Financing Projects in the Energy Infrastructure Louis Borgo Senior Banker, Power & Energy Utilities Bucharest, Romania 4 th April 2006. Content. About the EBRD Power and Energy Utilities Reform and Restructuring Example Projects. A network of 32 offices in 27 countries. EBRD Facilities.

gaia
Download Presentation

Financing Projects in the Energy Infrastructure Louis Borgo Senior Banker, Power & Energy Utilities Bucharest, Roman

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Financing Projects in the Energy InfrastructureLouis BorgoSenior Banker, Power & Energy UtilitiesBucharest, Romania4th April 2006

  2. Content About the EBRD Power and Energy Utilities Reform and Restructuring Example Projects

  3. A network of 32 offices in 27 countries

  4. EBRD Facilities Loans Equity Guarantees • Partial risk guarantees(e.g. political) • Extension of loan maturities • Non/partial recourse to sponsors • Project specific • Hard/local currency • Medium and long term • Floating/fixed rates • New equity • Privatisation • Quasi-equity

  5. Our Clients in the Energy Field

  6. Content About the EBRD Power and Energy Utilities Reform and Restructuring Example Projects

  7. Power & Energy Utilities - Objectives • Support sector reforms • Accelerate competition & market liberalisation • Foster privatisation & private investment • Finance reinforcement of grid & inter-connection • Prioritise environmental & energy efficiency investments

  8. Power & Energy Utilities – Key Issues • Evolving regulatory environment and market • Subsidised tariffs: high energy consumption • Market Infrastructure: Critical under-investment • Ageing assets, low efficiency, high losses • Environmental standards

  9. Content About the EBRD Power and Energy Utilities Reform and Restructuring Example Projects

  10. Sector and Tariff Reforms are Essential to Mobilise Financing and Investment Needed: a combination of • Price reform, accompanied by measures that provide social protection for the vulnerable, • Measures to raise collection rates • Introduction of new institutions designed to provide appropriate regulatory supervision • Tariff reform and clear regulations, free of political interference, will attract long term Strategic Investors

  11. Why Power Sector Reform? • Increase efficiency • Technical and non-technical losses • Commercial discipline • Put sector on a sound financial basis • Cost-covering tariffs • Access to finance for maintenance and rehabilitation • Consumer satisfaction • Reliable service at lower cost

  12. Why tariff reform? • Ensure financial sustainability • Attract private know-how and investment • Incentives to conserve energy

  13. Reform elements • Tariffs that cover costs • No cross-subsidies • Predictable, transparent adjustment mechanism • With incentives for efficiency improvements • Transparent, on-budget support for poor consumers

  14. Implications for the poor • Tariff reform is crucial… • … but we need to know impact on the poor • Provide targeted support… • …rather than delay tariff reform • Efficiency gains can soften the blow • Regional trade • Energy efficiency and conservation

  15. Role of EBRD • EBRD assesses affordability in all its infrastructure projects • SEEREM study is the most detailed analysis to date • Collaboration with other organisations • Other IFIs have a comparative advantage on poverty issues

  16. Content About the EBRD Power and Energy Utilities Reform and Restructuring Example Projects

  17. Power and Energy Portfolio in SEE region Pioneering approach: • Developing IPPs in region: • Maritza East 3 - € 648m first private power sector generation project and largest foreign direct investment to date in Bulgaria • Maritza East 1 - Bulgaria • Equity Investment alongside western sponsor (Moldova, Romania) • Assisted privatisation of distribution companies (Moldova, Bulgaria, Romania, FYR Macedonia) • Pioneer: First loans to Serbia & Montenegro electricity sector • First cross-border transmission line: Bulgaria-Macedonia

  18. Moldova: Distribution Privatisation • Government of Moldova (GoM) privatised three power distribution companies (REDs) to Union Fenosa (UF), in 2000 • EBRD provided € 5m equity, valued at same price per share paid by UF, for 19.9% stake in REDs; with a Put right attached • EBRD also provided € 25m, limited recourse debt financing, with 10 years maturity • UF agreed on a Contingent Performance Support until REDs achieve performance targets on losses and collections for a full year; and completed the minimum portion of the investment plan agreed with GoM

  19. Romania: Investing in Gas Distribution Distrigaz Sud • EUR 31 million equity investment representing 5.1% beneficial ownership in Distrigaz Sud • Company privatised in 2004 to Gaz de France

  20. Bulgaria: Maritza East III • FGD and rehabilitation at Maritza East III Power Plant • 840MW, mine-mouth lignite-fired, providing 7% of Bulgaria's installed capacity • JVC ownership at financial close: 27% NEK, 44% Enel Produzione S.p.A, 29% Entergy Power Maritza Holding BV • PPA covering construction and further 15 years • Long-term take-or-pay Lignite Supply Agreement • Government Support Undertaking

  21. Bulgaria: Maritza East III

  22. Bulgaria: Argos Wind Energy Park • Project Cost – EUR 770,000; • Loan Amount – EUR 600,000; • KIDSF Incentive – EUR 120,000; • Payback Period – 5.07 years; • Installed Capacity – 1.20 MWe; • Electricity Production – 3.9 GWh/year; • Electricity Price – 61.36 EUR/MWh • CO2 Emissions Reduction - 3,084 t/year.

  23. EBRD contact Marko Kecman Principal Banker Power & Energy Utilities Telephone: + 40 21 202 7138 Fax: + 40 21 202 7110 e-mail: kecmanm@buh.ebrd.com Louis Borgo Senior Banker Power & Energy Utilities Telephone: + 44 207 338 6547 Fax: + 44 207 338 7280 e-mail: borgol@ebrd.com

  24. EBRD Annual Meeting & Business Forum 2006 Business development opportunities from Central Europe to Central Asia Sunday 21 – Monday 22 May London A unique opportunity to meet leading investors, bankers, entrepreneurs and senior government officials