Bilan and Objectives SU
150 likes | 304 Views
Bilan and Objectives SU. Dominique Missiaen. Departures-Arrivals. Arrivals Francis Klumb (ST) Philippe Dewitte (ST) Christophe Podevin Sebastian Waniorek (FE) Mathieu Duquenne (FE) Petre Radut (VIA) Michael Udzik (FSU) Mehdi Belhay (FE) Ales Hrabe (TECH)
Bilan and Objectives SU
E N D
Presentation Transcript
Bilan and Objectives SU Dominique Missiaen
Departures-Arrivals • Arrivals • Francis Klumb (ST) • Philippe Dewitte (ST) • Christophe Podevin • Sebastian Waniorek (FE) • Mathieu Duquenne (FE) • Petre Radut (VIA) • Michael Udzik (FSU) • Mehdi Belhay (FE) • Ales Hrabe (TECH) • Olivier Ggouabre Seri (TL) • Bruno Perret (TL) • 13 personsfrom the contract c201 • Departures : • Joanna Hulboj (FE) • Sylvain Griffet (FE) • Juha Kemppinen (FE) • Sylvain Mico (FSU) • Yann Bailly (VIA) • Mohamed Khamfir (TL) • Montse Montero (FE) • Christophe Podevin (end of August) • Bernard Noël (TL) ABP group meeting D. Missiaen
Before LS1 • Alignment of K12 and Na62 : • 1st beam in November 2012 • Linac4 : • Fiducialisation of Components : RFQ, CCDTL, DTL, etc • 3MEV test stand : RFQ, diagnostic line • Tunnel : marking on the floor, alignment of the source and LEBT • LHC • Fiducialisation of 15 dipoles and 3 SSS • Levelling tests in sector 67 to prepair LS1 NA62 LAV, STRAW, MUV ABP group meeting D. Missiaen
Before LS1 • low beta quads • Loadsensorsunder • Installation at PT 5 (100 %) and 2 (80%) • Visualisation under PVSS • Irradiation tests performedwithsuccess • Design of remote validation units for the HLS and WPS alignmentsystems • Prototypes validated (mechanics, electronics, acquisition and control) ABP group meeting D. Missiaen
Experiments ALICE DCAL : Load test CMS : YE4 assembly LHCb Magnet : Photogrammetry With and without B ATLAS IBL / New beam pipe: Mock-up scale1 (H180) LEB : Preparation of beam pipe changes (ATLAS, CMS, LHCb LS1, ALICE LS2) ABP group meeting D. Missiaen
NA62 – COMPASS – ALPHA – CAST – NA61 – ISOLDE – Others Non-LHC Experiments ALPHA Full installation • Survey in multiple areas • All along the year ISOLDE Survey of all lines CAST Grid, Dynamic survey COMPASS: New RPD, RICH, Liquid H target … HIE-ISOLDE Intégration 3D Scan Réunionannuelle 2012 D. Missiaen
LS1- accelerators LHC : -Fastlevelling - Network machine-exp. for Atlas and CMS PSB : Vertical shape SPS : Vertical realignment of the «hole» of sextant 6 TI2: V and H realignment ABP group meeting D. Missiaen
LS1 – accelerators (comingnext) • LHC : • LSSs and alignment of new components • Smoothing of the arcs fromSummernextyear • Maintenance of the permanent monitoring system of low beta quads • Installation of loadsensors and of validation systems for HLS and WPS in PT1 and 5 • SPS : • H and V realignment of all components • TI8 : H and V realignment of all components • TT10 • PS : Measurement/re-alignment of the PSR • Linac4 : • alignment of the components 3 MEV test stand in the L4 tunnel • Duringassemblychecks of CDDTL and DTL ABP group meeting D. Missiaen
LS1 -Experiments • Main survey done • Geodetic networks • Stabilities ATLAS – CMS • Experiment Opening surveys • ATLAS EE Muon alignment completed • CMS Pixel / bulkhead-YE1 3D scanning CMS Pixel Survey CMS Bulkhead/YE1 3D Scan • Some tasks for the next future • ATLAS: Muon Barrel / Install. Muon Sector 13 / Start of Open Close Monitoring installation • CMS: MABs Calib. / YE4 assembly start / Upgrade BCAM / Prepa insertion beam pipe and Pixel CT • ALICE: Installation DCAL and new TRD mod. • LHCb: Installation of new Beam Pipe (Full length) • And many others operations foreseen in 2014 ATLAS: Muon Barrel ABP group meeting D. Missiaen
Projects • CLIC • LAMBDA : validation of solution on short range • Development and validation of cammovers • Compact • Standard • Validation of the alignmentstrategy on the TBTM mock-up • Comparison of movementmeasuredwith CMM, WPS and AT401within 10 microns • Fiducialisation and active alignment : important progress • AbsolutemeasurementswithcWPS and oWPSwithin a few microns ABP group meeting D. Missiaen
Projects • HIE-Isolde • Bcam monitoring system • Open/Close monitoring system for Atlas • CLIC • Development of cammovers: • Standard and compact to betestedunder 5 DOF • Compatibility withstabilization solution to bechecked • Lambda project: • Validation of the concept on short range using a veryaccuratedisplacement table • Dimensional control, fiducialisation and alignment on test setups: • On the TBTM (including control of alignmentduring thermal and transport tests) ABP group meeting D. Missiaen
Projects • HIE-Isolde • Bcam monitoring system • Open/Close monitoring system for Atlas ABP group meeting D. Missiaen
Projects (future) • CLIC • Development of cammovers: • Lambda project: • Validation of the concept on short range using a veryaccuratedisplacement table • Dimensional control, fiducialisation and alignment on test setups: • On the TBTM (including control of alignmentduring thermal and transport tests) • Collaboration with NIKHEF: • Inter-comparisonbetweenalignmentsystems on short & long range • Follow-up of the spoke design in MDI area • PACMAN project (Particle Accelerator Components’ Metrology and Alignment up to the Nanometrelevel) • Marie Curie Initial Training Network, Innovative Doctoral Programme ABP group meeting D. Missiaen
Software and Database • The development of the APEX interface has been continued • Calculation menu • Measurements menu • Several versions of • Post-processing : LGC++, CHaBa++, • Data acquisition : SFB, PFB, carnet, Pctopo32 • Somedevelopmentswillbecontinuedduring LS1 ABP group meeting D. Missiaen
Conclusions • A huge LS1 ahead of us • A good start for the first 4 months • Motivation willbevery the mostdifficultthing to maintain all along the 20 months • But not only LS1 • LC and HIE-Isolde studiesstill continue • Software and databasedevelopments as well ABP group meeting D. Missiaen