An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. New Morehead State Bowling Facility IET 499C, Fall 2012 Stephen Glossner

  2. Why the need for a new bowling facility? • The current bowling facility is • Too small • No restrooms • Outdated • Font desk area is cramped • No space for maintenance/repairs

  3. Site Work • Site location • Site survey • Cut and fill analysis

  4. Site location

  5. Photo of site location 1 of 2 Site Pictures Photo of site location 2 of 2

  6. Design • General floor plan • Plumbing/ HVAC/ Electrical • Finished floor plan • 3D rendering

  7. 36’ Current Floor Plan 4’ Total square feet = 3,640 sq./ft. 68’ Dimensions = 96’ X 36’ 96’ 15’ 13’ 28’ 23’ 8’

  8. New Floor Plan Total square feet = 16,172 sq./ft. Dimensions = 151’ 6” X 106’ 9” 151’ 6” 15’ 33’ 10’ 7” 20’ 106’ 9”

  9. Comparison Current Floor Plan New Floor Plan • Total square feet = 3,640 sq./ft. • Available standing room = 468 sq./ft. • Area behind front desk = 184 sq./ft. • Maintenance area = 144 sq./ft. • Total square feet = 16,172 sq./ft. • Available standing room = 5618 sq./ft. • Area behind front desk = 380 sq./ft. Maintenance area = 1121 sq./ft.

  10. Plumbing Plan Men’s restroom -handicapped stall -three urinals -double sink Woman’s restroom -handicapped stall -two additional stalls -double sink

  11. HVAC Plan • Forced centralized air system with outside unit mounted on the roof • Fourteen, ceiling hung, air vents

  12. Electrical Plan Electrical Key Electrical outlet Recessed can light Fluorescent tube light Single switch

  13. Finished Floor Plan

  14. Current BowlingFacility Pictures

  15. Area behind front desk Area behind pin-setters

  16. New Bowling Facility Design

  17. Cost/ Schedule • Material and Labor estimate • Cost analysis • Project schedule

  18. Turn-Key Estimate Sample

  19. Overview of Estimate

  20. Cost Analysis • Expected annual income for new bowling facility = $157,800 • It would take just over 17 years to cover the initial cost of the project.

  21. Section of Project Schedule

  22. Start Date Half Way Date End Date Project Schedule: 296 working days May/1/2012 December/7/2012 June/18/202

  23. Conclusion A new bowling facility would benefit the university, the bowling team and the city of Morehead • The university • Increased revenue • greater appeal for potential students • The bowling team • Bigger, better facility • More members can join • Updated machines/equipment • The city of Morehead • Something new and exciting • New place to take family

  24. Questions ?