An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Bond Construction Update Facilities Advisory Committee Long Beach Community College District February 2, 2011 EDUCATE ENGAGE EMPOWER

  2. Agenda • Completed Construction Projects • District Wide – Electronic Signage Plan • Current Construction Projects • LAC Building A – Student Services Retrofit • LAC Parking Structure • LAC Building O Complex • LAC Infrastructure Improvements Project and District Wide – Energy Efficiency Project • LAC Building I (Bookstore) • LAC South Walkway Extension • PCC MDAB (Multi-Disciplinary Academic Building) • PCC Walnut Ave. Arrival Court • District Wide – Monument Signs • Upcoming Construction Projects • LAC W Trailers Demo • PCC Building CC Retrofit • Q & A

  3. Completed Construction Projects District Wide – Electronic Signage Plan Measure E 2008 • District Wide Signage Plan complete for LAC & PCC • Construction completed Fall 2010

  4. Current Construction Projects LAC Building A – Student Services Retrofit Measure E 2008 • Adds 6,500 Sq. Ft. to existing building • Notice To Proceed given to SMC Construction on 12/29/10 • Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc. • End of construction anticipated Summer 2012

  5. Current Construction Projects LAC Parking Structure – Measure E 2008 • Spaces for 900 Vehicles • Finalizing installation of solar arrays, irrigation, signage, and data/telecom runs • Anticipated end of Construction Spring 2011

  6. Current Construction Projects LAC Building O Complex – Measure E 2008 • Two structures totaling 87,000 square feet • Occupants for Building O2 are Foundation, ERD, tenants, and ALCI (soon to come) • Occupants for Building O1 will be IITS, BMT, and Warehouse Facility • Anticipated completion February 2011

  7. Current Construction Projects LAC Infrastructure Improvement Project and District Wide Energy Efficiency Project Measure E 2008 • Total annual estimated savings of 1.5 mil. Kwh • Project started Fall 2009; currently working on phase 6 (partial), 7, 8A, 9A (Landscape),and 10 (G and H Quad area) • Majority of existing building HVAC systems to be upgraded and connected to the Central Plant • Buildings G & H are connected • Buildings B, C, D, E, and J will be scheduled in the next couple months • Exterior lighting and controls upgrades • All parking lots north of Lew Davis are on new system • New Reclaimed Water tie-ins to irrigation still to come • New gas lines installed for Buildings B, C, D, E, G, H, J, M, N, and P • New domestic lines installed for Buildings B, C, D, E, F, G, H, I Trailers, J, K,L, M, N, P • Anticipated end of construction Winter 2011

  8. Current Construction Projects LAC Building I - Measure E 2008 • Adds additional 4,000 square feet to existing building • Architecture to match LAC Mediterranean Theme • Notice To Proceed given to G2K Construction on 11/15/10 • End of Construction anticipated Fall 2011

  9. Current Construction Projects LAC South Walkway Extension Measure E 2008 • 99% complete • Currently going through final punch-list • Continues Master Plan pedestrian corridor

  10. Current Construction Projects PCC MDAB (Multi-Disciplinary Academic Building) Measure E 2002 and 2008 • Notice To Proceed issued on 7/29/10 • Currently in phase 1 of construction (DD and EE in construction) • Portables for swing space installed Summer 2010 complete and occupied (MD Trailers) • Project to be completed in two phases – estimated completion for DD and EE is Summer 2012

  11. Current Construction Projects PCC Walnut Ave. Arrival Court - Measure E 2008 • UU/VV demo completed • Currently grading site • Site to be converted to a parking lot • Estimated end of construction Spring 2011

  12. Current Construction Projects District Wide – Monument Signs Measure E 2008 • District Wide Monument Signs. • Locations: • LAC-Clark/Conant – installed January 8, 2011 • PCC-20th/Walnut Ave. – installation still to come • Installation of building designators for LAC Bldg. O1 and O2 completed • Estimated construction completion Spring 2011 LAC Monument Sign LAC Bldg. Designator PCC Monument Sign

  13. Upcoming Construction Projects LAC W Trailers Demo - Measure E 2008 • Design for site completed • W Trailers to be demolished • Site to be converted to a parking lot and a bio-swale • Board of Trustees approved on 1/18/11 to Green Giant • Notice to Proceed to be issued once docs have been submitted by contractor

  14. Upcoming Construction Projects PCC Building CC Retrofit - Measure E 2008 • Houses the Fitness Center, Gymnasium, Weight Room, and Faculty and Staff Offices • Swing space located on PCC Campus (Bldg. GG) • Approved by DSA on 1/27/11. Bid process to commence shortly • To be completed concurrently with MDAB project phase 1 • Anticipated end of construction 2012

  15. Liberal Arts Campus Site Plan l i b e r a l a r t s

  16. Pacific Coast Campus Site Plan p a c i f i c c o a s t

  17. QUESTIONS& ANSWERS EDUCATE ENGAGE EMPOWER