350 likes | 578 Views
2. Overview. WBS to Schedule ProcessPERTSchedule TypesCPM. 3. Scheduling. A schedule is the conversion of a project action plan into an operating timetableIt serves as the basis for monitoring and controlling project activityTaken together with the plan and budget, it is probably the major too
E N D
1. 1 Project Management: A Managerial Approach Chapter 8 – Scheduling
2. 2 Overview WBS to Schedule Process
PERT
Schedule Types
CPM
3. 3 Scheduling A schedule is the conversion of a project action plan into an operating timetable
It serves as the basis for monitoring and controlling project activity
Taken together with the plan and budget, it is probably the major tool for the management of projects
4. 4 Scheduling In a project environment, the scheduling function is more important than it would be in an ongoing operation
Projects lack the continuity of day-to-day operations and often present much more complex problems of coordination
5. 5 Scheduling The basic approach of all scheduling techniques is to form a network of activity and event relationships
This network should graphically portray the sequential relations between the tasks in a project
Tasks that must precede or follow other tasks are then clearly identified, in time as well as function
6. 6 Scheduling Such networks are a powerful tool for planning and controlling a project and have the following benefits:
It is a consistent framework for planning, scheduling, monitoring, and controlling the project
It illustrates the interdependence of all tasks, work packages, and work elements
It denotes the times when specific individuals must be available for work on a given task
7. 7 Scheduling Network benefits (cont.):
It aids in ensuring that the proper communications take place between departments and functions
It determines an expected project completion date
It identifies so-called critical activities that, if delayed, will delay the project completion time
It identifies activities with slack that can be delayed for specific periods without penalty
8. 8 Scheduling Network benefits (cont.):
It determines the dates on which tasks may be started - or must be started if the project is to stay on schedule
It illustrates which tasks must be coordinated to avoid resource timing conflicts
It illustrates which tasks may run, or must be run, in parallel to achieve the predetermined project completion date
It relieves some interpersonal conflict by clearly showing task dependencies
9. 9 Simple Schedule – Gantt Chart
10. 10 Network Techniques: PERT and CPM With the exception of Gantt charts, the most common approach to scheduling is the use of network techniques such as PERT and CPM
The Program Evaluation and Review Technique (PERT) was developed by the U.S. Navy in 1958
The Critical Path Method (CPM) was developed by DuPont, Inc during the same time period
11. 11 Network Techniques: PERT and CPM PERT has been primarily used for research and development projects
CPM was designed for construction projects and has been generally embraced by the construction industry
The two methods are quite similar and are often combined for educational presentation
12. 12 Scheduling Terminology Activity - A specific task or set of tasks that are required by the project, use up resources, and take time to complete
Event - The result of completing one or more activities. An identifiable end state occurring at a particular time. Events use no resources.
Network - The combination of all activities and events define the project and the activity precedence relationships
13. 13 Scheduling Terminology Path - The series of connected activities (or intermediate events) between any two events in a network
Critical - Activities, events, or paths which, if delayed, will delay the completion of the project. A project’s critical path is understood to mean that sequence of critical activities that connect the project’s start event to its finish event
14. 14 Scheduling Terminology An activity can be in any of these conditions:
It may have a successor(s) but no predecessor(s) - starts a network
It may have a predecessor(s) but no successor(s) - ends a network
It may have both predecessor(s) and successor(s) - in the middle of a network
Interconnections from horizontal links in vertical WBS
15. 15 Hypothetical Network
16. 16 Activity and Project Frequency Distributions
17. 17 PERT Activity Calculation
18. 18 PERT Schedule Probability
19. 19 PERT Activity Times & Variances
20. 20 Variance of Activity Estimates
21. 21 Critical Path
22. 22 Possible Project Durations
23. 23 Z Table
24. 24
25. 25 Gantt Charts The Gantt chart shows planned and actual progress for a number of tasks displayed against a horizontal time scale
It is an effective and easy-to-read method of indicating the actual current status for each set of tasks compared to the planned progress for each item of the set
It can be helpful in expediting, sequencing, and reallocating resources among tasks
Gantt charts usually do not show technical dependencies
26. 26 Gantt Charts There are several advantages to the use of Gantt charts:
Even though they may contain a great deal of information, they are easily understood
While they may require frequent updating, they are easy to maintain
Gantt charts provide a clear picture of the current state of a project
They are easy to construct
27. 27 Drawing Networks Activity-on-Arrow (AOA) networks use arrows to represent activities while nodes stand for events
Activity-on-Node (AON) networks use nodes to represent activities with arrows to show precedence relationships
The choice between AOA and AON representation is largely a matter of personal preference
28. 28 Drawing Networks
29. 29 Hypothetical Network
30. 30 AOA Network Building Blocks
31. 31 Partial Koll Business Center - AOA
32. 32 Partial AOA Network
33. 33 Partial AOA Network
34. 34 Full AOA Network
35. 35 Activity-on-Node Network Fundamentals