1 / 11

Valley Import Overview Jeff Billo Regional Planning Group Meeting July 22, 2014

Valley Import Overview Jeff Billo Regional Planning Group Meeting July 22, 2014. Outline. Valley Overview Future Transmission System Needs Discussion and Next Steps. Valley Overview - 2014. Valley Interface. 6. 2. 3. 7. 5. 1. 4. 1769. 300. 600. Gas. Wind. DC-Tie.

eunice
Download Presentation

Valley Import Overview Jeff Billo Regional Planning Group Meeting July 22, 2014

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Valley Import Overview Jeff Billo Regional Planning Group Meeting July 22, 2014 Preliminary

  2. Outline • Valley Overview • Future Transmission System Needs • Discussion and Next Steps Preliminary

  3. Valley Overview - 2014 Valley Interface 6 2 3 7 5 1 4 1769 300 600 Gas Wind DC-Tie Preliminary

  4. Valley Transmission - 2016 6 2 3 7 5 1 4 1769 300 600 Gas Wind DC-Tie Preliminary

  5. Background Information • ERCOT Board endorsed Valley Import Project in September 2011 • ERCOT Independent Review indicated that additional reliability upgrades would be needed by 2020 to support import needs • FERC Final Rule on TPL-001-4 effective December 23, 2013 • Adds G-1+G-1 criterion to NERC planning standards (Category P3 contingency) • No loss of load allowed • Corrective Action Plan for “raise the bar” requirements do not have to be in place until 2020 • ERCOT annual stability analysis identified reliability criteria violations in the Valley Preliminary

  6. Valley Load Forecast (2014 RTP) Preliminary

  7. Valley Import Study • Study Case • 2016 Summer Peak (SSWG, March 2014) • Base Case Condition • All Valley Gas Generation at Pmax • Lobo – North Edinburg 345 kV in service (with series capacitor) • North Edinburg – Loma Alta (Cross Valley) 345 kV in service • Valley Wind Output = 10% dispatch • Railroad DC-Tie no import/export • Steady State PV Analysis Preliminary

  8. VSAT Results • Base Case Notes: • G-1includes entire combined cycle train • N-1 includes 345 kV transmission line • Dynamic analysis results (ongoing work) may show stability limits lower than in the above table Preliminary

  9. Discussion • N-1+N-1 and G-1+G-1 are the significant contingencies for the Valley • Entire combined-cycle train is treated as G-1 in this assessment (consistent with Planning Guide 4.1.1.1) • ERCOT is working on dynamic stability analysis • ERCOT will work with area TSPs and RPG to evaluate project alternatives to address the reliability need • Static and/or dynamic reactive devices • Ajo – Caballo 345 kV line (suggested in 2011 ERCOT Independent Review) • San Miguel – Lobo – North Edinburg second circuit • Additional import path • Railroad DC tie assumption Preliminary

  10. Valley Potential Gen (by County), COD by 2016 200 6 399 200 230 500 2 3 7 5 1 268 4 1601 1769 600 300 200 1198 2000 Gas Wind DC-Tie PG 6.9 Wind FIS Wind FIS Gas Preliminary

  11. Questions/ Comments? Preliminary

More Related