An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. S-graph Framework in Batch Process Scheduling T. Holczinger1, R. Adonyi1, G. Biros1, J. Romero2, L. Puigjaner2, F. Friedler1 1Department of Computer Science, University of Veszprém, Veszprém, Egyetem u. 10., H-8200, Hungary 2Department of Chemical Engineering, Universitat Politècnica de Catalunya, Barcelona, Av. Diagonal 647, E-08028 CAPE Forum 2004 Veszprem

  2. Problem definition Given: • The order of the tasks (recipe) • The set of plausible equipment units for each task (with operation times) • Necessary amount of products • Storage policy • Timing data Aim: • The optimal order of the tasks • Using the given resources

  3. Conventional representation Notations PT: processing time Eq.: equipment unit

  4. Product A Product B Product C Graph representation

  5. Recipe • Directed graph Products: A, B, and C

  6. 2 S-graph representation • Directed graph • The changeovers are denoted by arcs

  7. 6 1 2 E1 E2 3 7 4 E2 E1 6 1 2 E2 E1 3 7 4 E2 E1 NIS vs. UIS Unlimited Intermediate Storage Non Intermediate Storage

  8. 1 2 3 10 A E1 E3 E2 4 5 6 11 B E2 E3 E1 7 9 8 12 C E1 E2 E3 Schedule-graph • AnS-graph is a schedule-graph, if • the equipment-task assignment and • the operation order of the tasks are given (schedule-arc)

  9. Basic algorithm • Branch and bound framework • Extension of the recipe-graph with schedule-arcs according to the rules • Introduction of schedule-arcs • Identical set of nodes • The weight of the recipe-arcs can be changed • The number of the possible extensions are finitethe algorithm is finite

  10. Product A Product B More than one batch per product • Considering each batch as an individual productis not efficient enough

  11. Single equipment unit for a task

  12. Optional equipment units for a task with identical processing time

  13. Acceleration tools • Cycle prediction • To predict that a subgraph has no feasible solution • Based on the cycle search algorithm • It can reduce the size of the search tree • LP model for sharpening the lower bound

  14. 1 2 7 E1 E2 3 4 8 E1 E2 5 6 9 1 1 1 E1 E2 2 4 3 3 1 2 1 1 2 2 7 7 7 E1 E2 E1 E1 E2 E2 3 4 8 E1 E2 3 3 4 4 8 8 E1 E1 E2 E2 5 6 9 E2 E1 5 5 6 6 9 9 E2 E2 E1 E1 Illustrative example S-graph Search tree S-graph Search tree 1 2 4 3 2

  15. 1 1 2 2 7 7 E1 E1 E2 E2 3 3 4 4 8 8 E1 E1 E2 E2 5 5 6 6 9 9 E2 E2 E1 E1 Illustrative example S-graph Search tree 1 3 4 2 5 1 3 4 2 6 6 5

  16. 1 2 7 E1 E2 3 4 8 E1 E2 5 6 9 E2 E1 Illustrative example: search tree 1 3 4 2 6 5 1 1 7 3 4 2 3 4 2 6 5 6 8 7 9 5 10 7 11 12 13 With cycle prediction Without cycle prediction

  17. Industrial size scheduling problem • 123 products • 31 different base products • 13 possible pack sizes from 5 to 20000 liters • Necessary amount is from 5 to 12000 tons for a year (solved the production of a week) • Batch size is 6 tons for each mixer • Two types of tank • T901 – T922 (8 tons) • T951 – T968 (15 tons) • 120 minutes minimum residence time for intermediate products in a tank (bubbling)

  18. Parameters of the problem Number of products: 123 Total number of batches: 389 Number of equipment units Mixer: 5 (batch type equipment unit) Tank: 40 Packing line: 26 (continuous type equipment unit) Running time on PC (1 GHz) is less than 4 minutes and the optimality gap is 2.6%

  19. Further information • Publications • E. Sanmartí, F. Friedler, and L. Puigjaner, Combinatorial technique for short term scheduling of multipurpose batch plants based on schedule-graph representation, Comput. Chem. Engng.22 (1998) • E. Sanmartí, L. Puigjaner, T. Holczinger, and F. Friedler, Combinatorial framework for effective scheduling of multipurpose batch plants, AIChE J.48 (2002) • Holczinger, T., J. Romero, L. Puigjaner, and F. Friedler, Scheduling of Multipurpose Batch Processes with Multiple Batches of the Products, Hung. J. Ind. Chem., 30, 305-312 (2002) • Demonstration programs • http://www.dcs.vein.hu/CAPO/demo/sch/