1 / 26

BPA Rooftop Unit Research and Pilot Programs

BPA Rooftop Unit Research and Pilot Programs . Update for Regional Technical Forum April 7 th , 2009 Jack Callahan Bonneville Power Administration. BPA/EWEB/PECI Premium Ventilation Package 2008 – 2009 field tests with detailed pre/post metering 2 sites, 4 RTUs

erwin
Download Presentation

BPA Rooftop Unit Research and Pilot Programs

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BPA Rooftop Unit Research and Pilot Programs Update for Regional Technical Forum April 7th, 2009 Jack Callahan Bonneville Power Administration

  2. BPA/EWEB/PECI Premium Ventilation Package • 2008 – 2009 field tests with detailed pre/post metering • 2 sites, 4 RTUs • BPA/PNNL /State of Washington Smart Monitoring and Diagnostic System • Field test of concept and energy savings • 44 meters installed July 2008 • SMDS units fall 2008 – spring 2009. • Analysis and reporting will be completed by December 2009 • BPA/PNNL development of self-correcting HVAC diagnostics • RTF Rooftop Unit subcommittee Current BPA RTU Research

  3. Completed BPA 2008 AirCare Plus Pilot • 63 Rooftop Units Serviced • 27 units with ~ 2 weeks pre/post metering. • Planned 2009 RTU Pilot • Summer of 2009 • 600 Rooftop Units • 2 to 4 Program Delivery Contractors • Pre/Post metering for 120 + units • Use, test and develop M&V Protocol • Planned 2010-2012 regional RTU servicing programs. Current BPA RTU Pilots

  4. BPA 2008 AirCare Plus SM Pilot Inland Power Kootenai Electric Cooperative City of Cheney City of Chewelah PECI DRS Mechanical BPA

  5. Opportunity in Spokane • June – October 2008 • Service on 63 RTUs at 25 businesses • Metering and analysis for 27 RTUs 2008 AirCare Plus Research Project

  6. Servicing RTUs and split systems ranging in size from 3 to 60 tons • HVAC Service Assistant™ • Economizer diagnostics • Programmable Thermostats PECI AirCare Plus enhanced maintenance service AirCare Plus SM

  7. AirCare Plus Measures

  8. 2008 AirCare Plus SM Servicing

  9. 4 participating utilities • 21 sites visited • 63 units serviced • 27 units metered • 247 measures completed • $15,530 Incentives paid • $13,077 program delivery cost 2008 RTU Pilot Summary

  10. Sampling Plan • At least 20 RTUs • Time and Cost are main drivers • Erik Boyer, BPA: Metering Installation and Data Collection • Onset HOBO U-30 GSM Loggers • Temp/RH Sensors • Outside Air, Supply, Return, Mixed Air • RTU Total kWh • T-Stat (Y1) call for cooling • 1 to 2 weeks pre/post metering • 1-minute interval data RTU Metering

  11. RTU Metering

  12. Measured Energy Savings

  13. Questions?

  14. BPA 2009 RTU Service Pilot Preview for Regional Technical Forum April 7th, 2009 Jack Callahan Bonneville Power Administration

  15. Summer of 2009 • 600 Rooftop Units • Up to 20 utilities • 2 to 4 Program Delivery Contractors (PDC) • Pre/Post metering for 120 + units • Use, test and develop M&V Protocol 2009 RTU Service Pilot

  16. April 10, 2009 - Final selection of utilities • May 1, 2009 - Final selection of PDC’s • May 2009 - Pilot Kick-off meetings • July – Nov - 600 RTU's serviced 2009 RTU Service Pilot Projected Timeline

  17. Questions?

  18. Rooftop Unit Opportunity Jack Callahan Bonneville Power Administration Presented to Regional Technical Forum April 7th, 2009

  19. 500,000 + RTU’s in the region • Known problems • Known fixes • Scalable Solutions Existing RTUs

  20. Palm Pilot tool Flow plate RTU Tools & Techniques rik

  21. Economizer • Refrigerant cycle • Thermostat • Other Rooftop Unit (RTU) Efficiency Optimization Strategies

  22. Measured Energy Savings • RTF M & V protocols • Feedback to Service Providers Research and Pilot Goals

  23. Ongoing Research • 2008 60 unit Pilot • 2009 600 unit Pilot • RTF approved M&V Protocols • 2010 Region-wide Program BPA Long Term RTU Plan

  24. Questions?