1 / 27

Presentation to GDPCR Cost Workshop Alex Wiseman Regulation Director 19 th April 2007

Presentation to GDPCR Cost Workshop Alex Wiseman Regulation Director 19 th April 2007. Agenda. Introduction to NGN Environment for the 5 Year Reset Opex Forecasts Comparative Efficiency Summary. Introduction to NGN. Innovative Business Model.

ellema
Download Presentation

Presentation to GDPCR Cost Workshop Alex Wiseman Regulation Director 19 th April 2007

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Presentation to GDPCR Cost Workshop Alex Wiseman Regulation Director 19th April 2007

  2. Agenda • Introduction to NGN • Environment for the 5 Year Reset • Opex Forecasts • Comparative Efficiency • Summary

  3. Introduction to NGN

  4. Innovative Business Model • NGN has implemented a unique business model based on the principles of Strategic Asset Management, under which the roles of asset ownership/asset management and asset services are unbundled • NGN remains accountable for all asset management including licence and safety case obligations • Competitive procurement process used to select service provider. United Utilities selected on basis of market experience and success in similar utility contracts • UUOL is a special purpose vehicle working exclusively for NGN. Neither CKI nor NGN has any interests in UUOL or its parent • On 1 June 2005, NGN entered into an Asset Services Agreement (ASA) with UUOL to contract out the provision of a wide range of services including • Operation and maintenance of the DN • Delivery of Capex and Repex programmes

  5. NGN Business vision • To be benchmarked by Ofgem and HSE in the top two comparable utilities in: • Customer service • Efficiency • Health and Safety NGN supports the benchmark approach

  6. Business environment for 5 Year Reset

  7. Business Environment – leading to cost pressures • Legislative changes – such as waste, environment (including landfill tax), pensions, noise at work regulations and working at height regulations • Regulatory Changes – notably offtake and interruption reforms - although decision now made, still uncertainty on incentive mechanism and precise implementation mechanism • Real increases in EPC costs – EPC rates forecast to increase by RPI+4% pa driven by predicted shortages of engineers and manpower as a result of large UK infrastructure programmes • Real increases in salary costs – Direct labour costs forecast to increase at RPI +2% pa. Shortages of experienced gas personnel due to an aging workforce resulting in investment in apprentice schemes. Also increase in staff levels and training (eg. 2 years training for network control and 3 years for safety)

  8. Cost Pressures • Real increases in Material costs – General increase in material costs of RPI+2% pa from rising commodity prices in particular oil and oil based goods • Real increase in Energy Costs – Energy costs doubled during 2005/06. Forward curves continue to show significant volatility in market prices • Security - An increasing focus on security of assets due to potential terrorist threats on gas networks • Service improvements – Improvements that NGN is planning to make in its quality of service and safety to achieve the frontier.

  9. Changing Nature of RPI • Annual price changes in the goods and service sectors, 1993 to 2005 • Supermarkets and suppliers of goods produced overseas are seeing inflation below RPI • Service sector firms employing a UK based workforce are seeing inflation above RPI

  10. Opex Forecasts

  11. NGN Performance in Current Review Period Despite upward cost pressures NGN has delivered significant efficiencies in the current review period

  12. Source Data: 2004/5 Ofgem Second Consultation Document 2005/6 & 2006/7 Ofgem Third Consultation Document NGN Performance in Current Review Period NGN • NGN has reduced costs since sale • There is reduced scope for future efficiency savings

  13. Major Forecast Assumptions - Opex • Contractor costs increase by RPI + 2% against a forecast of RPI + 4% • Direct Labour costs increase by RPI + 2% • Material Costs increase by RPI + 2% • All xoserve costs treated as opex in BPQ consistent with current treatment • Shrinkage gas costs based on forward prices in September 06, modest demand increases and a reduction in the shrinkage factor in line with leakage reduction • Pension costs based on latest actuarial valuation

  14. Major Forecast Assumptions - Opex • 98.5% of controlled escapes will be attended within 2 hours on a 24/7 basis across the entire NGN area • External escapes anticipated to reduce by 2% year on year throughout the period but partly offset by increase in internal escapes • Continuation of TMS and UMS metering contracts which act as “fill in” work for emergency workforce (This is now looking very doubtful) • NGN exits SOMSA NSA in 2009

  15. Efficiency Initiatives Since Purchase • £1.9m spent on rationalisation and reducing workforce • Business model has substantially reduced central overheads • Initiatives on decommissioning expensive vehicles, procurement, recycling • Partnership approach to contractors Planned Initiatives • New IR framework • Changing working practices • Vehicle efficiency initiatives • Improved back office processes

  16. Opex Forecast Despite significant upward pressure on input costs NGN is forecasting to deliver efficiencies to hold costs stable in real terms over the plan period.

  17. Capex Forecast

  18. Major Forecast Assumptions - Capex • Contractor, direct labour and material cost increases as per opex • Investment based on existing legislation, policy and procedures • NTS storage available to NGN at zero cost throughout plan period • Network storage deficit position throughout plan period • Capacity designed to meet 1:20 demand criteria in line with 2006 LTDS • Existing numbers of network sensitive loads (ie no programme to actively reinforce the network to remove such loads) • Connections and diversion workload consistent with historic levels – no significant changes to connections market • PAS 55 principles applied

  19. Capex Forecast • Two major LTS projects required in 2011/12 and 2012/13 • IT investment required in early years to replace GTMS and to refresh IS systems

  20. Repex Forecast

  21. Major Forecast Assumptions - Repex • Labour, material and contractor cost increases in line with opex • Iron mains replacement workload based on existing agreement with HSE – 528km per annum abandoned • Selection of pipes for replacement driven by existing HSE risk model • Service volumes based on historic patterns • TMA costs excluded

  22. Repex - Forecast • Major project in 2009 /10 to replace the Catton to Weatherall LTS pipeline due to its deteriorating condition

  23. Comparative Analysis

  24. Results of Ofgem Consultants’ bottom up Analysis • PB Power – Direct Opex: • NGN at the efficiency frontier for 4 out of 5 cost categories • LECG – Support Services Opex: • NGN not identified as being at the frontier in Support Services, but NGN ahead of the median • Allocation issues between support services and direct costs suggests that the benchmarking may not be consistent eg SGN most efficient for support service and least efficient for direct costs • Hence top down benchmarking may be appropriate • PB Power report on Capex and Repex: • NGN at the efficiency frontier for total net repex • Capex projects less suitable to comparative analysis but proposed reduction in forecasts lower than for other IDNs

  25. EE Relative efficiency • Models should pass ‘real world’ test. For example, not clear that % non- domestic customers is a direct cost driver and it is ‘explained’ by customer numbers and volume • Objectively, main cost driver is network length (eg driving repairs and maintenance, emergency costs) • Substantive correlation between network length, customer numbers and volume • Different networks will favour different drivers but given small number of data points, a composite variable seems appropriate • One solution would be network length, customer numbers and volume in ratio 50:25:25 in line with DNO review

  26. Summary

  27. Summary • NGN has a clear focus on efficiency and continuous improvement led by its corporate vision and implemented via its business model. • Resulted in ongoing improvements in efficiency since purchase in June 2005 in an environment of increasing cost pressures. • NGN business plan continuing to contain costs despite exposure to significant above inflation increases • NGN incurred the lowest capital expenditure overspend in 2002-2007 period and is the only GDN to forecast 2006/7 costs below 2004/5 costs. • This achievement reflected in Ofgem Consultants’ analysis that places NGN at or close to the efficiency frontier. • Top down benchmarking using a composite variable the most appropriate approach to set regulatory allowances to maintain the strength of incentives for efficiency and hence lead to customer benefits.

More Related