An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. How to Successfully Implement & Use a CMMS Yorick de Tassigny, FMP, SFP John Rimer, CFM

  2. Introduction Yorick de Tassigny, FMP, SFP • 11 years facility management experience in the public sector • Involved in the implementation and management of CMMS in two different organizations John Rimer, CFM • 17 Years Facility Management • Numerous Industries & Various Roles • Owner, FM360 Consulting • Implemented & Managed Multiple CMMS Installations

  3. Agenda • Value of a CMMS • Common Reasons for Failed Systems • Steps to Select & Implement • City of Boise Example • Resources • Q&A

  4. Why a CMMS? • “The Nervous System of a Facility Program” • A Necessary Business Tool for Today’s FM • Assess Efficiency & Effectiveness • Drive Business Decisions • Operations & Capital Budgeting • Market FM Program

  5. Key Functions of a CMMS • Maintain Asset Information & History • Exhibit Hierarchy & Relationships • Store Procedures & Practices • Submit & Track Service Requests • Prioritize, Schedule, & Dispatch WOs • Document Work Performed • Capture Labor & Mat’l Costs, Notes, etc. • Capital Renewal Planning • Reporting & KPIs

  6. Key Performance Indicators (KPIs) • PM/CM Ratio • Backlog • % Utilization • Discovery Mode • SRs by Type • Failure Modes/Causes • Labor & Mat’l Costs

  7. Common Reasons for Failed Systems • Wrong System for the Job • Old, Slow System • Change Paralysis • Budget to Install but not to implement • Insufficient planning & Stakeholder buy-in • Lack of Knowledge & Experience

  8. Steps to Implement • Identify Stakeholders • Define the Processes • Develop System Requirements • Create Assessment Matrix • Identify & Evaluate Qualifying Vendors • Perform Test Fit • Budget & Schedule for Success • Training & Support • Solicit help

  9. Example - City of Boise • Overview • Enterprise solution – multiple departments with similar needs: Airport, Parks, Public Works, Police and Fire • Project spearheaded by IT • Compliance with Clean Water Act and new stormwater regulations is key driver • RFP released in 2013 • Product has been selected • Implementation slated for late 2014

  10. Example - City of Boise • Identify Stakeholders • Define the Processes • Develop System Requirements • Create Assessment Matrix • Identify & Evaluate Qualifying Vendors • Budget & Schedule for Success • Solicit help as needed

  11. Example – City of Boise Identify Stakeholders • Leadership (buy-in, purse strings) • Formation of core team (subject matter experts) • Identify communication process to keep everyone informed

  12. Example – City of Boise Define the Process • Mapping the workflow – hired consultant to help with process documenting (AS IS) • Objective is to find opportunities for improvement • Lesson learned? Completing process diagrams before vs. after selection process

  13. Example – City of Boise

  14. Example – City of Boise

  15. Example – City of Boise Develop System Requirements Word of caution: Be careful not to allow an existing process influence your requirements • Core Team worked with respective departments • Identified areas of overlap and combined • Prioritized • Included items that will improve process

  16. Example – City of Boise

  17. Example – City of Boise Identify and Evaluate Qualified Vendors • RFP – Requirements became specifications • Assessment matrix

  18. Example – City of Boise Assessment Matrix

  19. Example – City of Boise

  20. Example – City of Boise Identify and Evaluate Qualified Vendors • Evaluated total cost of ownership: • IT & business resources required to maintain the system past implementation • Complexity of system to maintain, configure, update • Maintenance cost over 10 years • Consultant vs. software developer • Shortlisting of vendors • Vendors given scripts to follow for their 2-day presentations

  21. Example – City of Boise

  22. Example – City of Boise Plan for Successful Implementation • Met with key stakeholders (the ones that control the purse strings) to reaffirm funding and support for project • Standardization of nomenclature • Defined process using PMI Standards and ADKAR Change Management methodologies • Use Microsoft Project and SharePoint for project management tools

  23. Resources • IFMA’s FMJ – March/April Issue • “CMMS – Realizing the Value” • FacilityU.com • “CMMS – A Necessary Business Tool for Today’s Facility Manager” • “CMMS is Not a Four-Letter Word”