The Featherstone Rovers RLFC Stadium redevelopment project has been a significant endeavor with key milestones outlined from its inception. Site works commenced in July 2011, followed by hardware arrivals starting in August 2011. The planning submission occurred in September 2011, with approval granted by the end of December 2011. By early 2012, work officially began on-site, marking a new chapter for the club and its facilities. This timeline illustrates the strategic planning and dedicated effort involved in enhancing the stadium for fans and the community.
E N D
Featherstone Rovers RLFC Stadium Redevelopment Timeline Scarborough Site works commence July ‘11 Hardware starts to arrive at August ‘11 Submit Planning, Sept ‘11 Planning approved, End Dec ‘11 Scarborough Site Works Complete Sept ‘11 Work begins on Site Early 2012