230 likes | 332 Views
DT: stato e attivita ’ 2013. di-muon in B s mass window. Prestazioni rivelatore nel 2012 ( poche “highlights”) attivita ’ LS1 e programmi futuri organigrammi / richieste 2013. DT performance nel 2012. Il rivelatore ha operato stabilmente ; < 1% canali morti ,
E N D
DT: stato e attivita’ 2013 di-muon in Bs mass window • Prestazionirivelatorenel 2012 • (poche “highlights”) • attivita’ LS1 e programmifuturi • organigrammi/ richieste 2013 U.Gasparini, Incontro con i Referees
DT performance nel 2012 • Il rivelatore ha operatostabilmente; < 1% canalimorti, • > 99.5% DAQ “live time”; ottimeprestazionidi trigger, timing deimuoni • e ricostruzione • (piu’ chesoddisfacenteottimizzazionedicalibrazioni, configurazioni • di trigger, allineamenti) • Detector Control System affidabile, tools di data quality monitoring • bensviluppati e integratinel software generaledell’ esperimento • sistemaconsolidatodishifts+ expert on-call ( man-power al Cern • ragionevolmentelimitato) efficienza del L1 local trigger nellecamere a mu r.m.s. of Rec.hit residuals distributions ~220 mm probleminoti (e risolti) U.Gasparini, Incontro con i Referees 2
DT : esempida online-DQM Reference run from this week (22-28 Aug) LHC lumi U.Gasparini, Incontro con i Referees
Curve turn-on muon trigger pTthres=16 GeV/c (L1 seeding, input to HLT) Cfr. Incandela’s talk 4th July: H->ZZ(*) muon spectra U.Gasparini, Incontro con i Referees 4
DT upgrade plan & status * Theta Trigger Board (TRB) * Sector Collectorrelocation Today’s report LS1 Phase 2 New DTTF Improve maintainability and performance New TSC design + gradual installation Improves maintainability and performance… Future connection to Tracker? Tracker connection New ROS design + gradual installation Bottleneck at increased luminosities details on next slides… U.Gasparini, Incontro con i Referees
Sostituzione Theta TRB - Operazionediconsolidamento/ “maintenance non-ordinaria” resa necessariadall’ altamortalita’ inizialedei BTIM evidenziatasiduranteil commissioning (fortementeattenuatasi, per fortuna, in condizionidi “stable operations”) -failure rate attuale : 6 schede/anno (~indipendentedallaluminosita’: problemaprincipalesonogli stress termici, non la radiazione) → criticita’ intorno al 2013 • Sostituzione theta BTIM (ASIC) con • boards FPGA in un’ interastazione (60 camere): • costo ~ 350 keuro • Agreement per assorbireicostisu MOF-B, • profilodispesacostantesu 2011-2014, • cost sharing con ilrestodellaCollaborazione • (Spagna, Germania) • R&D concluso • tender FPGA concluso (giugno), 210kCHF • altriordini /gare (PCB…) in progress.. • project on schedule
TRB (ulterioridettagli…) • - Prototipifinali FPGA prodotti & • estensivamentetestati • Tests di radiation hardness • eseguiti con successo • (PSI, LNL) Test difunzionalita’: “timebox” con nuove/vecchie schededi trigger U.Gasparini, Incontro con i Referees 7
Sector Collector relocation Goal: Replace SC crate with simple CuOF electronics and place TSC (Trigger Sector Collector) and ROS (Read Out Server) in USC during LS1 -ROS -TSC INFN (To,Bo) Slow control upgrade: Pd
ECR review del progetto (giugno 2012), superata con successo U.Gasparini, Incontro con i Referees
CuOF mezzanine • PROTOTYPE PRODUCED • BEING TESTED Each CuOF mezzanine contains 8 copper to optical links. electrical input Optical output • Equalizer restores the data quality and the DC balance (LMH0024) • Laser driver (ONET1191) sets the modulation signal for the VCSEL (OPTOWELL TP85-LCP1F). In the same package, a photodiode measures the light for implementing a feedback loop to compensate the laser ageing (operation in closed loop). • The VCSEL diodes connect to fibers through custom LC adapters 6/6/12 DT Sector Collector Re-location ECR 10
OFCu & slow control • OFCU-TSC prototype produced • Test set-up built • First tests on going 11 U.Gasparini, Incontro con i Referees
Slow control upgrade Inheriting the solution developed for the upgraded secondary links to control to CUOF boards and the OFCU-TSC (not needed for commissioning of the rest of the system) U.Gasparini, Incontro con i Referees
LS1: detailed 2013-14 plan (as of August 2012) CMS runs… (HI) → normal shifts YBxavaiability Close CMS, then global cosmics runs w new DAQ… TRB replacement & chamber repairs (+ “local” cosmics runs) SC relocation & system tests very intense activity all over 2013 and (at least) 1st quarter 2014… U.Gasparini, Incontro con i Referees
ME per LS1 • Le DT richiedono 67 m.u. per attivita’ LS1 specifiche (fisici+tecnici); • Le istituzionistranierecoinvolte (Spagna/Germania/Ungheria) ciaspettiamo • forniscano 40 m.u., in linea con lo sharing MOFB dellacollaborazione • ~10 personefissedurante LS1 • 2-3 teams chelavorano in parallelo (come gia’ sperimentatonel • 2007-09 al tempo del commissioning del detector); • Parallelizzazioneessenziale per portare a compimentoilavori • ( maintenance “ordinaria” camere / interventi TRB / commissioning • nuova catena SC) nellaschedulatemporale data U.Gasparini, Incontro con i Referees
costi & spesegia’ impegnate DT upgrade fase 1: Gia’ spesi/impegnati: prototipi/tests CuOF (To) 10 keu PrototipiOFCu (BO) 6.5 keu ricevitoriottici AVAGO (ordineCern) 80 keu Totalispesi 96.5 keu Daspendere: ~54 keu : 150 OFCu boards, 6 crates VME 3U, loro backplanes, alimentatori. Slow controls….. U.Gasparini, Incontro con i Referees
Milestones: 2012 & 2013 2012: 1) validazione prototipo completo trigger board FPGA (aprile/maggio 2012) soddisfatta al 100% (test funzionalita', radiation hardness) 2) primi prototipi elettronica per spostamento sector collector in USC soddisfatta al 50 % (primi prototipi completati, intera catena di test funzionante. Prime modifiche gia' apportate per migliorare prestazioni, ma affidabilita' non ottimale; work in progress...) 2013 (in strettaconnessione con schedula LS1): 1) ottobre 2013: nuove TRB installate sulla prima wheel esterna accessibile (YB-2) 2) dicembre 2013: riallocazione Sector Collector e piena connettivita' ottica su YB-1 U.Gasparini, Incontro con i Referees
Costbook (updated) & richieste 2013 costi un po’ lievitati rispetto a quantopresentato in Sett.2011 (slide in backup): ~1090 keu → 1222 (CuOF mezzanines & motherb leggermentepiu’ costose…) Richieste 2013: Apparati: Produzione upgrade (TO) 290 ke Consumo: Upgrade (BO) 30 ke Consumo: Upgrade (TO) 20 ke Consumo: Slow controls (PD) 20 ke Budget: New entry (Estonia) → mancanti a bilancio: ~ 60 keu U.Gasparini, Incontro con i Referees
DT : responsabilita’ U.Gasparini, Incontro con i Referees
ME: dettagliorichieste U.Gasparini, Incontro con i Referees
Profilo MOFB & spese TRB Profilo MOFB: TRB maintenance: Gia’ spesi: Tender FPGA: 210 kCHF To be done: PCB, montaggi,burn-in… U.Gasparini, Incontro con i Referees
progetti Tbd… PRIN… Altro …. U.Gasparini, Incontro con i Referees
Back-up slides U.Gasparini, Incontro con i Referees
Costs (as in Sept.2011) After detailed review, contacts with manufacturers…. Total cost ~1090 ke (**however**: many items prices not “frozen” ) U.Gasparini, Incontro con i Referees