350 likes | 377 Views
The ISOLDE Solenoidal Spectrometer project, funded by UK STFC, involves the implementation of Internal and External spectrometers starting from January 2015 with a completion target of March 2019. The project aims to address challenges related to TSR relocation and spectrometer systems at CERN. Magnet procurement, detection system integration, and operational planning play key roles in accomplishing project milestones.
E N D
The ISOLDE Solenoidal Spectrometer project Robert Page
The original plan: Move TSR to ISOLDE UK STFC funded project ~£5M investment Internal spectrometer External spectrometer Start January 2015 Completion March 2019 Spectrometer Systems for TSR@ISOLDE
Solenoidal spectrometer concept vlab v0 θlab θcm z Vcm CM Angle: CM Energy:
Challenges: TSR not in CERN MTP Spectrometer Systems for TSR@ISOLDE
Internal Spectrometer Plan to exploit Si detector system on CRYRING@ESR
Challenges: TSR not in CERN MTP ISS on XT02 beam line No TSR – beam quality (beam manipulation) No funding for magnet Spectrometer Systems for TSR@ISOLDE
Magnet procurement • Magnet available from Brisbane (UQ) • OR66 4T ex-MRI magnet • “Active shield” reduces stray field • Installed February 2003 • Discharged then warmed ~2013 • Funding request (STFC/UoL) June 2015
Magnet procurement • Magnet available from Brisbane (UQ) • OR66 4T ex-MRI magnet • “Active shield” reduces stray field • Installed February 2003 • Discharged then warmed ~2013 • Funding request (STFC/UoL) June 2015 • Magnet ordered November 2015
sailing across the globe… Calicanto Bridge
Preparation & cleaning magnet bore ~90 cm diameter
Cooling down, January 2017 Thanks to CERN cryogenics team, Patrick Retz, ...
Energising, February 2017 ramped up to 2.75 T, held for 1 hour then ramped down
In the ISOLDE Hall ~18 tons – too heavy for ISOLDE hall crane!
Magnetic shielding design Jérémie Bauche, Kevin Buffet & Yacine Kadi (CERN)
ISS Mechanical Design Target & detector drive systems Hexagonal Si tube ~50 cm long 4 DSSDs per face ASIC readout Cooled
ISS Si detector module 6 R3B ASICs 0 – 50 MeV 128 channels 100 MHz time stamp daisy-chained
Si detectors DSSDs: 1 mm thick x: 128 × 0.95 mm y: 11 × 2 mm
132Sn(d,p) with TSR beam quality simulations by Marc Labiche
Reconstructing the z position CM Energy: Algorithm devised by P. Butler Implemented in GEANT4 by M. Labiche
Exploitation plans early exploitation before LS2 stable & long-lived isotope running during LS2 + commissioning of the ISS Si array + commissioning of gas recoil detector… followed by ISS running after LS2
Conclusions • Design work well advanced • First Si DSSDs delivered • Prototype tests under way • Magnet recommissioned • ISOLDE integration continuing