This project aims to establish communication between Universal Software Radio Peripherals (USRPs) and sensors using the Zigbee protocol (IEEE 802.15.4) at a 2.4GHz frequency, employing a star network topology. Utilizing GNU Radio as the software platform, we are implementing an open-source Zigbee solution for data transmission. Our team consists of design members from Iowa State University, working to achieve a robust sensor network that can broadcast useful data efficiently. Key steps include software setup, sensor installation, and overall project management.

durin
Download Presentation

Ad-Hoc Wireless Networks: Communication via Zigbee Protocol for Sensors and USRPs

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Content Delivery on Ad-Hoc Wireless Networks Wyatt Brenneman Taylor McKechnie Prashanth Yanamandra

  2. Senior Design Team 3 • Adviser : Dr. Lei Ying • Research Assistant: Ming Ouyang • Team Members: • Prashanth Yanamandra • Wyatt Brenneman • Taylor McKechnie • Client: ECpE Department Iowa State University Ames, IA, 50010 USA

  3. Project Plan • To establish communication between USRPs and Sensors using Zigbee protocol (IEEE 802.15.4) at 2.4GHz broadcasting frequency • Using Star Network Topology for sensor networks • Print useful data obtained from the sensors

  4. Project Design • GNU Radio • Software to be used on the USRP • Zigbee • Open Source implementation of GNU Radio to implement Zigbee protocol (IEEE 802.15.4) • TinyOs • Operating System to be installed on the sensors to establish communication with the USRPs

  5. Project Design • Sensors • Crossbow TelOs motes • MicaZ motes • 250 kbps data rate • 2.4GHz frequency between USRPs and Sensors for communication • Both sensors use IEEE 802.15.4

  6. Project Implementation • Week 1 • Setting up group meeting times • Recapping last semester progress

  7. Project Implementation • Week 2 • Met with Adviser and the instructor to discuss the progress of the project • Obtained new directions for the project • Met with the graduate assistant to discuss project progress during the summer • Revised the earlier strategy for the 2nd semester of the project

  8. Project Implementation • Week 3 • Obtained the sensors required for the project • Started installation of new software for the USRPs and the sensors • Hydra • TinyOS ( OS for the Sensors)

  9. Project Implementation • Week 4 • Reinstalled Ubuntu 9.2 • Installed GNU Radio, Zigbee, Hydra, TinyOS

  10. Project Implementation • Week 5 • Learning TinyOS • Testing installation of software

  11. Semester Plan