Potential Air Impacts of Demand Response in New England

Potential Air Impacts of Demand Response in New England. Geoff Keith Synapse Energy Economics, Inc. www.synapse-energy.com 617-661-3248. Synapse Energy Economics, Inc. DR Emissions Modeling for NEDRI. Hourly dispatch modeling with PROSYM

grant
Download Presentation

Potential Air Impacts of Demand Response in New England

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Potential Air Impacts of Demand Response in New England Geoff Keith Synapse Energy Economics, Inc. www.synapse-energy.com 617-661-3248

  2. Synapse Energy Economics, Inc. DR Emissions Modeling for NEDRI • Hourly dispatch modeling with PROSYM • Modeled a hypothetical near-term year with a system reserve margin of 20% • 500-MW DR resource in New England • 60% of DR capacity modeled as load response and 40% generation • Modeled economic (day-ahead bidding) demand response – not emergency programs • DR bid at five bid points: $100-500 per MWh

  3. Synapse Energy Economics, Inc. Overview (cont.) • Examined emissions of NOx, SO2, CO2 , PM2.5, PM and seven air toxics • Explored different assumptions about: • Level of participation by diesel- vs. gas-fired IC generators • Amount of loads shifted to off-peak periods • Whether the DR resource could be used to meet operating reserve requirements • Also modeled energy efficiency programs for comparison

  4. Synapse Energy Economics, Inc. DR Operation • DR operated in approximately 90 summer hours. • It provided 3,360 MWhs of load relief (over three times as much • as ISO NE’s 2002 economic demand response program). • The vast majority of the load relief was in southwest CT.

  5. Synapse Energy Economics, Inc. When DR Is Used for Reserves • The result is more efficient unit commitment, reduced operation of oil- and gas-fired steam units and overall emission reductions. • The emission reductions are primarily due to the use of DR capacity to meet reserve requirements. • Increasing the level of diesel participation in the DR program reduces overall emission reductions for NOx, SO2, CO2, PM2.5 and PM. Reductions of NOx are compromised most. Some toxics increase, some decrease

  6. Synapse Energy Economics, Inc. When DR Is Not Used for Reserves • Emissions impacts are much smaller than when DR is used for reserves. • The net impact on NOx could be positive or negative depending on the amount of DR provided by diesel-fired units. • While overall emission impacts are small, they could pose health risks in specific locations. The most serious of these risks are probably diesel fine particulates and PAHs. • DR emissions are likely to come from units without tall stacks located in populated areas. • On one day in the modeled summer, total DR emissions in southwest CT are in the range of: 3.5 tons NOx.

  7. Synapse Energy Economics, Inc. Summer Emission Changes from New England DR (when DR is used for reserves) Range of uncertainty ±10%

  8. Synapse Energy Economics, Inc. Summer Percentage Changes from DR (when DR is used for reserves)

  9. Synapse Energy Economics, Inc. Summer Emission Changes from DR (when DR is not used for reserves) Range of uncertainty ±10%

  10. Synapse Energy Economics, Inc. Impacts of Efficiency vs. DR • Two efficiency programs we modeled, an energy-targeted and a peak-targeted program. • The energy-targeted program reduced annual energy use the most, followed by the peak-targeted program and the DR program. • Focusing on annual emissions, the peak-targeted program reduced NOx and SO2 most, but the energy-targeted program reduced CO2 most. • Focusing on summer emissions, the energy-targeted program reduced NOx, SO2 and CO2 most. For DR, these results are from the scenario in which DR is used to meet reserve requirements.

  11. Synapse Energy Economics, Inc. Summer Impacts of Efficiency vs. DR Demand Response Peak-Targeted EE Energy-Targeted EE For DR, these results are from the scenario in which DR is used to meet reserve requirements.

  12. Synapse Energy Economics, Inc. Annual Impacts of Efficiency vs. DR Demand Response Peak-Targeted EE Energy-Targeted EE For DR, these results are from the scenario in which DR is used to meet reserve requirements.