Thomas VitezDirector, System Planning International TransmissionCo-Chair Michigan Capacity Needs Forum T/D GroupMay 27, 2005

  2. Factors that Influence How Much Can be Transferred Across the Transmission System • “Topology” – how many facilities are there and how are they connected? • “Capacity” – what are these facilities capable of carrying? • “Normal” – amount of flow that can be carried for an indefinite period of time • “Emergency” – amount of flow that can be carried for a shorter, defined period of time • “Response” – how does the transfer split up amongst the facilities (related to topology) • “Normal” – all facilities in service • “Post-Contingency” – after facility is outaged • “Pre-load” – how much is flow on the lines before transfers? • “Base” – starting generator dispatch • “Alternative Dispatch” 200 /400 100% 40% 0% X 0 100 Area B Area A 60% 0% X 100% /320 300 G X 0 100

  3. Determination of Transfer Capability – Simplified Example 200 40% Line 1 0 Area B Area A Line 2 G • For A to B transfers – Line 1 with G in-service and all transmission in-service • 200 MWs rating + 0 MWs pre-existing flow = 200 MWs of capacity available • A to B transfers * 40% = 200 • A to B transfers limited to 500 MWs for this condition Check -- Flow through Line 1 After Transfer pre-existing flow + percentage of transfer * transfer = Rating of Line 1 0 + 40% * 500 = 200 • A to B transfers limit confirmed for this condition

  4. Determination of Transfer Capability – Simplified Example Continued Line 1 Area B Area A X 300 60% Line 2 G 100 • For A to B transfers – Line 2 with G out and all transmission in-service • 300 MWs rating - 100 MWs pre-existing flow = 200 MWs of capacity available • A to B transfers * 60% = 200 • A to B transfers limited to 333 MWs for this condition Check -- Flow through Line 2 After Transfer pre-existing flow + percentage of transfer * transfer = Rating of Line 2 100 + 60% * 333 = 300 • A to B transfers limit confirmed for this condition

  5. Determination of Transfer Capability – Simplified Example Continued Some More Line 1 X Area B Area A 320 100% Line 2 G 0 • For A to B transfers – Line 2 with Line 1 out • 320 MWs rating - 0 MWs pre-existing flow = 320 MWs of capacity available • A to B transfers * 100% = 320 • A to B transfers limited to 320 MWs for this condition Check -- Flow through Line 2 with Line 1 out After Transfer pre-existing flow + percentage of transfer * transfer = = Rating of Line 2 0 + 100% * 320 = 320 • A to B transfers limit confirmed for this condition

  6. Determination of Transfer Capability – Simplified Example -- Wrap Up • What is the transfer capability? • Line 1 with G in and all transmission in-service – 500 MWs • Line 2 with G in and all transmission in-service – 333 MWs • Line 2 with Line 1 out – 320 MWs • Transfer Limit = Overall Minimum = 320 MWs 200 /400 Line 1 Area B Area A /320 300 Line 2 G

  7. Determination of Transfer Capability – Not So Simple Illustration 2 3 Area A Area B With sub-areas 1 2 Area D Area C Area E • Any facility can limit transfers – including lines between sub-areas • Dispatch and load patterns throughout the area impact results – this includes “parallel” transfers

  8. T/D Group Results Lower Michigan – Analysis Performed • All transmission in-service + • “Base” Generation Dispatch – OR -- • One Unit in MECS out • One transmission element out + • “Base” Generation Dispatch – OR -- • One Unit in MECS out • Sensitivities • Flow changes on Michigan-Ontario Interface • Unit outages outside MECS • Areas monitored – ITC, METC, AEP, NIPSCo, FE • Assumptions include – Sufficient Generation Outside of MECS to “fill the pipe”

  9. Transmission/Distribution Work Group Status • Transmission/Distribution Work Group Status • Transfer Capability Results Published for Lower Michigan • Transmission Upgrades Scenarios for Lower Michigan Identified and Analyzed • Remaining Work • Complete Review of Potential Voltage Limits • Publish Results for Upper Michigan • Analyze Off-Peak Conditions • Issue Report • Continue Work with Other CNF Groups Questions?

More Related