1 / 10

Progress Report on HIE-ISOLDE LINAC Development by Matteo Pasini at SRF09 Conference

This report presents the current status of the HIE-ISOLDE LINAC project as discussed by Matteo Pasini at the SRF09 conference in Berlin (September 20-25, 2009). Key activities include high-beta cavity prototypes, RF beam dynamics studies, and the design of a new cryomodule. The report highlights the completion of a cavity prototype, upcoming tests at TRIUMF, and plans for a QWR test bench at CERN. It also covers advancements in chemical etching, Nb sputtering, and mechanical drawings for the SC solenoid prototype.

dolph
Download Presentation

Progress Report on HIE-ISOLDE LINAC Development by Matteo Pasini at SRF09 Conference

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HIE-LINAC status report Matteo Pasini BE/RF

  2. R&D activity • RF – Beam dynamics studies • High b cavity prototype • Copper substrate manufacturing • Chemical etching • Nb sputtering • RF sub-system prototypes • Tuner • Power coupler • SC solenoid prototype • Cryomodule design • In parallel preparation of a test stand for QWR at CERN M. Pasini SRF09 Berlin, 20-25.09 2009

  3. HIE-ISOLDE LINAC - layout 3 stages installation 1.2 MeV/u 3 MeV/u 5.5 MeV/u 8 MeV/u 10 MeV/u M. Pasini SRF09 Berlin, 20-25.09 2009

  4. RF – Beam Dynamics studies • Beam Port shape studies THPPO026 M. Pasini SRF09 Berlin, 20-25.09 2009

  5. QWR cavities (Nb sputtered) M. Pasini SRF09 Berlin, 20-25.09 2009

  6. High –beta cavity final welding and cleaning THPPO010 M. Pasini SRF09 Berlin, 20-25.09 2009

  7. SC solenoid prototype (Nb3-Sn technology) Mechanical drawings for the model are completed M. Pasini SRF09 Berlin, 20-25.09 2009

  8. Cryomodule design • Features: • Single vacuum cryostat • Side loading of the cold masses • Independent alignment of the cavities w.r.t. solenoid • Heat shield cooled by He cold gas M. Pasini SRF09 Berlin, 20-25.09 2009

  9. The HIE-ISOLDE facility M. Pasini SRF09 Berlin, 20-25.09 2009

  10. Summary • Cavity prototype completed. Tests to be done @ TRIUMF before the end of the year • Cryomodule concept design completed, will start detailed design as soon as manpower is available • Preparation of test bench at Cern of QWR resonators (new test cryostat is planned to be ready by Feb/Mar 2010) • Complete Cavity configuration test is planned by the end of 2010. M. Pasini SRF09 Berlin, 20-25.09 2009

More Related