CMC ERP Project Update. January 16, 2009. Project Timeline. Analysis and Assessment Phase. Accomplishments to Date. Held University wide project kick-off – 10/24 Established project management structure and processes

loader
I am the owner, or an agent authorized to act on behalf of the owner, of the copyrighted work described.
capcha
Download Presentation

CMC ERP Project Update


An Image/Link below is provided (as is) to download presentation

Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author.While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server.


- - - - - - - - - - - - - - - - - - - - - - - - - - E N D - - - - - - - - - - - - - - - - - - - - - - - - - -
    Presentation Transcript
    1. CMC ERP Project Update January 16, 2009

    2. Project Timeline

    3. Analysis and Assessment Phase

    4. Accomplishments to Date • Held University wide project kick-off – 10/24 • Established project management structure and processes • Identified functional project team members and established schedule of team meetings • Developed and initiated project communication plan • Project website: www.mercer.edu/bear2.0

    5. Accomplishments (cont.) • Completed Business Process Analysis (BPA) sessions for • Admissions • Academic Records/Registrar • Financial Planning • Student Accounts/Bursar • University Development and Alumni • Finance • HR/Payroll

    6. Accomplishments (cont.) • Completed data analysis review for SIS to CampusVue data conversion • Completed first round of integration analysis • Setup of all Mercer hardware for Test and Production environments • Installation of CMC software in Test and Production environments

    7. Current Activities • Prepare data conversion extract files – January and February • Review Business Requirements Documents for CampusVue, Cornerstone, and Portal • Demo of Talisma CRM (Constituent Relationship Manager) – January 23rd

    8. Upcoming Activities • Receive and approve final SOW • Receive and review Vantage BRD • Finalize Vantage implementation schedule • Finalize Cornerstone implementation schedule • Revisit CampusCRM BPA with Talisma • Publish complete project schedule • Begin CampusVue configuration