Chapter 5 Project Evaluation: Principles and Methods

Chapter 5 Project Evaluation: Principles and Methods. Learning Objectives. Explain the importance of each of the steps in the capital expenditure process. Outline the decision rules for each of the main methods of project evaluation.

Download Presentation

Chapter 5 Project Evaluation: Principles and Methods

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Chapter 5Project Evaluation:Principles and Methods

  2. Learning Objectives • Explain the importance of each of the steps in the capitalexpenditure process. • Outline the decision rules for each of the main methods of project evaluation. • Explain the advantages and disadvantages of the main project evaluation methods.

  3. Learning Objectives (cont.) • Explain why the net present value method is preferred to all other methods. • Understand the link between economic value added (EVA) and net present value (NPV).

  4. CapitalExpenditure Process • The capitalexpenditure process involves: • Generation of investment proposals. • Evaluation and selection of those proposals. • Approval and control of capital expenditures. • Post-completion audit of investment projects.

  5. Generation of Investment Proposals • Investment ideas can range from simple upgrades of equipment, replacing inefficient exiting equipment, through to plant expansions, new product development or corporate takeovers. • Generation of good ideas for capital expenditure is better facilitated if a systematic means of searching for and developing them exists. • This may be assisted by financial incentives and bonuses for those who propose successful projects.

  6. Evaluation and Selection of Investment Proposals • To enable evaluation of a proposal, it should include the following data: • Brief description of the proposal. • Statement as to why it is desirable or necessary. • Estimate of the amount and timing of the cash outlays. • Estimate of the amount and timing of the cash inflows. • Estimate of when the proposal will come into operation. • Estimate of the proposal’s economic life.

  7. Approval and Control of Capital Expenditures • Capital expenditure budget (CEB) — maps out the estimated future capital expenditure on new and continuing projects. • CEB has the important role of setting administrative procedures to implement the project (project timetable, procedures for controlling costs). • Timing is important, project delays and cost over-runs will lower the NPV of a project, costing shareholder wealth.

  8. Post-completion Audit of Investment Projects • Highlights any cash flows that have deviated significantly from the budget and provides explanations where possible. • Benefits of conducting an audit: • May improve quality of investment decisions. • Provides information that will enable implementation of improvements in the project’s operating performance. • May result in the re-evaluation and possible abandonment of an unsuccessful project.

  9. Methods of Project Evaluation • Methods of project evaluation include: • Net present value (NPV) • Internal rate of return (IRR) • Benefit–cost ratio (profitability index) • Payback period • Accounting rate of return

  10. Project Evaluation Methods Used by the Entities Surveyed Table 5.1: Selected project evaluation methods used by the CFOs surveyed (a) The aggregate percentage exceeds 100 per cent because most respondents used more than one method of project evaluation. Source: Graham, J.R. & C.R. Harvey (2001)

  11. Discounted Cash Flow Methods • Discounted cash flow (DCF) methods involve the process of discounting a series of future net cash flows to their present values. • DCF methods include: • The net present value method (NPV). • The internal rate of return method (IRR).

  12. Net Present Value (NPV) • Difference between the PV of the net cash flows (NCF) from an investment, discounted at the required rate of return, and the initial investment outlay. • Measuring a project’s net cash flows: • Forecast expected net profit from project, making an adjustment for non-cash flow items. • Estimate net cash flows directly.

  13. Calculation of NPV • The standard NPV formula is given by:

  14. Net Cash Flow • Cash inflows: • Receipts from sale of goods and services • Receipts from sale of physical assets • Cash outflows: • Expenditure on materials, labour, and indirect expenses for manufacturing • Selling and administrative • Inventory and taxes

  15. Evaluation of NPV • NPV method is consistent with the company’s objective of maximising shareholders’ wealth. • A project with a positive NPV will leave the company better off than before the project and, other things being equal, the market value of the company’s shares should increase. • Decision rule for NPV method: • Accept a project if its net present value is positive when the project’s net cash flows are discounted at the required rate of return.

  16. NPV Example Example 5.1 • Investment of $9000 • Net cash flows of $5090, $4500 and $4000 at the end of years 1, 2 and 3 respectively. • Assume required rate of return is 10% p.a. • What is the NPV of the project?

  17. NPV Example (cont.) Example 5.1: • Apply the NPV formula given by (5.5). • Thus, using a discount rate of 10%, the project has a NPV = +$2351 > 0, and is therefore acceptable.

  18. Internal Rate of Return (IRR) • The internal rate of return is the discount rate that equates the present value of a project’s net cash flows with its initial cash outlay. • IRR is the discount rate (or rate of return) at which the net present value is zero. • The IRR is compared to the required rate of return (k). • If IRR > k the project should be accepted.

  19. Calculation of InternalRate of Return • By setting the NPV formula to zero and treating the rate of return as the unknown, the IRR is given by:

  20. Multiple and Indeterminate Internal Rates of Return • Conventional projects have a unique rate of return. • Multiple or no internal rates of return can occur for non-conventional projects with more than one sign change in the project’s series of cash flows. • Thus, care must be taken when using the IRR evaluation technique. • Under IRR: accept the project if it has a unique IRR > the required rate of return.

  21. Choosing Between the Discounted Cash Flow Methods • Independent investments • Projects that can be considered and evaluated in isolation from other projects. • This means that the decision on one project will not affect the outcomes of another project. • Mutually exclusive investments • Alternative investment projects, only one of which can be accepted. • For example, a piece of land is used to build a factory, which rules out an alternative project of building a warehouse on the same land.

  22. Choosing Between the Discounted Cash Flow Methods (cont.) • Independent investments: • For independent investments, both the IRR and NPV methods lead to the same accept/reject decision, except for those investments where the cash flow patterns result in either multiple or no internal rate(s) of return. • In such cases, it doesn’t matter whether we use NPV or IRR.

  23. Choosing Between the Discounted Cash Flow Methods (cont.) • Evaluating mutually exclusive projects • NPV and IRR methods can provide a different ranking order. • The NPV method is the superior method for mutually exclusive projects. • Ranking should be based on the magnitude of NPV.

  24. Benefit–Cost Ratio (Profitability Index) • The profitability index is calculated by dividing the present value of the future net cash flows by the initial cash outlay: • Decision rule: • Accept if benefit–cost ratio > 1 • Reject if benefit–cost ratio < 1

  25. Other Methods of Project Evaluation • There are two major non-discounted cash flow methods that are used: • Accounting rate of return method • Payback period method • These methods are usually employed in conjunction with the discounted cash-flow methods of project evaluation.

  26. Accounting Rate of Return • Earnings (after depreciation and tax) from a project expressed as a percentage of the investment outlay. • The calculation involves: • Estimating the average annual earnings to be generated by the project. • Investment outlay (initial or average).

  27. Accounting Rate of Return (cont.) • Fundamental problems of ARR as a basis for project evaluation: • Arbitrary measure — based on accounting profit as opposed to cash flows, depends on some accounting decisions like treatment of inventory and depreciation. • Ignores timing of the earnings stream — no time value of money concepts are applied, as equal weight is given to accounting profits in each year of the project’s life.

  28. Payback Period • The time it takes for the initial cash outlay on a project to be recovered from the project’s after-tax net cash flows. • Decision: • Compare payback to some maximum acceptable payback period. • What length of time represents the ‘correct’ payback period as a standard against which to measure the acceptability of a particular project?

  29. Payback Period (cont.) • Popular because: • It is simple to apply. • It provides information on how long funds are committed to a project. • Weaknesses: • Inferior to discounted cash flow techniques because it fails to account for the magnitude and timing of all the project’s cash flows. • Does not consider how profitable a project will be, just how quickly outlay will be recovered.

  30. Summary of Evaluation Methods • Discounted cash flow methods are superior investment appraisal methods as they account for timing of cash flows and the time value of money. • DCF methods will always give the same accept/reject decision for a conventional project. • In practice, the abovementioned alternative project evaluation methods (most likely payback period) may be used in conjunction with DCF methods: see Table 5.1.

  31. Economic Value Added • Alternative to discounted cash flow methods, accounting rate of return and payback period. • Key factor is the required rate of return. • EVA is the difference between the project’s accounting profit and the required return on the capital invested in the project. • EVA can be improved by increasing accounting profit or by reducing capital employed.

  32. Economic Value Added (cont.) • EVA is given by: • Discounted sum of EVA s equals NPV of project.

  33. Summary • NPV method is recommended for investment evaluation. • NPV is consistent with maximisation of shareholder wealth. • NPV is also simple to use and gives rise to fewer problems than the IRR method —such as non-uniqueness. • Independent projects — accept if NPV > 0, reject if NPV < 0.

  34. Summary (cont.) • Mutually exclusive projects — accept project with the highest NPV. • In practice, other valuation methods such as accounting rate of return, payback period and economic value added are used in conjunction with NPV, despite a preference for DCF methods. • This may be to measure some other effect, like the effect of the project on liquidity — payback period.