1 / 11

Yury Meltsov Aug. 201 7

Yury Meltsov Aug. 201 7. Experience in C onformity A ssessment of P roducts and S ervices for Russian NPPs and Overseas Nuclear Power Plant New Builds. Experience in C onformity A ssessment of P roducts and S ervices for Russian NPPs and Overseas N uclear P ower P lant New Builds.

gunter
Download Presentation

Yury Meltsov Aug. 201 7

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Yury Meltsov Aug. 2017 ExperienceinConformityAssessmentofProductsandServicesforRussianNPPsandOverseas Nuclear Power Plant New Builds

  2. ExperienceinConformityAssessmentofProductsandServicesforRussianNPPsandOverseas NuclearPowerPlant New Builds • Since 2007 therehas been NP-071 standard,a documentofRostekhnadzor(theregulatorybodyofRussia), in Russiawhichdeterminestheneed for conformity assessmentofequipmentandservices. • Thedocumentdefinesfourformsofconformityassessment: • - Testing • - Acceptanceofequipment • - Certification • - Statesupervision • Therequirementsofthisdocumentapplytoequipmentanditscomponentsrelatedtosafetyclasses 1, 2 and 3(systemsandequipmentimportantforsafety)

  3. Onthebasisofthisdocument,the RussianUtility(Rosenergoatom) developed a document,RD EO1.1.2.01.0713-2007,thatclarifiedthespecificfeaturesoftheseformsofconformityassessment, participants, scopesofapplication, deliverabledocuments,etc. Both Russian and foreign enterprises had these documentsin placeas a guidance for conformityassessmentduring development(design) andmanufactureofequipmentforRussiannuclearpowerplants. Therequirementssetforthinthesedocumentswerealsoappliedfor comformity assessment of equipmentforforeignnuclearpowerplants (Belarus, China, India).

  4. Slide title Mainparticipantsintheconformityassessmentare: - Customers (RussianNPPsandforeigncustomers) - Contractors - Manufacturers - Authorizedorganizations - Material engineeringorganizations (asexperts)

  5. 1. Conformityassessmentintheformoftests Basically, thisformofconformityassessmentisusedinthedevelopmentandtestingofnewequipment, sincemaincharacteristicsof serialorwell-knownequipmenthavealreadybeendefinedorconfirmed. Atthisstage, fullscaletestsarecarriedout, includingtestsforreliability, operability,andtakingintoaccountenvironmentalconditions, operatingtemperatures, pressure,etc. Requirementsfortest procedurearesetinRussian GOST 15.201 andotherRussianstandards. Intheabsenceofnecessaryrequirements, a testprogramisdeveloped, agreedwiththedesignorganizationsandapprovedbytheCustomer.

  6. Theresultofthisformofconformityassessmentistheapprovalorconfirmationoftheequipmenttechnicalrequirements (specifications) Inaccordancewiththe Russian standard(GOST 15.201),testsareconductedwiththeparticipationoftheCustomer, theprojectorganizationandcontractor. Ifitisnecessary,the Customermayassign anauthorizedorganizationtotakepartinthetests.

  7. 2. Conformityassessmentintheformofacceptance Basically, thisformofconformityassessmentisusedinthemanufactureofserialequipmentandequipmentwith design, technologicalandoperationalexperience(referenceequipment). ThemaindocumentconfirmingthefulfillmentbythemanufacturerofsafetyanddesignrequirementsistheQualityPlan (inourcase, theInspectionandTestingPlan). Theteststhatarecarriedoutbythemanufactureofthisequipment, as a rule,arestandardanddescribedintherelevantdocuments. Acceptanceofequipmentiscarriedoutbyanauthorizedorganization, ifnecessarywiththeparticipationofthecontractorandthecustomer.

  8. Requirements forContentofQualityPlan(Inspection andTestingPlan)

  9. RequirementsforContentofQualityPlan(InspectionandTestingPlan)RequirementsforContentofQualityPlan(InspectionandTestingPlan)

  10. Requirements forContentofQualityPlan(Inspection andTestingPlan)

  11. 3. Conformityassessmentintheformofcertification • Conformityassessmentiscarriedoutunder a separatelawandprocedures. • 4. ReceivingInspection • Receiving inspection is conducted to verifythecompletenessoftheequipmentandthedocumentationatthesite. • - electroniccontrolofdocumentation • - transportationofequipment • - Visualinspectionandtestingofequipment (ifnecessary) • Receiving inspection procedure is defined in the Utility’s documents.

More Related