1 / 25

Construction Accounting and Financial Management

Construction Accounting and Financial Management. Chapter 7 Managing Costs. Material Purchases. Purchase orders approved by project manager Supervisor has limited authority to approve small purchase orders. Materials Purchases. Materials Purchases. Labor Costs. Hard to control

darius
Download Presentation

Construction Accounting and Financial Management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Construction Accounting and Financial Management Chapter 7Managing Costs

  2. Material Purchases • Purchase orders approved by project manager • Supervisor has limited authority to approve small purchase orders

  3. Materials Purchases

  4. Materials Purchases

  5. Labor Costs • Hard to control • Tracked by timecards • Must be processed quickly

  6. Labor Costs

  7. Subcontracts • Often requires progress payments • Hard to determine percent complete

  8. Subcontracts

  9. Subcontracts

  10. Equipment • Hard to control • Controlled like labor • Use equipment time cards • Be sure equipment is returned as soon as the project is done with it

  11. Other Costs • Where possible, use purchase orders • When a purchase order has not been used, approval by project manager is required • For example, for utility bills

  12. General Overhead Costs • Must be managed as aggressively as construction costs

  13. Job Profitability • Update weekly • Cost to complete • Estimated cost at completion • Estimated profit • Include committed costs even if not tracked in the accounting system

  14. Cost Loaded Schedule • Prepare schedule • Assign cost to the tasks • Determine the weekly or monthly costs

  15. Earned Value • Measures performance with regards to • Schedule • Cost • Ignores items which do not have a cost • For example, submittals

  16. Budgeted Cost of Work Scheduled(BCWS) • The expected cost of the work that is scheduled to be performed during a specific period of time

  17. Budgeted Cost of Work Performed(BCWP) • The expected cost of the work that is actually performed during a specific period of time

  18. Actual Cost of Work Performed(ACWP) • The actual cost of the work that is performed during a specific period of time • Hard to calculate in a timely matter because of lag in receiving and processing invoices

  19. Schedule Performance Index (SPI) • SPI = BCWP/BCWS • Measures progress of work • Results >1 : Ahead of schedule=1 : On schedule<1 : Behind schedule

  20. Cost Performance Index (CPI) • CPI = BCWP/ACWS • Measures control of budget • Results >1 : Under budget=1 : On budget<1 : Over budget

  21. Labor Cost Performance Index (LCPI) • Same as CPI except it only looks only at in-house labor • LCPI = BCLP/ACWP • BCLP = budgeted cost of labor performed • ACLP = actual cost of work performed • Measures control of in-house labor costs

  22. Labor Cost Performance Index (LCPI) • Results >1 : Under budget=1 : On budget<1 : Over budget

  23. Total Estimate Cost at Completion • TEC at C = Total Estimate/CPI • Assumes CPI will not change

  24. SPI/CPI Target levels

  25. Project Closeout Audit • Validate data • Find areas where performance was better than expected • Learn how to repeat it • Find areas where performance was worse than expected • Learn how to avoid it

More Related