An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BPAC October 2012 Milestonesand Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf ofthe Belle II SVD Collaboration

  2. What Happened Since February? • Sensors  Details by T.Tsuboyama • Micron delivered trapezoidal sensors with new atoll design • Construction database under development • Ladder assembly  Details by Y. Onuki • Double-origami ladder built at IPMU, Japan • 4 construction sites for series production • Mechanics  Details by I.Gfall • Design completed for all layers • Cooling  Details by C.Niebuhr • Detail design converging • Mockup tests ongoing • Electronics  Readout details by myself, integration by K.Hara • DC/DC converters and other parts tested • FADC design completed, layout in progress Concerns/recommendations In Feb 2012 BPAC report M.Friedl (HEPHY Vienna): SVD Schedule

  3. SVD Schedule • In early 2012, a detailed schedule was worked out and is now maintained by C.Irmler (HEPHY Vienna) • More than 200 unique items (and growing) with dependencies, duration and responsible persons • MS Project & PDF versions are available at http://www.hephy.at/project/belle/belle2svd/schedule • SVD ready for installation in August 2015 M.Friedl (HEPHY Vienna): SVD Schedule

  4. Sensors Ladder Production Mechanics Cooling Electronics Summary M.Friedl (HEPHY Vienna): SVD Schedule

  5. Sensors (1/2) • HPK • Large rectangular sensors: • 130% of installed quantity delivered already • Will issue an extra order for ~15% more in 2013 • Small rectangular sensors: • Design submission and order by November 2012 • Delivery until June 2013 • Construction database is being developed • First filled with sensor data (objects, measurements, transfers, …) • Then also other objects M.Friedl (HEPHY Vienna): SVD Schedule

  6. Sensors (2/2) • Micron • Trapezoidal sensors: • 3 wafers with new p-stop design delivered in August 2012, tested OK • Beam test + irradiation + beam test in October 2012 • After analysis: series production order by December 2012 • Delivery until August 2013 M.Friedl (HEPHY Vienna): SVD Schedule

  7. Sensors Ladder Production Mechanics Cooling Electronics Summary M.Friedl (HEPHY Vienna): SVD Schedule

  8. Ladder Production Sites • Discussion among all parties during summer 2012 B2GM • Plan for sharing of production: • L3: Melbourne • L4: Tata (at CERN due to export restrictions) • L5: HEPHY Vienna • L6: IPMU • We also agreed that it is important to keep some flexibility in our plan, so that one site can help another if trouble/delay occurs M.Friedl (HEPHY Vienna): SVD Schedule

  9. Origami Prototype Modules • Single Origami modules (HEPHY, 2010 and 2011) • Double Origami module (IPMU, 2012) • Both: collaborative effort of HEPHY, IPMU and Tata M.Friedl (HEPHY Vienna): SVD Schedule

  10. Ladder Production Schedule • Full ladder prototypes (L5 & L6) by February 2013 • Followed by final optimization of jigs • Series production for ~1 year starting summer/autumn 2013 M.Friedl (HEPHY Vienna): SVD Schedule

  11. Sensors Ladder Production Mechanics Cooling Electronics Summary M.Friedl (HEPHY Vienna): SVD Schedule

  12. Mechanics • Detailed design for all layers (including L3) completed M.Friedl (HEPHY Vienna): SVD Schedule

  13. Mechanics: Minor Open Issues • Ladder mount on end rings • Not finalized yet, but converging • Prototypes being prepared • Cooling for L3 hybrids • heat pipes look promising, now investigating Acknowledging help from MPI & DESY engineers! M.Friedl (HEPHY Vienna): SVD Schedule

  14. Mechanics Schedule • Overview: • Overall design is completed • Ladder mounts to be finalized by end of 2012 • Carbon fiber rib prototypes now being produced • Support cone prototypes in August 2013 • End flange prototype by March 2013 • Detailed SVD mockup by March 2013 • See slides from recent SVD-PXD meeting for more details: http://indico.mppmu.mpg.de/indico/getFile.py/access?contribId=2&sessionId=2&resId=0&materialId=slides&confId=1877 M.Friedl (HEPHY Vienna): SVD Schedule

  15. Sensors Ladder Production Mechanics Cooling Electronics Summary M.Friedl (HEPHY Vienna): SVD Schedule

  16. Cooling • CO2 system in Belle II does not need inspection by Japanese government (capacity is too small) • Will be operated by the KEK cryogenics experts • Cooling Mockup at DESY • Operated with XFEL CO2 unit (similar to MARCO which will become available by the end of 2012) • Distribution & Routing of cooling pipes • Number of lines is defined • First design for manifolds and routing exists • 2 options for transfer lines (3 pipes in larger one or pipe-in-pipe) • APV25 cooling contact is converging M.Friedl (HEPHY Vienna): SVD Schedule

  17. Sensors Ladder Production Mechanics Cooling Electronics Summary M.Friedl (HEPHY Vienna): SVD Schedule

  18. Front-End Electronics Schedule prototypes successfully tested design submitted prototypes available designed but not yet ordered prototypes tested  ok design very similar to +z L4-6  soon! M.Friedl (HEPHY Vienna): SVD Schedule

  19. Back-End Electronics Schedule • FADC: circuit design done, now to CAD & PCB layout • Then surrounding system components (controller, backplane, …) • Prototype system in Q1/2013 • Firmware development in parallel M.Friedl (HEPHY Vienna): SVD Schedule

  20. Sensors Ladder Production Mechanics Cooling Electronics Summary M.Friedl (HEPHY Vienna): SVD Schedule

  21. Summary • Lots of progress in all fields • Detailed (and maintained) schedule available on the web • Sensors • all deliveries to be completed in 2013 • Ladder assembly • Prototype ladder in early 2013, series production in late 2013 • Mechanics • Overall geometry solved, now optimizing details • Cooling • Mockup tests at DESY • Electronics • FADC layout in progress M.Friedl (HEPHY Vienna): SVD Schedule