10 likes | 113 Views
Immediate work plan to relocate and organize lab, re-operate panels, conduct 1D and 2D position scans, gather components, assemble and install system for signal testing. First studies aim to replicate AA measurement by November.
E N D
Tel Aviv immediate work plan • Relocate and organize the lab • Re-operate the panel • signals on the scope – early next week • 1D position scan (VME scalar) - next week • 2D scan (VME scalar) - after the 1D position scan • MicroDAQ • Teishengand J gathered all the components (except for the KvaserPCIcan) for the system – Erez should bring with him - this weekend • Buy the missing piece – next week • Assemble and install the system • First studies should reproduce a measurement done in AA – hopefully November • Test bench (cosmic & source) – after we get the system working We have two panels (Ni-Ni and SnO2-Ni)