X-ray Pump-Probe Instrument

Loading in 2 Seconds...

play fullscreen
1 / 12

X-ray Pump-Probe Instrument - PowerPoint PPT Presentation


  • 273 Views
  • Uploaded on

X-ray Pump-Probe Instrument. David Fritz XPP Instrument Scientist June 9, 2009. Outline. Overview XPP Update from previous FAC Component Status Design Procurement and Fabrication Early commissioning?. XPP Instrument Overview. Update from Fall FAC.

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

PowerPoint Slideshow about 'X-ray Pump-Probe Instrument' - easter


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
Presentation Transcript
x ray pump probe instrument

X-ray Pump-Probe Instrument

David Fritz

XPP Instrument Scientist

June 9, 2009

outline
Outline

Overview

XPP Update from previous FAC

Component Status

Design

Procurement and Fabrication

Early commissioning?

update from fall fac
Update from Fall FAC
  • Received advanced procurement approval December 18, 2009 for:
    • Sample Goniometer
    • Detector Mover
  • Final Instrument Design Review successfully held Feb 24, 2009
    • Procurement authorization for everything except OPA, multipass amplifier
  • Baseline change request processed to include large offset monochromator system for XPP
    • Procurement documents were reviewed at the XCS advanced procurement review April 24, 2009 and the documents are being updated
laser tables and enclosure
Laser Tables and Enclosure
  • Completed design of laser containment system and optical table layouts
    • Design review November 14, 2008
  • Laser tables are fabricated and are in storage in the control room.
    • Anchor holes are drilled and tables are ready to be installed once granite is installed
  • Enclosure PO placed April 20, 2009

5’ x 12’

5’ x 6’

x ray optics tables
X-ray Optics Tables
  • Completed final design of X-ray optics tables
    • Final design review January 26, 2009
  • Granite PO placed April 14, 2009
    • Expected to be delivered in July w/ rails installed
  • Anchor holes for the earthquake restraints already drilled
sample goniometer
Sample Goniometer
  • Received advanced procurement authorization Dec. 18, 2008
  • Goniometer PO awarded to Huber April 1, 2009
    • Expected to be delivered in April 1, 2010
  • Vendor site visit scheduled for July 17, 2009
detector mover
Detector Mover
  • Received advanced procurement authorization Dec. 18, 2008
  • Robot basing design study completed in January, 2009
  • Robot PO awarded March 31, 2009
    • Expected to be delivered this week
  • Robot support design review held May 22, 2009
    • Detailed fabrication drawings in process
  • Robot software PO in process
hutch facilities
Hutch Facilities
  • Work benches and storage cabinets received and installed
  • Tools and tool boxes PO placed March 24, 2009
    • Expected to be delivered and installed in August
  • Raised floor PO in process (req submitted March 10)
  • Cable trays are here
laser equipment
Laser Equipment
  • RFP issues for 20 Ghz Oscilloscope
  • Various optics and optomechanics PO’s in process
    • Much more to be procured over the next 6 months
  • Hopefully procurement authorization will be given for OPA and multipass amplifier shortly so req’s can be placed
updated schedule
Updated Schedule

FY08

FY09

FY10

FY11

Preliminary Design Reviews

  • X-ray Optics Support Tables – August 2008
  • Detector Mover Support – May 2009

XPP Advanced Procurement Review – November 2008

Final Instrument Design Review – February 2009

Final Design Reviews

  • Optical Table Layout\Containment – November 2008
  • X-ray Optics Support Tables – January 2009
  • Detector Mover Support – May 2009

CD-3 - July 2009

Award PO

  • Sample Goniometer – April 2009
  • Hutch Facilities – June 2009
  • Detector Mover – March 2009
  • X-ray Optics Support Tables – April 2009
  • Laser Containment System – April 2009
  • Optical Tables – April 2009
  • Detector Mover Support – July 2009

Receive

  • Optical Tables – May 2009
  • Hutch Facilities – August 2009
  • X-ray Optics Support Tables – July 2009
  • Laser Containment System – July 2009
  • Detector Mover – June 2009
  • Sample Goniometer – April 2010
  • Detector Mover Support – September 2009

Ready for User Run – July 2010

early commissioning
Early Commissioning?

X-ray support tables are expected to be installed in July

Vacuum transport can/will be installed in the summer as well

Prototype X-ray diagnostics will be ready in the fall

Would be extremely beneficial to receive some early “machine time” to test prototype diagnostics, optics, materials, etc…

4-8 hours per week???

This would significantly reduce the risk and commissioning time allocated to the dedicated XPP instrument commissioning