1 / 35

Presented by Darrell Nicholas, P. E. Cable Arm Professional Services

CASE STUDIES ON THE USE OF ENVIRONMENTAL CLAMSHELL BUCKETS FOR REMEDIATION OF CONTAMINATED SEDIMENTS. Application of Environmental Dredging Tips Lessons learned from more than 10 years of completing dredging projects with environmental clamshell buckets. Presented by Darrell Nicholas, P. E.

Download Presentation

Presented by Darrell Nicholas, P. E. Cable Arm Professional Services

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CASE STUDIES ON THE USE OF ENVIRONMENTAL CLAMSHELL BUCKETSFOR REMEDIATION OF CONTAMINATED SEDIMENTS Application ofEnvironmental Dredging TipsLessons learned from more than 10 years of completing dredging projects with environmental clamshell buckets Presented by Darrell Nicholas, P. E. Cable Arm Professional Services

  2. Clamshell Advantages • Rapid mobilization with usually lower costs • Equipment and labor readily available in most markets • Handles deep water greater than 40 feet • Some rock and debris handling capability • Much lower water treatment costs Clamshell Disadvantages • Lower production rates usually vs. cutterhead • Need for onshore unloading/transfer facilities, trucks • Loss of volatile organic compounds from open barges • Need for secondary spill containment at transfer points Cable Arm, Inc. June 2005 – p2

  3. Comparison of Water Treatment Needs Environmental Clamshell vs. Cutterhead Cutterhead dredging typically produces 4 to 14 times more water to be treated than clamshell dredging in environmental applications. Cable Arm, Inc. June 2005 – p3

  4. ENVIRONMENTAL CLAMSHELL BUCKET FEATURES

  5. Contaminant – PCBs Concentration Range: 1 to >1000 ppm Area Remediated: 22 acres Volume Removed: 86,400 cubic yds Water Depth: 0 to 30 ft Current: 0 to >4 ft per second Tidal range: 0 to 3 ft (ship traffic) Secondary Turbidity Control: Sheetpile Obstructions: Cobbles, dredge spoil, driftwood, old dock Operations Software: WINOPS Clean-up Goal: 1 ppm St. Lawrence River Remediation ProjectApril – November 2001 Cable Arm, Inc. June 2005 – p5

  6. Removal of 86,600 cy of sediment containing 20,200 lbs of PCBs 98.6% reduction in PCB contaminant levels 4% of the area remained above 10 ppm and was capped. St. Lawrence River Remediation Project Cable Arm, Inc. June 2005 – p6 Source: SLRPP Completion Report, Bechtel, 2002.

  7. St. Lawrence River Remediation Project – Lessons Learned Sections on 25 to 50 ft centers aren’t good enough. Sonar depth positioning wasn’t fast enough to provide on-the-fly updates in production mode. Need a survey point within 1 bucket width of every bite. Source: SLRPP Completion Report, Bechtel, 2002. Cable Arm, Inc. June 2005 – p7

  8. St. Lawrence River Remediation Project – Lessons Learned Accurate starting elevation essential. Real time xy and z positioning required under production conditions. Update bottom elevations as material is removed. Real time operator display of current bucket depth, current bottom depth, and target depth needed. Cable Arm, Inc. June 2005 – p8

  9. Make sure your contract rewards the right things Retain the ability to reject a bid if the contractor cannot demonstrate 100% compliance with the specifications. Don’t be afraid to use a hybrid contracting system that mixes lump sum items with time and material items. Identify and spell out testing and reporting requirements. Provide separate pay items for health and safety support and quality assurance work Don’t under estimate budget and schedule impacts for interfacing with the public and regulators. Include a pay item for contractor support with these issues. Provide a start-up period for training and working out the kinks. Require dry runs and trials of equipment before starting production, particularly with complicated procedures and/or difficult interfaces. Lessons Learned - Contracting Cable Arm, Inc. June 2005 – p9

  10. Contaminant – PCBs Concentration Range: 1 to 150 ppm Area Remediated: 2 acres Volume Removed: 8,000 cubic yds Water Depth: 40 to 60 ft Current: negligible Tidal range: negligible Secondary Turbidity Control: Floating cell w/ short curtain skirt Obstructions: Timber Operations Software: Clamvision – 1st field application Clean-up Goal: 2 ppm White Lake, Michigan – Summer 2003 Cable Arm, Inc. June 2005 – p10

  11. White Lake, Michigan – Summer 2003

  12. White Lake, Michigan - Summer 2003 Lesson Learned and Applied – Obtain a highly accurate survey with no more than a bucket width spacing between sections. Cable Arm, Inc. June 2005 – p12

  13. White Lake, Michigan - Summer 2003 Lesson Learned and Applied – Evaluate Survey Accuracy & Precision Before Dredging - Provided independent QA/QC of surveys for precision and accuracy. - Performed 3 independent surveys on 3 different days. - Evaluated 15 profiles. All profiles fell within an 8-inch vertical band. Cable Arm, Inc. June 2005 – p13

  14. White Lake, Michigan - Summer 2003 Lesson Learned and Applied – Update bottom elevations as dredging progresses Cable Arm, Inc. June 2005 – p14

  15. Lesson Learned and Applied Correlate turbidity measurements with operational practices Result - 100% Compliance with Turbidity Limits Cable Arm, Inc. June 2005 – p15

  16. White Lake, Michigan - Summer 2003 A very simple pie chart – 100% successfully remediated Apparently the first clean closure of a site with PCB contaminated sediment in the Great Lakes region. Cable Arm, Inc. June 2005 – p16

  17. Jacksonville, Florida – Summer 2004 • Contaminant – Coal tar, creosote • Navigational with environmental handling of sediments • Volume Removed: 5,000 cubic yds • Water Depth: 15 to 45 ft • Current: reversible, up to 3 knots • Tidal range: 3 ft • Secondary Turbidity Control: Floating cell w/ short curtain skirt • Obstructions: Poles, tires, etc. • Operations Software: Clamvision • Clean-up Goal: Reach target depth Cable Arm, Inc. June 2005 – p17

  18. Jacksonville, Florida - Summer 2004

  19. Jacksonville, Florida – Summer 2004 Lesson Learned and Applied – Use wash tank, drip pan, dredge cell, and underwater spill containment to reduce sediment resuspension.

  20. Jacksonville, Florida – Summer 2004 Lesson Learned and Applied - Work from high to low where possible. Cable Arm, Inc. June 2005 – p20

  21. Lesson Learned and Applied Perform Quality Control Checks on All Survey Data No dredging has taken place, yet comparing two independent pre-dredge surveys indicates more than one ft of cut or fill in portions of the site!! The alignment of high and low spots was found to be caused by a failure to adjust for sonar latency on one survey. In flat areas, this failure made little difference. On steep side slopes, the difference was significant. Always make and compare at least two surveys. Cable Arm, Inc. June 2005 – p21

  22. Lesson Learned and Applied – Be Prepared to Handle Rock, Debris, and Excess Water on Every Job Cable Arm, Inc. June 2005 – p22

  23. Contaminant – Coal tar Removal of up to 9 ft of contaminated sediment Volume Removed: 4,000 cubic yds Water Depth: 15 to 45 ft Current: Less than 1 fps Tidal range: 5 ft Secondary Turbidity Control: Silt curtain Obstructions: Scrap metal Operations Software: Clamvision Clean-up Goal: Reach target depth Hudson River – Fall 2004 Cable Arm, Inc. June 2005 – p23

  24. Hudson River – Fall 2004 Cable Arm, Inc. June 2005 – p24

  25. Lesson Learned and Applied - Triple check coordinate transforms, datum conversions, and tide settings in the software; these are the most frequent sources of errors. Cable Arm, Inc. June 2005 – p25

  26. Lesson Learned and Applied - Verification by Independent Methods Builds Confidence in Regulators and Public. Cable Arm, Inc. June 2005 – p26

  27. Contaminant – PCBs Concentration – 1 to <50 ppm Approx. 1 acre site Removal of 14 inches of contaminated sediment Volume Removed: <2,000 cubic yds Water Depth: 0 to 20 ft Current: negligible Tidal range: 4 ft Secondary Turbidity Control: Silt curtain Obstructions: Cobbles, boulders, driftwood Operations Software: Clamvision Clean-up Goal: 1 ppm Sherman Reservoir, Massachusetts – Fall 2004 Cable Arm, Inc. June 2005 – p27

  28. Lesson Learned and Applied: Precision dredging requires a crane in top mechanical condition. Precision instrumentation can be wasted on a poorly functioning crane or uncooperative operator. Cable Arm, Inc. June 2005 – p28

  29. Lesson Learned and Applied Have a plan for handling debris and obstructions. Cable Arm, Inc. June 2005 – p29

  30. Lesson Learned and Applied Use a differential global positioning system, bucket and crane instrumentation, tide gauge, and dredging software to track bucket location in 3-D. Don’t swing across clean areas. Cable Arm, Inc. June 2005 – p30

  31. Lesson Learned and Applied • For comparability, sample & test sediments using the same methods before & after dredging. Determine sampling locations & depths precisely, before & after. • Unless comparable methods are used in the same x-y location, dredging effectiveness cannot be accurately evaluated. Cable Arm, Inc. June 2005 – p31

  32. Lessons Learned and Applied Provide time in the project schedule to train crane operators to use new instrumentation and procedures for precision dredging. Cable Arm, Inc. June 2005 – p32

  33. Lesson Learned and Applied Involve the crew. Track project status on a real-time basis and provide daily updates. Provide feedback that includes both successes and areas for improvement. Establish realistic performance expectations. Cable Arm, Inc. June 2005 – p33

  34. Sherman Reservoir – Fall 2004 Another Site 100% Successfully Remediated Applying the lessons learned from past environmental dredging experience can produce results that are easy to explain to your clients, to the public and to the regulators. Cable Arm, Inc. June 2005 – p34

  35. Structure your contract to procure the right equipment operated by well-qualified personnel using the correct techniques by rewarding safe, efficient, high quality performance that achieves your well-defined project goals. To Summarize the Lessons Learned Cable Arm, Inc. June 2005 – p35

More Related