1 / 39

Risk Management

Presentation Sequence. Risk's Basics tuned to PMBOK Evolution of Risk Register (Theoretical). Risk's Basics: Risk HISTORY

guenevere
Download Presentation

Risk Management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


    15. Business (e.g. misuse of project funds, resources, etc) Technical (e.g. inability to complete any activity to fulfill the project requirement) Operational (e.g. inability of a team member to coordinate and communicate effectively and efficiently with other peer, subordinate or supervisor)

    16. With respect to project life cycle (PLC), the risks can be categorized into followings: Scope risks (e.g. change in scope due to client requirement) Quality risks (e.g. inability to complete tasks up to required technical or quality performance) Schedule risks (e.g. inability to complete tasks within estimated time limits) Cost risks (e.g. inability to complete tasks within the estimated budget) Procurement risks (e.g. inability to procure material or machinery in time)

    19. The extent or scope of events to be assessed The complete range of potential risks or hazards should be considered All team members and stake-holders on board. Sufficient monitoring and review Project objectives should be crystal clear i.e. time, cost, scope and quality Clear Focus i.e., maximizing opportunities to enhance project objectives with shorter schedule, lower cost, improve scope and higher quality Minimize crisis by crisis-management-strategies.

    20. Realistic and honest recognition of project risks even if they indicate problems with the project Candid and unbiased discussions. Quantity not the Quality, initially. Do not reveal repercussions of discussions to the general attendees. Do communicate the gravity and significance of the results to the selected wisdom of the industry while doing Quantification process. Bureaucratic hierarchy should be discouraged in meetings where risk identification and assessment is discussed The team members should be committed in collecting realistic and high quality data about risks. Risk data is based on the expertise and judgment of informed individuals. It requires committed effort and organizational support to spend the time and resources needed to collect data about project risk Final success factor is developing threshold definitions of risk consequence on main objectives, identifying the combinations of probability and consequence that lead to risk ranking/rating as low, moderate and high and determining the relative importance of different project objective. Technically termed as Risk Strategy.(Risk Matrix)

    21. ISO (International Organization for Standardization) suggests: IT SHOULD: create value. be an integral part of organizational processes. be part of decision making. explicitly address uncertainty. be structured and systematic. be based on the best available information. be tailored. take into account human factors. be transparent and inclusive. be dynamic, iterative and responsive to change. be capable of continual improvement and enhancement.

    22. PLAN Risk Management

    23. Risk Management PLANNING

    25. PLAN Risk Management

    31. Thanks

    33. Purposely left blank

    36. RISK MATRIX

    40. RISK MATRIX

More Related