Update presentation to the WMKO Science Steering Committee Ian McLean, Chuck Steidel, Sean Adkins November 3, 2008. MOSFIRE Multi-Object Spectrometer For Infra-Red Exploration. Cassegrain focus of Keck 1 Wavelengths: 0.975-2.40  m

esusan
Download Presentation

MOSFIRE Multi-Object Spectrometer For Infra-Red Exploration

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Update presentation to the WMKO Science Steering Committee Ian McLean, Chuck Steidel, Sean Adkins November 3, 2008 MOSFIREMulti-Object Spectrometer For Infra-Red Exploration

  2. Cassegrain focus of Keck 1 Wavelengths: 0.975-2.40 m Resolving power (R) > 3,200 for a slit width of ~0.7 (2.9 pixels) Optics allow up to 46 x 7.0 slits over entire 6.14 x 6.14 FOV Imaging field of 6.8 diameter projected onto a 6.14 square 2K x 2K HgCdTe detector with 0.18 pixels; 5e- noise Cryogenic Slit Unit (CSU) reconfigurable under computer control without thermal cycling in < 5 mins. Independent CCD Guider Cost-capped project ($12.3M) Summary of Design Requirements Arguably, most challenging IR instrument to date.

  3. Summary of Project Status • Significant progress since June 2008 • Several challenging problems resolved • Major milestones achieved • MOSFIRE is now in Integration & Testing (Year 4) • On-target for first cool down early December 2008 • Running ~6 months behind original DDR schedule • Still within budget, but remaining contingency tight • Outstanding team; successful joint operation among CIT, UCSC, UCLA and WMKO

  4. Milestones Achieved • Rotator module aligned at Keck I Cass, delivered to CIT, installed in modified ESI stand and now in use for I&T • Dewar shell & internal structure pumped and baked out; MLI, CCRs, thermal wiring & dummy camera installed • CSU complete; ready for cryogenic testing at CERN • Lens coating issues apparently resolved: 10 of 13 science optics delivered to UCLA; all other optics (guider, folding flats, windows, grating & filters) in hand; lens mounting procedures refined • Mechanisms (Grating, Pupil, Filter, Flexure Compensation) built; all pass warm tests; detector focus mechanism in fab • Science grade detector received; ASIC-driven engineering grade detector achieves <6 e- rms with Fowler Sampling Some details follow …

  5. Rotator Module • Rotator Module • Built by UCO/Lick • Aligned on Keck 1 • Received at CIT and installed in modified ESI stand • Drive system installed by UCO/Lick • In use for instrument assembly and test

  6. Dewar Assembly • Dewar assembled with internal structure (Bulkheads A & B) & laminate thermal stand-off tube • Pumped down: trapped water and other contaminants found • Initiated a long (6 weeks) vacuum bake out with cold trap and residual gas analyzer - successful

  7. Dewar Vacuum Testing • Finally reached ~1E-5 Torr at room temperature • Contaminant identified • JPL lab analyzed sample of “goo” found in cold trap as part of a “common lubricant” • Source of contamination found during disassembly: • Insufficient cleaning to remove cutting fluid from front barrel shield at weld joints & pockets for cable penetrations • Insufficient cleaning of laminate tube HeliCoil inserts to remove grease used for assembly • All parts successfully re-cleaned at CIT

  8. Installation of MLI and CCRs • Multi-layer insulation (MLI) has now been added • Subcontract to SDL • Thermal straps for CCRs installed • Dummy camera with cross hairs installed • Thermal wiring (temperature sensors and heaters) installed • CCR Heads (pair) being installed now

  9. CSU Status • The CSU is fully assembled and undergoing acceptance testing • Warm tests meet specification • Horizontal position • Vertical position • Ready for cryogenic testing at CERN (this week) • We are sending a computer to enable remote testing of the operation of the MOSFIRE CSU server with the CSU controller software (this month) • Due: late December/early January

  10. Optics Status • Warm optics complete • guider doublets bonded (all at CIT) • Science optics in coating • 10 lenses coated & shipped to UCLA • Typical reflectance <0.6% per surface from 0.97-2.40 m • As-built grating and filters meet spec • QC problems at coating vendor seem to be resolved • Poor adhesion due to improper cleaning • Regrinding & polishing done; 3 lenses left to coat or recoat • Cryo-testing of lenses in progress

  11. Grating Shim Proximity Sensor Cryo-Mechanisms • Grating turret with dummy mirror and dummy grating; proximity sensor installed for testing; cryo-motor installed • Excellent preliminary results on warm test repeatability of this mechanism 0.04-0.06 pixels(0.1 pixels was goal)

  12. Cryo-Mechanisms • Pupil Mechanism • Warm testing complete • Filter Wheel • Warm testing resumed • Flexure Control mechanism • Warm & Cold testing complete • Detector Head Focus mechanism • Prototyped; final unit in fab

  13. Science Detector Initially 4 devices; accepted M2; then Teledyne made M5 and gave us the opportunity to switch!

  14. MOSFIRE 5: 2μm Flat/QE map 88±2% QE

  15. ASIC Tests on Eng. Grade 32-channel readout by ASIC Engineering Grade Device Observed Predicted

  16. Status – Electronics/Software • Electronics • On schedule for 1st & 2nd dewar integration milestones • Thermal circuits now installed for first cool down • Glycol cooling for Electronics Cabinet in fabrication • Software • All GUIs in advanced state of development • Hardware servers almost complete, including CSU • Deliverable computers received • Test routines running mechanisms

  17. Remaining Risk • Optics is highest risk now • 3 of 13 lenses left to ship • Cryo testing for coating adhesion in progress • Lenses must be aligned and bonded into their cells • Significant effort on-going to refine alignment and bonding procedures • Careful review and rehearsal prior to optics mounting is continuing • 3D metrology at every step using CMM • Dewar • First cool down will identify any thermal performance issues • Mechanisms • All will be cryo-tested prior to installation • Find and correct problems without major impact to schedule • CSU will be cold tested (at CERN) prior to delivery • Expected delivery late December or early January • Installation scheduled for March 2009 Risk Status Matrix follows …

  18. MOSFIRE Risk Status Orange highlighting flags highest risks

  19. MOSFIRE Schedule Current schedule has been holding.

  20. Budget Summary • Budget • Cost cap = $12.3M ($11.2M + $1.1M contingency; 10% materials, 15% labor; 4.5 project years) • Current estimated cost-at-completion $11.7M • Still within available funding, but significant risk remains • Current budget includes effect of 6 month slip • Anticipated contingency usage • Fabrication cost over-runs • CSU cost overrun (shared with CSEM) • Based on anticipated I&T monthly labor costs of ~$38K per month, funding is available for ~9 months additional labor beyond current First Light date of March 31, 2010