An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Intersection Control Evaluation (ICE)

  2. Outline • Background • ICE Process • Impacts • Current Status

  3. Background • Signal Justification Reports • Completed during final design • Document warrants • Straightforward, but no consideration of other alternatives

  4. Background • Increased Traffic Control Options • All-way stop • Signal • Roundabout • Access Management • Grade Separation • Non-Traditional • Continuous flow • Michigan left

  5. Background • Need process to analyze intersection traffic control options • Document analysis and selection of preferred alternative

  6. Why Change? • All intersection control decisions documented • Early decisions help limit scope creep • Improve coordination and collaboration with local agencies • All intersection control options considered on an equal basis

  7. The ICE Process • Required on all trunk highways • State-Aid is considering adoption • Not required for two-way stop or uncontrolled intersections • Written by licensed engineer • Approved by the District Traffic Engineer

  8. The ICE Process • Goal: • Consider technical, financial, and political aspects of each control alternative • Select optimal intersection control

  9. The ICE Process • Phase 1- Scoping • Complete as early in the project development process as possible • Can occur prior to project programming • Determine feasibility of traffic control options • Phase 2- Alternative Selection • Layout development • Identify recommended traffic control

  10. The ICE Process

  11. The ICE Process • Phase 1- Scoping • Conduct a technical analysis of options • Initial public acceptability of options • Interim report and recommendations

  12. The ICE Process • Phase 1- Scoping • Warrant analysis • Traffic volumes (vehicle/pedestrian/bicycle), crash history, delay • All-way stop • Signal • Roundabout considered warranted if meets either AWS or signal warrants

  13. The ICE Process • Phase 1- Scoping • Justification • Safety • Congestion • Intersection spacing • Future traffic volumes • Percentage of turning traffic • Vehicle types and percentages • Sight distance • Right of Way • Available funds • Local support

  14. The ICE Process • Phase 1- Scoping • Crash Evaluation • Crash diagram with most recent 3 years of data for existing intersections • Estimate anticipated crashes for each traffic control alternative • Calculate crash reductions per year • Calculate crash cost reduction per year

  15. The ICE Process • Phase 1- Scoping • Capacity Evaluation • Existing AM and PM peak hour volumes • Design year AM and PM peak hour volumes • Existing and design year pedestrian and bicycle volumes • Design vehicle • Horizontal, vertical, and site constraints • District Traffic Engineer to determine acceptable level of analysis (including software)

  16. The ICE Process • Phase 1- Scoping • If only one viable alternative comes out of Phase 1, ICE is complete • For corridor or planning study, Phase 1 evaluation may be sufficient • District Traffic Engineer to determine appropriate level of analysis for each project

  17. The ICE Process • Phase 1- Scoping • Preservation projects and signal revisions still require memo/letter to be submitted for approval • All decisions and evaluation should be documented in final ICE report

  18. The ICE Process • Phase 2- Alternative Selection • Develop conceptual layouts • Determine ROW impacts and estimated costs • Estimate construction costs • Assess public involvement and acceptance • Prepare final ICE document

  19. The ICE Process • Phase 2- Alternative Selection • Other considerations • Skew angle • Offset approaches • Odd number of approaches • Closely spaced intersections • Approach grades

  20. The ICE Process • Phase 2- Alternative Selection • More detailed capacity analysis • AWS- Synchro/SimTraffic • Signals- Synchro/SimTraffic • Roundabouts- RODEL • Roundabouts in series or roundabouts within traffic control system- VISSIM

  21. The ICE Process • Phase 2- Alternative Selection • RODEL is a roundabout design tool (empirically based) • Synchro/SimTraffic and VISSIM are analysis tools (gap acceptance based)

  22. The ICE Process • Phase 2- Alternative Selection • Other considerations • Coordinated signal systems • Interregional Corridors (IRC) • Compare to recommendations of corridor study • Address impacts on IRC performance

  23. Mn/DOT Impacts • Dependent upon two major factors • Project origin • Size and/or type of project • For internal project, Mn/DOT completes analysis and ICE report • For external project, outside agency or consultant completes ICE • District makes decision on the scope/detail of the analysis

  24. Mn/DOT Impacts • Internal Project Roles • Capacity and safety analysis (Traffic) • Public involvement (District) • Conceptual layouts and impacts (Design) • Final report documentation (Traffic)

  25. Other Impacts • Program and Project Management System (PPMS) modification • New software and training • Increased internal and external coordination • Districts document their process (warrants and justification)

  26. Current Status • Technical Memo No. 07-02-T-01 (03/20/07) • Actions in Metro • Purchase of Rodel and VISSIM • Drafting a detail of “how to” complete and ICE study • Simplifying the capacity analysis

  27. Current Status • Actions in Metro • Reviewing ICE documents • Timing of implementation (FY 2008)

  28. QUESTIONS?