An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Albanian Motorway ProjectA New Direction Michael Swinford Bechtel International Project Director, Autostrada Transilvania Friday 22nd October 2010

  2. Overview • Four-lane, 61 km motorway, stretching northeast from Rreshen in central Albania to Kalimash on the country's border with Kosovo • Integral part of the Durres to Morine route, currently the largest infrastructure project in the region • The project maximizes Albanian content in staffing, purchasing and subcontracting 2

  3. Tirana Reps Camp Thirre Camp Kukes Camp Tunnel Route 3

  4. Project Key Features • The Project is being implemented as a fast-track process • The challenge is to complete this key infrastructure link in as short a time as possible • Full support of the Client • Team working with GRD • Serious engagement of Albanian institutions • Strong collaboration with the local community 4

  5. 5.5 km long Twin bores; 85 m2 cross section Drilling operations on both bores on both sides of the tunnel (i.e. 4 faces) Drilling and blasting operations based on the New Austrian Tunnel Method (NATM) 2 and 3 boom drills used in the tunnel Volume of Works; Tunnel 5

  6. 55.5 km of road alignment Major quantities: Clearing and grubbing: 565 ha Excavation: 33 million m3 Fill: 13 million m3 Daily excavation approx 70,000 m3 Major equipment includes: 3 crusher plants 6 concrete batch plants 250 trucks 70 excavators Volume of Works; Earthworks 6

  7. 29 bridges in the design, 10 over 80 m high 4.4 km of bridge roadway Beams: 40 m long, weighing 165 t each Placed by launchers or cranes Structural concrete quantity: 365,000 m3 Major equipment includes: 6 tower cranes 1 beam plant 6 concrete plants Volume of Works; Structures 7

  8. 3,700 people employed at peak 2,500 Albanians Training and expertise in all aspects of construction – safety, equipment, specialized software, construction techniques, procurement and contracting standards Employment & Training 8

  9. Size: Number of employees to peak at 3,700 Sheer quantities Terrain: Geography – mountains, river valleys Material ranging from clay and gravel to rock Remote location: Mobilization of people, camps, and equipment Status of existing local roads Fast track completion schedule: Implementing a unit price contract with design being done in parallel with construction Major Challenges 9

  10. Subcontractors & Suppliers • Project actively solicits subcontractor and supplier interest from Albanian companies • Selection factors: • Safety and environmental protection practices • Quality • Experience and performance • Financial stability • Technical capability • Price • Over 90% of Project’s material and subcontract commitments are with Albanian companies 10

  11. Bechtel ENKA JV • BEJV is a joint venture established in 1988 between two major EPC companies; U.S. Bechtel and Turkish ENKA • Engineering News Record: • Bechtel: #1 US contractor since 1998 • ENKA: 37th on the list of top international contractors • Major motorway projects include: • Ankara-Gerede Motorway, Turkey (1986-1998) • Croatian Motorway Project, Croatia (1998-2004) • Autostrada Transilvania, Romania (2003-Present) • Kosovo Motorway Project, Kosovo (2009-Present) 11

  12. Provides a vital connection within Albania and the region, linking the markets to the Adriatic port of Durres Contributes to economic growth as Albania prepares for accession to the EU Creates jobs through: Direct hires Subcontractors Procurement of materials Spurs short and long term economic development through: New and expanded businesses International investment Increased trade and tourism Economic Development 12