Overview and Scrutiny. Outline of Procurement Processes Contract Monitoring Single Tender Actions and Waivers. PROCUREMENT PROCESSES . Identify Contract Need (PID) Review Contract Provision Amend Spec If Required Framework Agreement (OGC, FireBuy, Blue Light, Regional Collaboration)
E N D
Overview and Scrutiny • Outline of Procurement Processes • Contract Monitoring • Single Tender Actions and Waivers
PROCUREMENT PROCESSES • Identify Contract Need (PID) • Review Contract Provision • Amend Spec If Required • Framework Agreement (OGC, FireBuy, Blue Light, Regional Collaboration) • CSO 15 Restrictions • Timescales - Determined by Process OJEU (6-9 months) Full Tender (3-6 Months), Mini Tender (2-3 Months), Collaboration (variable)
OJEU Tendering Process • OJEU Process - 6/9 months • Agree evaluation criteria – part of the notice • Determine if straight to tender or requesting expressions of interest (PQQ) • Determine Time Table i.e. tender to be issued, tender return date, tender evaluation, Interview date, award of contract (TUPE, CFA) • Finalise Documentation
OJEU Tendering Process cont’ • Agree Specification • Complete OJEU notice, place on website • Advertise contract on SECE website and/or specialist publications • Complete Register, Expressions of Interest • Competitive Dialogue (before final tenders) • Despatch Tender Documents • Closing Date For Submissions • Open & Evaluate Tenders • Challenge Processes
OJEU Tendering Process cont’ • Interview Process • Select Overall Best Provider (MEAT) • Consider Standing Orders • Award Contract • Complete award of contract notice OJEU website • Finalise contract documents
Non OJEU Contracts The processes is the same as OJEU, however no need for the tender to be advertised on the OJEU website.
FRAMEWORK AGREEMENTS CSO 15 • All Office Government Commerce (OGC) • All Central Buying Consortium (CBC) • All FireBuy Contracts • Mini Tender Process
COLLABORATION • Thames Valley Cluster • South East Region • Regional Procurement Strategy • RPE, PPE, Work-Ware, Appliances, IT Solutions, Property, Utilities, Agency/Consultancy, Training, Occ Health, Insurance, Smoke Alarms
Tendering Process – Projects Premises Projects – (Capital and Revenue) • Babcock provided with project briefing sheet • Design meeting with surveyor and PFM • Outline feasibility proposal submitted and discussed with PFM and Customer
Tendering Process – Projects • Feasibility agreed, tender documents prepared by surveyor • Tenders sent out by Surveyors in line with standing orders, using the approved supplier listing • Tenders returned to RBFRS in line with standing orders • Open Tenders returned to Surveyor for evaluation
Tendering Process – Projects • Tender Evaluation returned with recommendations • Contractors Selected • RBFRS raise purchase orders • Contract issued for approval by Contractor and return to RBFRS • Initial pre- start project meeting
Tendering Process - Projects • Commencement of project • Future review of project meetings arranged • Project completed • Snagging undertaken
Contract Monitoring From Award of Contract - Arrange implementation meeting with supplier for commencement of contract • Agree programme of monthly, quarterly and annual contract review meetings - Agree method of reporting Key Performance Indicators Monitor and Manage
Contract Monitoring Cont’ Monthly review meetings – • RBFRS contract manager i.e. Senior Accountant + contractors day to day contract manager. PFM would attend the 1st meeting of the contract Quarterly review meetings – • RBFRS contracts manager + i.e. Treasurer +senior contracts manager Annual Contractual Review meeting – • As above, + Procurement & Facilities Manager + Director of contractor
Contract Monitoring Cont’ Format of meetings • Agenda standing items • Agree minutes of last meetings • Update on items outstanding • Key performance indicators • Any Other business
WAIVERS • 3 Waivers to Standing Orders 12 months • Grounds Maintenance Contract • Cleaning Contract • Training Centre Refurbishment