1.07k likes | 1.55k Views
2. CONTENTS. Scenario of Power System before the setup of LDCsNecessity/Objectives/Ideal ConditionsDecision of GOISetting up of SLDC/Sub-LDC in HPSCADA/EMS functions.ABT RegimeSome samplesU.I. ChargesPoints for considerationGrid Management. 3. SCENARIO OF POWER SYSTEM BEFORE THE SETUP OF LOAD DESPATCH CENTRES.
E N D
1. 1
2. 2 CONTENTS Scenario of Power System before the setup of LDCs
Necessity/Objectives/Ideal Conditions
Decision of GOI
Setting up of SLDC/Sub-LDC in HP
SCADA/EMS functions.
ABT Regime
Some samples
U.I. Charges
Points for consideration
Grid Management
3. 3 SCENARIO OF POWER SYSTEM BEFORE THE SETUP OF LOAD DESPATCH CENTRES No Grid Discipline.
Low voltage, low frequency.
Frequent Grid failures.
Non optimum utilization of available resources.
No real time availability of data/ events occurring.
Contd…...
4. 4 Inefficient Power System Operation & Load Management
Wide gap in Demand - Supply position (no regulation).
Low voltages at Consumer end.
High per Unit cost.
5. 5
6. 6 NECESSITY/OBJECTIVES: For running the power system at maximum economy.
For getting real time information for speedy and efficient decision-making.
For meeting the demands of the ABT regime.
7. 7
8. 8 DECISION OF GOVT. OF INDIA To set up
Regional Load Despatch Centres
State Load Despatch & Communication Centres
Sub-Load Despatch Centres with ultimate aim of ‘National Grid’
9. 9
10. 10 CONTROL HEIRARCHY
11. 11 CONTROL HEIRARCHY
12. 12 INTER CONNECTIVITY DIAGRAM OF SLDC –SUB-LDC’s OF H.P.
13. 13
14. 14
15. 15
17. 17 132kV SUB-STATION AT JUTOGH
18. 18 132kV SUB-STATION AT JUTOGH
19. 19 RTU AT JUTOGH
20. 20 COMMUNICATION ROOM
21. 21 COMPUTER ROOM
22. 22 CONTROL ROOM
23. 23 CONTROL ROOM
24. 24 PROGRAMMING ROOM
26. 26
27. 27 SCADA/EMS FUNCTIONALITIES
28. 28
29. 29
30. 30 EMS PACKAGE-LOAD FORECASTING (LFC)
31. 31
32. 32 EMS RTGEN
33. 33
34. 34
35. 35
36. 36
37. 37 What we have done…….. Matching of forecasted & Actual Demand
Meticulous Planning for Day Ahead Schedule
Regulation of own generation according to frequency profiles
38. 38
39. 39
40. 40
41. 41 SOME SAMPLES Sample Day Ahead Schedule
Sample Graphs
Frequency
Unscheduled Inter-change
Daily Generation, Availability & Requirement of State
42. 42 Electricity - A scientific phenomenon EMF travels at the speed of light
Available ‘just-in-time’
Delivered to the customers fresh
No one get placed on hold
Impartial in its benevolence and wrath
Good servant but a ruthless master
43. 43 Power flow characteristics Is directional
Does not recognize geographical boundaries, asset ownership
Does not check the map to determine the shortest route
Flows are dictated purely by
Impedances of the transmission lines
Point of injection by generators
Point of consumption loads
44. 44
45. 45 Reliability
Is a general term encompassing all the measures of the ability of the system generally given as numerical indices to deliver electricity to all points of utilization within acceptable standards and in the amounts desired
CIGRE
Comprises of “Adequacy” and “Security”
46. 46
47. 47 Security
48. 48 Stability Angle Stability
ability of interconnected synchronous machines of power system to remain in synchronism under normal operating conditions and after subjected to a disturbance
Small signal, Transient, Mid term, long term
Voltage Stability
ability of a power system to maintain steady acceptable voltages at all buses in the system under normal operating conditions and after subjected to a disturbance
49. 49 Power System in India
50. 50 Hierarchy of Indian Power System
51. 51 NATIONAL POWER SCENARIOInstalled Capacity in 1947 1,300 MWInstalled Capacity as on 31.08.2007 1,35,000MW
Demand Estimates (FY2012) 16th EPS*
Energy Demand (Billion Units) 750
Peak Demand 155,000
Installed Capacity required to 195,000
meet peak demand (MW)
Additional Capacity Required (MW) 71,000
Present Energy Shortage 8.2%
Peak Demand Shortfall 13%
* Energy Survey by GOI
52. 52 Present Power Scenario
53. 53 Synchronous Grid interconnecting four(4) regions of 90 GW capacity geographically spread over 2.6 million sq. kms.
South(SR) is asynchronously connected
Transmission Grid$ (as on 30th September 2007)
765 kV / 400 kV Lines - 82089 ckt. km
220 kV Lines – 116745 ckt. km
HVDC Bipole (3 nos.) - 2389 ckt. Km, 5 GW
HVDC back-to-back - 7 nos., 3 GW
FSC – 18 nos.; TCSC – 6 nos.
Inter-regional capacity – More than 16 GW
$source: CEA, India Transmission Network
54. 54 Development of Electric Grid
55. 55 Energy Resources
56. 56 Installed Capacity & Inter Regional links
57. 57
58. 58
59. 59
60. 60
61. 61
62. 62 Zones and Flowgates in Northern Grid
63. 63
64. 64 HPSEB-Taking Power to people Existing Power System
Installed Capacity 460 MW
Villages Electrified 16915 Nos
Hamlets Electrified 4482
Consumer Connected 17.56 Lacs
Connected Load 3531300 KW
65. 65 HPSEB-Taking Power to people Existing Power System
EHV Station 35Nos.
Distribution Sub Stns. 18255Nos.
H.T.Lines 28012Kms
L.T.Lines 50435 Kms
A State Load Dispatch Centre with Latest State of Art has been established to have online control and transaction of Electricity
Minimum fatal/non-fatal accidents
Minimum Transformer failure
66. 66
67. 67
68. 68
69. 69 Role of Himachal Pradesh State Load Dispatch Centre Himachal Pradesh State Load Dispatch Center is ensuring integrated operation of the power system of the HP State with the Northern Region Load Dispatch Center of India. The main responsibilities of HPSLDC are:
Management, Monitoring & Control of power system parameters and security etc.
To ensure the integrated operation of the power system of HP State Grid with Northern/NEW Grid.
System studies, planning and contingency analysis.
Analysis of tripping/disturbances and facilitating immediate remedial measures.
Issuance of Day Ahead Schedules/Dispatches w.r.t demand of loads, generations etc. and operational planning/control.
Facilitating bilateral exchanges.
Computation of energy dispatch and drawal values using SEMs.
Augmentation of telemetry, computing and communication facilities.
70. 70
71. 71 Critical Corridor In Northern Region Central UP to western part is a critical corridor having the following lines:
72. 72 Fog on 27th January 2007
73. 73 Incident on 27th January 2007 Heavy Fog in North West India (rail, road, air traffic)
Tripping/Auto Reclosure started from 0300 Hrs.
Maximum impact in Delhi, Western UP and Haryana areas.
Most critical period between 0745 Hrs to 1130 Hrs.
Max 53 (400 & 220kV) lines were out at 0812 Hrs.
Western UP/Uttaranchal (approx 1200 MW load) area was being fed through 400 kV Agra-Muradnagar and 400 kV Lucknow- Moradabad lines only for more than 2 hours.
74. 74 The five hour ‘test of nerves’ Time of incident: 0600 hrs to 1100 hrs
Information overload
3300 Alarms : 11/Minute
1200 Sequence of Events : 4/Minute
Situational awareness challenge
17 number of corridors affected
32 no. of lines out of 81 lines in these corridors affected
Total 82 no. of Auto-Reclosures on 17 lines
400 kV Bus-II lost at Dadri at 08:12:22 hrs
220 kV bus-II lost at Auraiya at 08:46:11 hrs
220 kV Bus fault at Panipat (BBMB) at 09:00:51 hrs
8 no. of 400 kV & 16 no. of 220 kV lines declared under breakdown
Auraiya 2 GTs and 1 STs & Panipat(Th) # 1, 2, 3 & 4 tripped
Backing down of generation at Singrauli, Rihand-1 & Rihand-2
Curtailment of Inter-Regional STOA transactions
75. 75
76. 76 December-2007
77. 77 January 2008
78. 78
79. 79 Fog Related incident on 4th /5th Feb 2008 in Northern Region First line tripped at 20:49 hrs/ 04 Feb- 2008
63x400 kV lines and 54x220 kV lines tripped
15x400 kV Substations and 9x220 kV Substations dead.
NR System separated into two parts at 0437 hrs.
Islanded system comprised of
Punjab -Chandigarh -North Haryana -HP-Jammu & Kashmir –BBMB
Island size about 5500 MW
Rest of NR(Delhi/UP/Uttarakhand/Rajasthan) remained connected with “NEW” Grid.
80. 80 At 07:45 hrs, 400 kV Dadri remained connected with rest of the grid only via 400 kV Dadri-Maharanibagh-Ballabhgarh line
Tripping of 400 kV Dadri-Maharanibagh-Ballabhgarh would have led to islanded operation of Dadri (T) & Dadri (G)
Islanded operation continued for 4 hour 19 minutes
Fog Related incident on 4th /5th Feb 2008 in Northern Region
81. 81 Load shedding of around 5000 MW to avert cascade failure and survival of island
Generation affected at Panipat (T )(unit 3 & 8) –110 MW x1+1x250MW=360 MW
2600 SOEs received from 00 hrs to 0900 hrs of 5th Feb 2008
121 number of switching instructions issued by NRLDC
83 instructions for closing of lines Fog Related incident on 4th /5th Feb 2008 in Northern Region
82. 82
83. 83
84. 84 ACTION TAKEN Total 1500 MW of Generation Backed down at
Singrauli,Rihand,Unchahar,Dadri(G),Auriya
Additional support of 200-300 MW taken from BBMB for more than 10 hours
Inter-Regional STOA curtailed
Power exported to Central grid to the tune of 700 MW against a normal import of 1270 MW( swing of 1970 MW)
85. 85 Generation Backdown
86. 86
87. 87 BBMB GENERATION
88. 88
89. 89 Island kept ready for synchronisation at two places viz.
Bassi end on 400 kV Bassi-Hissar and
Hissar end on 400 kV Hissar-Bawana but finally synchronised at 08.57 hours at Hissar . Fog Related incident on 4th /5th Feb 2008 in Northern Region
90. 90 Highlights/Issues-Fog related Trippings Behaviour of autoreclosure feature
System separation alerts issued continuously since 02:30 hours and BBMB/Punjab/Haryana/J&K/HP SLDCs alerted on 5th Dec-08 morning
Loss of 220 kV Panipat(BBMB) bus at 02:30 hours while carrying out switching operations to isolate the stuck breaker of 220 kV Panipat-Ch.Dadri line………..islanding of Panipat unit-3 & its tripping.
91. 91 Highlights/Issues-Fog related Trippings 1x250 MVA, 400/220 kV ICT at Dehar providing the synchronous interconnection for nearly 40 minutes.
Attempts to maintain connectivity on 220 kV Panipat-Narela D/C
Survival of Island after separation possible only as it was surplus by 250 MW at the time of separation
Absence of free governor operation in the Island
92. 92 Highlights/Issues-Fog related Trippings UFR operation in Island at 04:49 Hours
Relative Humidity not dropping…..conscious decision to synchronize only afer 08.30 hours
Response from SLDCs/Substations during crisis
Outage of 400 kV Muradnagar(UPPCL) for more than 4 hours
No communication to substation either through SLDC or directly from NRLDC
Overdrawal by Rajasthan
Data related issues raised by DTL
Loading of 400 kV Dadri-Malerkotla (PSEB
93. 93 Highlights/Issues arising out of FOG related tripping 5th/6th Feb-08 Fault leading to isolation of 400 kV Bawana at 01:50 hours
Load remaining connected at Bamnauli…..
94. 94
95. 95
96. 96
97. 97
98. 98
99. 99 Future Demand-Capacity Projection
100. 100
101. 101
102. 102 Grid operation - A collective responsibility Transmission is an indivisible shared facility (public service)
“Failures in one location can propagate through the network”- Thomas Overbye
“Power markets are the only markets that can suffer a catastrophic instability that develops in less than a second… The extent and speed of the required coordination are unparalleled”-Steven Stoft
103. 103
104. 104
105. 105 Tangible Benefit Accrued
106. 106
107. 107
108. 108 THANK YOU FOR YOUR VISIT
TO SLDC CONTROL CENTRE